Conventional Facilities Status LCLS Conventional Facilities Introduction Key Elements Staff Schedule Construction Status Remaining Issues
LCLS Installation and Commissioning Time-Line Install Undulators First Light in FEH LTU/Und Install FEE/NEH Install First Light in FEE X-Rays in NEH FEH Hutch BO CD-4 (7/31/2010) PEP-II run ends now J F M A M J J A A S O N D D J F M A M J J A S O N D D J F M A M J J 2008 2009 2010 Down Down? PPS LTU/Und Comm. NEH Ops & Commissioning Linac/BC2 Commissioning Re-establish e- to SL2 FEL/FEE Commissioning Nov. 3, 2008
Substantial Completion Dates Central Utility Plant NOV 08 Undulator Hall NOV 08 Beam TransferNOV 08 Near Experimental Hall NOV 08 Beam Dump NOV 08 Front End Enclosure NOV 08 Xray/Diagnostics NOV 08 Far Experimental Hall NOV 08
Equipment Testing Reports Equipment Warranties Equipment Testing Reports Mark up Drawings and Specifications Subcontractor Financial Records Final Acceptance Records
Status e-beam System (thru e–DUMP) TCCo —> LCLS CF Status e-beam System (thru e–DUMP) Install. compl. Dwgs of Record Commiss. Test reports Final Punch List Final acceptance CF Recip. Building/Housing shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz AC Pwr √ Sevilla Ch. W. Baclit/Sevilla Hot W. LCW HVAC C. Air Fire Systems 31-Oct-08 Sump 30-Nov Radio Phones Magnets Vacuum Mag. Power spl Controls
Beam Transport Hall
Undulator Hall
Electron Beam Dump Area
Access Tunnel
20 ITEMS REMAINING
CF Construction Organization
Summary Substantial Completion has been achieved. Punch list items are currently being addressed. Installation tasks were successfully supported with Beneficial Occupancy and logistics under CF direction. All systems accepted and ready for transfer to installation or laboratory service groups. Plans are in place for the beam commissioning program.
End of presentation