Richard M. Boyce FAC April 16, 2007 1 LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Nov. 19, 2008 ILC08 Global Design Effort 1 Status Report Alternative Siting and Tunnel Design Tom Lackowski.
Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project LCLS NEH ARR John Arthur LCLS Experimental Facilities Division August 11, 2009 Welcome.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
Javier A. Sevilla Interface & Configuration FAC Review April 16, Interface and Configuration Management Outline CF.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
Kathleen Ratcliffe LTU Installation October 30, LTU Installation Coordination Kathleen Ratcliffe.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Jose Chan FAC - BC2/Linac Installation Status & 4/16/07 1 BC2/Linac Installation Status & Schedule Jose Chan.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
Process Engineer’s Role in Project Management Dr Abdullah Malik.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Javier A. Sevilla Interface & Configuration FAC Review October 12, Interface and Configuration Management Outline.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
ASTA Accelerator Directorate Review Project Plan and ES&H Carsten Hast May 20, 2014.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
Details on the Accelerator Installation Plan E. Sargsyan & L. Lari 20 April 2016.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
Accelerator Readiness Review October 31, 2006
Installation Global System
Experimental Facilities Planning
X-ray Pump-Probe Instrument
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LTU/Undulator Installation Status
Meeting of the LCLS Facilities Advisory Committee
e-Beams Systems Update
CONVENTIONAL FACILITIES STATUS
Electron Beam Systems ETC and Methodology
Project Status Review May 13-15, 2008.
Integrated Safety and Environmental Management
Conventional Facilities Status
Shutdown Planning & Installation Schedule
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LTU/Undulator Installation Status
Linac Coherent Light Source Transition to Operations 11 July 2007
Installation Status & Operational Readiness Process
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Undulator Alignment Plan
CF Scope, Management & Organization
e-Beams Systems Update
BC2 / Linac Installation Coordination Kathleen Ratcliffe
LINAC System Engineering / Design Status C.E. Rago
DOE Status Meeting of the LCLS Project
LCLS e- Beams Systems Manager
Presentation transcript:

Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH -> NEH 2008 Installation Planning

Richard M. Boyce FAC April 16, Integration Management Team Overview IMT Organization Integration Area managers are points of contact for changes and schedules Changes are documented in a Design Change Request (DCR) form Signatures from Integration Area Managers and System Managers assures acknowledgement and communication across systems Project Office final approval – assures funding path is known and approved DCR to CF provides clear direction that action on change is approved and can begin CCB to be submitted by group performing work APD Conventional Facilities (Jess Albino) APD Engineering (Tom Fornek)

Richard M. Boyce FAC April 16, System Design/Construction Integration Integration Management process Integration Management Team Established core team to ensure systems wide communication Review and approve change requests to CF from technical groups Review IFC drawings for technical requirements and compatibility Review installation plans and provide input on integration activities Document change requests that are cross divisional (affecting more than one system) Processes A Design Change Request, once approved, gets turned into a BCR by group doing work Technical requirement documents (ESD, PRD, RDS, ICD) are tracked by the QA Manager

Richard M. Boyce FAC April 16, Integration Management Team IMT Design Topics and Issues DCRs complete Service Building Power: IMT-DCR (Controls-CF) Offset Mirror support pad relocation: IMT-DCR (XTOD/XES-CF) Electron Beam dump: IMT-DCR (Linac-CF) NEH Concrete Wall Penetrations: IMT-DCR (XTOD/XES-CF)NEH Concrete Wall Penetrations: IMT-DCR BTH West Room Data Sheets (RDS) (CF-all) DCRs in process FEE Electrical Alcove: IMT-DCR (XTOD/XES-CF) NEH Floor Plan Re-design (XTOD/XES-CF) LCW for LTU (PM/Linac-CF) Issues being worked PPS requirements for CF (lighting controls, AC power, HVAC/ventilation controls, etc) Concrete floor stability wrt support structure anchor installations

Richard M. Boyce FAC April 16, Integration Management Team Systems Integration IMT will assist in overall integration of activities Involved in installation scheduling Knowledgeable of CF schedule and Technical components Important to understand relationships between systems to avoid “items” falling through the cracks Important to have communication between systems to ensure “items” have responsible owners and get scheduled Key individuals as points of contact; heavily involved in their areas of responsibility

Richard M. Boyce FAC April 16, Installation Planning 2006 Installation is complete, last meeting held on 4/3/07 ~550 line schedule covering all activities 2007 SLAC Shutdown SLAC downtime – September, October, November 2007 Assuming 2 weeks for PPS in Nov 2007 Installation Planning Installation through BC2 & all cable plant; including cables through the BSY into the BTH West Will develop Integrated schedule using P3 Will use SLAC Schedule process for resource loading Installation risk is tracked in Risk Registry; handling plan being worked 2008 Installation Planning LCLS installations begin at Early Occupancy dates defined by TCCo Draft 2008 Installation schedule used to begin detailed planning & integration process Staggered Early Occupancy dates Will use P3 for detailed install schedule Installation Organization Chart in development Key individuals being identified Meetings to be held weekly

