Conventional Facilities Status

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Jess Albino CF – Breakout Session June 17, Facility Advisory Committee LINAC Coherent Light Source Project Conventional.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
David Saenz CM/GC April 8, 2005 CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
David Saenz Far Experimental Hall - June 17, Far Experimental Hall - Hutches Scope Budget Schedule.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Jess Albino / David Saenz / Facility Advisory Committee October 30, 2007 FACILITY.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
Javier A. Sevilla CF Commissioning Plan-FAC June 17, CF LCLS Commissioning Plan Javier A. Sevilla Engineering Group.
1 Jess Albino 1 Conventional Facilities Status FAC Review – Breakout Session CONVENTIONAL FACILITIES STATUS Jess Albino – Associate.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
John Arthur X-Ray Endstation April 29, 2004 X-Ray Endstations Overview John Arthur.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
Hal Tompkins Photon October 30, LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
LUSI Coordination with LCLS
Experimental Facilities Planning
Potential Use of PEP-II Magnets by Project X
Undulator System Installation
CF Organization & Schedule
LTU/Undulator Installation Status
Meeting of the LCLS Facilities Advisory Committee
Linac Ops Budget Review LCLS Overview / Org Structure / Legacies
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
e-Beams Systems Update
CONVENTIONAL FACILITIES STATUS
Electron Beam Systems ETC and Methodology
John N. Galayda – Director, LCLS Construction May 13, 2009
Department Of Energy Review LINAC Coherent Light Source Project
X-Ray Endstations Update
Far Experimental Hall - Hutches
Project Status Review May 13-15, 2008.
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
FEE Diagnostics and Commissioning
PIXEL Project Status John Arthur Photon Instrumentation for
Shutdown Planning & Installation Schedule
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LTU/Undulator Installation Status
CONVENTIONAL FACILITIES
DOE Review 7-9 February, 2006 Steve Lewis
LCLS Operation in 2009 Roger A. Erickson
Linac Coherent Light Source Transition to Operations 11 July 2007
Installation Status & Operational Readiness Process
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Phase 1 Statement of Work Preconstruction “Plan The Work”
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
CF Scope, Management & Organization
X-Ray Endstation Systems (XES) 2006 Schedule
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
Presentation transcript:

Conventional Facilities Status LCLS Conventional Facilities Introduction Key Elements Staff Schedule Construction Status Remaining Issues

LCLS Installation and Commissioning Time-Line Install Undulators First Light in FEH LTU/Und Install FEE/NEH Install First Light in FEE X-Rays in NEH FEH Hutch BO CD-4 (7/31/2010) PEP-II run ends now J F M A M J J A A S O N D D J F M A M J J A S O N D D J F M A M J J 2008 2009 2010 Down Down? PPS LTU/Und Comm. NEH Ops & Commissioning Linac/BC2 Commissioning Re-establish e- to SL2 FEL/FEE Commissioning Nov. 3, 2008

Substantial Completion Dates Central Utility Plant NOV 08 Undulator Hall NOV 08 Beam TransferNOV 08 Near Experimental Hall NOV 08 Beam Dump NOV 08 Front End Enclosure NOV 08 Xray/Diagnostics NOV 08 Far Experimental Hall NOV 08

Equipment Testing Reports Equipment Warranties Equipment Testing Reports Mark up Drawings and Specifications Subcontractor Financial Records Final Acceptance Records

Status e-beam System (thru e–DUMP) TCCo —> LCLS CF Status e-beam System (thru e–DUMP) Install. compl. Dwgs of Record Commiss. Test reports Final Punch List Final acceptance CF Recip. Building/Housing   shop dwgs n/a 15-Nov-08 30-Nov-08 Saenz AC Pwr √ Sevilla Ch. W. Baclit/Sevilla Hot W. LCW HVAC C. Air Fire Systems 31-Oct-08 Sump 30-Nov Radio Phones Magnets Vacuum Mag. Power spl Controls

Beam Transport Hall

Undulator Hall

Electron Beam Dump Area

Access Tunnel

20 ITEMS REMAINING

CF Construction Organization

Summary Substantial Completion has been achieved. Punch list items are currently being addressed. Installation tasks were successfully supported with Beneficial Occupancy and logistics under CF direction. All systems accepted and ready for transfer to installation or laboratory service groups. Plans are in place for the beam commissioning program.

End of presentation