Shutdown Planning & Installation Schedule

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
Javier A. Sevilla Interface & Configuration FAC Review April 16, Interface and Configuration Management Outline CF.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
Kathleen Ratcliffe LTU Installation October 30, LTU Installation Coordination Kathleen Ratcliffe.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Hal Tompkins Photon October 30, LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
LUSI Coordination with LCLS
Experimental Facilities Planning
Maintain a single control room for all accelerator programs
Undulator System Installation
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LTU/Undulator Installation Status
Meeting of the LCLS Facilities Advisory Committee
Far Experimental Hall Hutches Civil Construction
Far Experimental Hall Hutches Civil Construction
e-Beams Systems Update
CONVENTIONAL FACILITIES STATUS
Installation of Photon Beam Transport to FEH
Electron Beam Systems ETC and Methodology
X-Ray Endstations Update
Details supporting the increase
DOE Review of the LCLS Project
Far Experimental Hall - Hutches
Project Status Review May 13-15, 2008.
Integrated Safety and Environmental Management
FEE Diagnostics and Commissioning
LCLS Undulator System Production Management
2007 Downtime Controls Installation
Conventional Facilities Status
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LTU/Undulator Installation Status
LCLS Undulator System Status and Schedule
CONVENTIONAL FACILITIES
Control System Overview Hamid Shoaee LCLS Control System Manager
LCLS Operation in 2009 Roger A. Erickson
Linac Coherent Light Source Transition to Operations 11 July 2007
Installation Status & Operational Readiness Process
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Electron Beam Systems ETC and Methodology
Undulator Alignment Plan
CF Scope, Management & Organization
e-Beams Systems Update
BC2 / Linac Installation Coordination Kathleen Ratcliffe
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS Undulator Scope, Management, Organization
DOE Status Meeting of the LCLS Project
LCLS e- Beams Systems Manager
Presentation transcript:

Shutdown Planning & Installation Schedule Integration process – IMT update Installation Planning & Schedules 2007 Installations BTH -> FEH 2008 Installation

Integration Management Team Overview IMT Organization Integration Area managers are points of contact for changes and schedules Changes are documented in a Design Change Request (DCR) form Signatures from Integration Area Managers and System Managers assures acknowledgement and communication across systems Project Office final approval – assures funding path is known and approved DCR to CF provides clear direction that action on change is approved and can begin CCB to be submitted by group performing work APD Conventional Facilities (Jess Albino) APD Engineering (Tom Fornek)

System Design/Construction Integration Integration Management process Integration Management Team Established core team to ensure systems wide communication Review and approve change requests to CF from technical groups Review IFC drawings for technical requirements and compatibility Review installation plans and provide input on integration activities Document change requests that are cross divisional (affecting more than one system) Processes A Design Change Request, once approved, gets turned into a BCR by group doing work Technical requirement documents (ESD, PRD, RDS, ICD) are tracked by the QA Manager

Integration Management Team IMT Design Topics and Issues to date DCRs complete & approved Service Building Power: IMT-DCR-1006-01 (Controls-CF) Offset Mirror support pad relocation: IMT-DCR-1006-02 (XTOD/XES-CF) Electron Beam dump: IMT-DCR-1106-01 (Linac-CF) NEH Concrete Wall Penetrations: IMT-DCR-0207-01 (XTOD/XES-CF) Beam Dump Crane: IMT-DCR-0507-02 NEH Hutch cable trays: IMT-DCR-0607-01 DCRs in process FEE Electrical Alcove: IMT-DCR-0307-01 (XTOD/XES-CF) LCW for LTU: IMT-DCR-0507-02 (PM/Linac-CF) Issues being worked PPS requirements for CF (lighting controls, AC power, HVAC/ventilation controls, etc) The process is working well and continues with weekly meetings

Shutdown Planning & Installation Schedule Installation Planning & Schedules Install org chart & planning 2007 Installations

* Denotes IMT member

Installation Planning 2007 SLAC Shutdown SLAC downtime – September, October, November 2007 Assuming 2 weeks for PPS in Nov 2007 Installation Planning Installation through BC2 & all cable plant; including cables through the BSY into the BTH West Will develop Integrated schedule using P3 after iterations in MSProject and SLAC downtime schedule input Will use SLAC Schedule process for SLAC resource loading 2008 Installation Planning LCLS installations begin at Early Occupancy dates defined by TCCo 2008 Installation schedule developed to begin detailed planning & integration process Early Co-Occupancy dates being defined Will follow on 2007 Installation learning curve and use P3 for detailed install schedule (shift work, multiple calendars, etc) Schedule shows Cable Plant rack Installation starting as early as December 2007

2007 Installation Planning A 2007 Installation Schedule Readiness Review was held on March 16 - report determined that: Integrated schedule is needed; amount of work shown by independent schedules does not match downtime duration and conflict with each other Majority of system will be ready for the down; just need to fit into the timeline Detailed schedule being developed in MS Project Integration of individual system schedules Weekly LCLS Installation meetings held Weekly SLAC Downtime meetings held SLAC Directors Readiness Review held on May 16 – report confirmed the LCLS plan and schedule is sound and will maintain the downtime dates as published LCLS is major focus of downtime, confirms laboratory support