Richard M. Boyce FAC April 16,

Richard M. Boyce FAC April 16, SLAC/LCLS 2007 Downtime Schedule – sample SLAC Downtime Schedule Controlled by Area Managers Tasks show SLAC resources LCLS is one part of the downtime schedule Weekly meetings to review schedule and site outages LCLS Downtime meetings Weekly meetings held by various groups plus weekly integration meeting Interfacing with SLAC groups on a routine basis SLAC Downtime Schedule format will be used for LCLS 2007 Linac area Installations Needed to coordinate resources and accelerator turn on dates

Richard M. Boyce FAC April 16, Installation Planning A 2007 Installation Schedule Readiness Review was held on March 16 - report determined that: Integrated schedule is needed; amount of work shown by independent schedules does not match downtime duration and conflict with each other Controls schedule does not match component installation schedule Detailed plans are needed to track component fabrication and processing to ensure RFI dates are held Clear scope definition needed for downtime work to avoid unplanned activities being added late in the down Majority of system will be ready for the down; just need to fit into the timeline Consideration is being given to defining early March 2008 as the start of BC2 commissioning Allows time for Controls integration and testing over a longer duration, but will require ROD periods which are an impact on PEPII Allows 6 months BC2 commissioning time Detailed schedule being developed in P3 Integration of individual system schedules 2007 Installation Planning

Richard M. Boyce FAC April 16, Installation Planning LCLS installations begin at Early Occupancy dates defined by TCCo Draft RMB 2008 Installation schedule used to begin detailed planning & integration process Staggered Early Occupancy dates Planned sequence of work Metrology Core drilling Stand installation Cable installation Component installation Cable termination Testing & Checkouts Will use P3 for detailed install schedule 2008 Installation Schedule Readiness Review in early May

Richard M. Boyce FAC April 16, LCLS Installation Schedule 1 - DRAFT 2008 High Level Planning Schedule Staggered Early Occupancy dates BTH West through Far Hall areas Major subcontracts used for installations Supports Electrical Concrete drilling Etc

Richard M. Boyce FAC April 16, LCLS Installation Schedule 2 - DRAFT 2008 High Level Planning Schedule Detailed integrated schedule required below each major heading Planning will be done to pull in schedule 10 hr days double shifts Etc

Richard M. Boyce FAC April 16, LCLS Installation Schedule 3 - DRAFT 2008 High Level Planning Schedule No delays in Early Occupancy dates yield a ready to commission into NEH by early October 2008 Note: X-ray & FEH dates do not yet reflect CR impact and will slide accordingly

Richard M. Boyce FAC April 16, Summary 2007 Installation Planning 2007 SLAC downtime to install Linac hardware Use P3 integrated schedule to cover all activities Need to continue to use SLAC format for resources 2008 Installation Planning Installation schedule will use detailed P3 schedule with hourly task durations Early occupancy of Conventional Facilities will begin installation process for technical systems Does not require Linac/PEPII down for LCLS installations Need to coordinate several subcontracts (~6-10?) to install mechanical systems and cable plant simultaneously Starting process now – Integration of overall plan is a must to be successful and meet schedule 2008 Install Schedule Readiness Review to be held in early May Installation/Commissioning Timeline to CD-4a - DRAFT Draft version based on RMB 2008 install schedule Still needs to be reviewed and approved by management Will be scrubbed after 2008 IRR

Richard M. Boyce FAC April 16, LCLS Installation Time-Line April 11, 2007 rmb DRAFT AASSOONNDDJJFFMMAAMMJJJJAASSOONNDDJJFFMMAAMMJJJJ BTH/LTUInstall CF Early Occupancy First Spont. Light AASS CD-4a OONNDDJJFFMM PPS linac/BC2 Install Und/DumpInstall FEE/NEH Install LCLS PPS Certification Linac PPS re-certification & Linac/LCLS/NEH global certification Facility work requiring downtime??? Electrons through Undulator BTH-NEH B.O. X-Ray/FEH B.O.

Richard M. Boyce FAC April 16, LCLS Installation and Commissioning Time-Line April 11, 2007 rmb DRAFT AASSOONNDDJJFFMMAAMMJJJJAASSOONNDDJJFFMMAAMMJJJJ Drive- Laser Installed Drive-Laser Commissioning Gun/Inj/BC1 Commissioning Gun/Inj./BC1 Install linac/BC2 Install Linac/BC2 Commissioning LTU/Und/Dump FEE/NEH Install LTU/und. hall “ready” ControlsCheckout LTU/und. Commissioning First Spont. Light AASS CD-4a OONNDDJJFFMM PPS Controls checkout Checkouts

Richard M. Boyce FAC April 16, End of Presentation