FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.

Similar presentations


Presentation on theme: "FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System."— Presentation transcript:

1 FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System development advancing. Undulator System In production.

2 FAC review, 10/27 D. Schultz 2 Drive laser transport tube installed 10/14: The first piece of installed LCLS beamline. The ceiling in the injector vault Injector System Installation Laser bldg. construction

3 FAC review, 10/27 D. Schultz 3 SLAC linac tunnelresearch yard Linac-1 L  9 m Linac-2 L  330 m Linac-3 L  550 m BC-1 L  6 m BC-2 L  22 m LTU L =275 m undulator 135 MeV 250 MeV 4.54 GeV14.1 GeV Linac-X L =0.6 m 21-3b 24-6d 25-1a 30-8c Linac-0 L =6 m 6 MeV L0-A,B rf gun X T-Cav Installation Schedule Dump Injector, 2006 down Spect. 21-1b 21-1d Linac, 2007 down ‘Wall Region’

4 FAC review, 10/27 D. Schultz 4 Laser System April 2006 Gun Region Nov. 2006 through Heater Region March 2006 Wall Region October 2005 Injection Region August 2006 Spectrometer Region through BC1 August 2006 Waveguide through wall and up penetration October 2005 Injector System Installation

5 FAC review, 10/27 D. Schultz 5 Current Injector Installation Installed Injector beamline, to mate to spring install schedule.

6 FAC review, 10/27 D. Schultz 6 Injector Installation Access to the Injector vault. Laser facility construction through 2/06 Install Injector in the vault 3/06-11/06 Aug.- Nov. 2006 down Install to end of Injector spectrometer Install Linac to Bunch Compressor 1 dump PPS connection to SLAC Linac & certification

7 FAC review, 10/27 D. Schultz 7 Injector Commissioning Commission drive laser 4/06-11/06 Needs laser safety system certification Coordinate with Injector installation in vault Dec. 2006 to Aug. 2007 Commission electron beam through Injector and BC1 Occurs during B-factory operations. Need Injector SAD, ARR 11/06

8 FAC review, 10/27 D. Schultz 8 Injector System Status Drive laser is ordered. Gun in detailing L0A, L0B are in fabrication. Laser tables on order Magnets are on order Vacuum hardware in hand, Special chambers in design Floor, supports, finishing design Schedule remains critical for these systems.

9 FAC review, 10/27 D. Schultz 9 BC1 articulation is with a vendor with vacuum system Magnets through BC1 are on order X-band system designed X-band structure in hand New klystron fabricated, to test Linac-1 design complete, parts on order BPMs design modification Linac System

10 FAC review, 10/27 D. Schultz 10 Controls SLC-aware IOC is complete In test with SLC applications Magnet power system for the ’06 installation, Supplies in purchasing/ordered Cable plant defined and in design Still investigating new designs for Linac and Und. Redundancy, Imbedded IOC controllers PLC based PPS system for Injector in preparation for SLAC approval.

11 FAC review, 10/27 D. Schultz 11 Controls LLRF system conceptual design review was held Significant issues were raised Design and reviews will continue Vacuum system well defined System hardware design review, Electrical safety review Timing system is in test Event Generator and the Event Receiver boards are being interfaced Work on high level applications has started In coordination with the LCLS Commissioning/Operations Working Group Controls group leader, interviews held, offer soon

12 FAC review, 10/27 D. Schultz 12 1st article Ti undulator strongback machined. Mechanical tolerance met and bettered. Undulator System 1 st article undulator strongback. 3 other units in rough machining at 2 vendors. Poles and magnet blocks in fabrication – on schedule Assembly contracts placed, 2 vendors, at favorable costs.

13 FAC review, 10/27 D. Schultz 13 Undulator support girder preliminary design Good temperature stability Cam mover motion/reproducibility studies well along Cavity BPM system development Scope moved to APS Install 4/06 for beam tests @ APS WP system is under study at SLAC Resolution & drift < 100nm/day Undulator System

14 FAC review, 10/27 D. Schultz 14 Vacuum system Al on SS prototypes under study BFW system under design New scope Well under way LCLS Undulator Alignment and Motion Review 10/20-21 Addressed undulator fiducialization and measurement See Heinz-Dieter Nuhn’s talk Undulator System

15 FAC review, 10/27 D. Schultz 15 1 st article finished undulator due at SLAC 5/12/06 2 nd Article due 6/12/06 MMF facility under construction, b.o. 2/06 Major equipment on order Undulator girder assembly area identified SLAC building 750 Undulator System

16 FAC review, 10/27 D. Schultz 16 Undulator hall: Baseline from JE was overpriced. Able to loosen tolerances, redesign for lower cost. Temperature stability ±0.2°C  ±1°F Support structure stability design study at ANL k variations sets the tolerance Diagnostic cable length is also a concern 150k CFM conditioned air  20k CFM Need to validate the ability of the design to meet the tolerances. Undulator System

17 FAC review, 10/27 D. Schultz 17 We’re going to be busy in 2006 Injector installation Laser commissioning Aug.-Nov. ’06 downtime preparations Undulator girder assembly and measurement FFBT removal in preparation for BTH const. preserve hardware for LCLS Linac use. Conclusion