2007 Installation Schedule LCLS 2007 Installation schedule includes: Facilities Work Sector 21 – 30 electrical BTH West MEP & LCW Cable Plant Sector 24 – 30 I&C and DC cables for BC2 BSY Work Cables from B005, B105, B106, B136 into BTH West BPM S21 to BSY Mechanical/Vacuum Sector 24 – 29 removal and installations of BC2 & L3 Controls BCS; BC2 Magnet controls; Vacuum System; BC2 Timing System; BC2 MPS; BC2 Networks; BC2 Motion Control System

2007 Installation Schedule (cont) LCLS 2007 Installation schedule, as of 6/22/07, contains 520 task lines Shift work and multiple crews being used for Mech/Vac; shift work in schedule for Cable Plant work during PPS no access periods Critical Path As of 6/22/07, CP runs through BC2 Removal of hardware - Cable plant and component install – cable terminations – cable testing; complete 11/9/07 Magnet testing & checkouts follow through end of downtime

2007 Installation Schedule (cont) LCLS 2007 Installation schedule 6/22/07 BSY Work (for example) Cable Plant from B005, B105, B106, B136 into BTH West Requires Downtime (obviously) to install cables, therefore needed in 2007 down. Magnet loads not installed until ~March 2008, but need to checkout & commission before next downtime Cable plant (Controls) install needs to be coordinated with BTH West MEP (LCLS CF)

BSY Work – B005 to BTH West Cable run from B005 through the BSY, into BTH West via ~12 small penetrations B005

2007 Installation Schedule (cont) Continue to plan downtime requirements Systems checks & balances RSWCF for linac & cable way penetrations ES&H review of SOW’s Subcontractor installations Appropriate training Work authorization forms (WAF) AD & LCLS forms RWP Electrical safety for cable plant install & connection to PS PO lockdown procedure being considered

Shutdown Planning & Installation Schedule Installation Planning & Schedules BTH -> FEH 2008 Installation

2008 Installation Planning LCLS installations begin at Early Occupancy dates defined by TCCo BTH, Undulator Hall & Service Buildings available as early as December 5, 2007; NEH 12/21/07; X-ray tunnel 1/8/08; FEH 3/24/08; SB 2.3 late December TCCo has priority over co-occupied space until B.O. BTH-NEH B.O. 3/21/08; X-ray tunnel – FEH B.O. 6/23/08 Subcontract SOWs are being prepared Need to ensure this work does not impact the 2007 installation effort

2008 LCLS Installation Schedule 1 of 5 Co-Occupancy dates defined Major subcontracts used for installations - Electrical needs to be ready at Early Occupancy dates of service buildings First activity is Metrology network installation 2007 Downtime LTU components connect to cables installed through BSY in 2007 downtime

East Maze – Undulator entry point LTU Hardware contained inside BTH West and BTH Entry areas are East & West mazes, and openings at headhouse Will plan access areas to limit interferences with Undulator and LTU installation phases West Maze entry point Headhouse entry East Maze – Undulator entry point BTH West tunnel Undulator Hall

2008 LCLS Installation Schedule 2 of 5 Undulator girder installation, testing and checkouts are on critical path FEE component installation

LCLS UNDULATOR SYSTEM 33 rf Beam Position Monitors 33 Beam Finder Wires Wire Position Monitor Hydro static level system 33 Undulators 33 Quadrupoles/Correctors EM air-cooled 10 Long breaks 22 Short Breaks Supports with movers 5 DOF plus horizontal slider Vacuum System interconnects

LCLS 2008 Installation schedule FEE systems are well along in the planning stages

2008 LCLS Installation Schedule 3 of 5 X-Ray tunnel and FEH installation delayed until FY2009

LCLS 2008 Installation schedule NEH overview NEH Hutches

2008 LCLS Installation Schedule 4 of 5 Systems ready for first electron beam into dump by 12/8/08 2008 Downtime duration may impact initial startup 2008 Downtime

2008 LCLS Installation Schedule 5 of 5 2009 Downtime Commissioning activities leading to CD-4a and CD-4b

Summary 2007 Installation Planning 2008 Installation Planning Continue to use SLAC format for SLAC resource loading Continuing to ‘squeeze’ schedule to fit within 3 month time frame 2008 Installation Planning Early occupancy of Conventional Facilities will begin the installation process for technical systems Does not require Linac/PEPII down for LCLS installations BTH West install will require ‘50B1 ON’ state which prevents ESA and SABER beams from operation Need to coordinate several subcontracts (~6-10?) to install mechanical systems and cable plant simultaneously Installation/Commissioning Timeline to CD-4a - DRAFT Draft version based on 2008 install schedule

LCLS Installation and Commissioning Time-Line June 21, 2007 rmb DRAFT X-Ray/FEH Install X-Rays in FEH LTU/Und/Dump FEE/NEH Install First Spont. Light CF Early Occupancy X-Ray Systems Checkout - Commission e- beam & Photon Systems Checkout CD-4b CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M 2007 2008 2009 PPS PPS 2010 Photon Flux Measurements Controls checkout Re-commission Inj/BC2 to SL2 X-Ray Operations LTU/Und/FEE Commissioning Linac/BC2 Commissioning NEH Commissioning & experiments linac/BC2 Install FEL Commissioning

End of Presentation