Presentation is loading. Please wait.

Presentation is loading. Please wait.

2007 Downtime Controls Installation

Similar presentations


Presentation on theme: "2007 Downtime Controls Installation"— Presentation transcript:

1 2007 Downtime Controls Installation
Agenda Objectives & Scope Schedule & the Process Cable Plant, racks and other infrastructure I&C Systems status and schedule Issues & Concerns

2 Controls Installation for Linac, BC2 & beyond...
X-Ray tunnel/FEH Install LTU/Und/Dump FEE/NEH Install CF Early Occupancy e- beam & Photon Systems Checkout CD-4b CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M 2007 2008 2009 PPS 2010 PPS Controls checkout LTU/Und/FEE Commissioning Linac/BC2 Commissioning linac/BC2 Install FEL Commissioning

3 LCLS Accelerator Regions
6 MeV 135 MeV 250 MeV 4.30 GeV 13.6 GeV Linac-0 L =6 m Linac-X L =0.6 m rf gun L0-a,b Linac-1 L 9 m Linac-2 L 330 m Linac-3 L 550 m 25-1a 30-8c ...existing linac 21-3b 24-6d 21-1 b,c,d X undulator L =130 m BC2 L 22 m BC1 L 6 m ‘Wall region’ DL2 L =275 m Commission now 2007 down, Sept-Nov Nov. 1, ’07 SLAC linac tunnel research yard Down: Sep., Oct., Nov. of 2007 Run: Dec through ~Aug. 2008 To: SL2-stopper in BSY (just past linac sector-30)

4 Modifications in Sector-24 for BC2 (Emma)
Remove 8 RF sections (24-7, 8) Remove quad Q24801 Add 4 new bends in sector-24 Add 6 new quads (3 types) Add 1 ‘wide’ BPM Add 1 x-collimator Add 1 OTR screen

5 Linac Modifications (Fall ‘07)
Remove 8 RF sections (24-7, 8) Remove quad Q24801 Add 4 new bends in sector-24 Add 6 new quads (3 types) Add 1 ‘wide’ BPM Add 1 x-collimator Add 1 OTR screen

6 Linac Modifications (continued)
Add 3 OTR screens (1 BC1, 2 in sec-25) Move LOLA (trans. deflector) from sec-29 to 25-2 (powered by the 24-8 klystron) Add pulsed horizontal dipole magnet in sec-25 (BXKIK) Move 2 LI28 Wire Scanners, 44 & 544, by meters BPM electronics upgraded (resolution improved) More feedback loops (energy & bunch length)

7 Linac Modifications (continued)
Power Systems BC2 racks & PS (install racks and PS at sector 24) I&C Systems I&C racks and systems (install racks at sector 24) Cable Plant Sector 24 ( install new trays and cable plant from sector 24 racks into Linac; terminate at racks and at loads) BTH West (pull cables from B005, 105, 106 through BSY into BTH West and coil cables; no loads & no racks installed yet) B136 through BSY to BTH West Remove cut cables from FFTB

8 Plans & Process for BC2 Controls System Installation
Controls installation takes place in several steps: Design, procurement and Installation of the cable plant including trays, long haul DC and I&C cables Cables Termination and connection to beam line components (Mechanical Systems) Procurement & preparation of electronics racks Installation of electronics chassis and modules including crates, IOCs, timing modules in the racks Rack installation in the field, AC & cable plant connection

9 Linac & BC2 Controls Installation Schedule Controls ready 12/3/2007

10 Cable Plant Design & Installation Process
From the list of devices to be installed… Develop racks layout & cable tray design Generate rack profiles for electronics modules Identify DC & I&C cabling requirements & document in CAPTAR Produce installation bid package from CAPTAR and tray designs Generate installation bid package & award contract Procure trays, cables, connectors, etc. Install cable plant and terminate to beam line components

11

12

13 Typical Sector Cable List (Michael De salvo, Mario Ortega)

14 Sector 24 Connector List 13k feet $245k (cable) $10k (connectors)
First draft BC2 cable design 13k feet $245k (cable) $10k (connectors)

15

16 Racks will be pre-loaded in B24 before field installation

17 BC2 Controls Sub-Systems
Cable plant Racks, crates, IOC, etc. Networks Magnet power supply control Vacuum control Safety systems PPS, MPS, BCS Motion control Wire scanners, Collimators, Chicane Timing Beam instrumentation and diagnostics BPM, Toroid, OTR/YAG, Bunch length monitor LLRF

18 LCLS Controls systems For each system…
Technical leads have developed a schedule covering all phases leading to installation and commissioning The schedules include development of appropriate field documents (EI, WD), rack profile/cable plant design, procurement, installation and system checkout Continue Interfacing with Mario Ortega, Bob Fuller, Mike DiSalvo to coordinate procurement and installation We will be reviewing each schedule to identify bottlenecks, dependencies on other systems, resource availability

19 Safety Systems for BC2,L2,L3
PPS The Linac PPS does not require modification to run LCLS beam to SL-2. There is an AIP project to convert the Linac and BSY to the LCLS PLC-based system in 2008 MPS We will use the current (1553-based) MPS for BC2. Two new ion chambers will be required The system will include 10 LDIM inputs OTR21 (2ea) OTR22 (2ea) OTR_CAV (2ea) BC2 Mover (2ea) CE21 (2ea) We will need to commission AP25 (currently installed but powered down) to accommodate a new PICP module and an LDIM (already installed).

20 BC2 MPS Schedule Check out 12/3

21 Concurrently developing new LCLS MPS
Response time of less than one pulse at 120 Hz Decoupling from Master Pattern Generator (MPG) Fast communication and processing Knowledge of beam rate Integration of EVR to MPS and fault devices New hardware extended 1.2 km past current MPS Non-CAMAC Ready for photon section

22 LCLS MPS Features Has response time low enough to protect the undulator (less than 8.3 ms) Communicates with LCLS timing system (EVG) Supports new beam loss monitoring hardware and rate limiting methods Easily extendable and is designed around standards based COTS components Flexible input and output methods

23 Overview

24 Core Hardware and Software
Completion Date Quantity Cost per Unit Digital Input Card 04/16/2007 30 700 Digital Output Card Done 4 MVME 6100 08/31/2007 27 3000 EVR 05/31/2007 1 2500 Reflective Memory 04/02/2007 25 2000 Reflective Memory Hub 5 Total 169800 Note: These are material costs only. Development labor, installation, etc. costs are not included.

25 Other MPS Devices Hardware and Software Completion Date Quantity
Beam Loss Monitors 05/01/2008 52–154 Beam Loss Monitor ADC (Argonne) 10–25 PLIC Scope Card 3

26 Milestones Task Completion Date User Interface 11/01/2007
Linac Installation BC2 Commissioning 12/03/2007 LTU-Undulator Commissioning 05/01/2008 Preliminary Design Review 04/16/2007 Final Design Review 09/03/2007 Readiness Review 10/17/2007

27 BCS (Beam Containment System)
We will use & extend the existing BCS for BC2 commissioning Two possible configurations are being considered New BCS PIC System installation in Sector-24 A 50 conductor trunk from the Sector-28 BCS rack to a new rack in Sector-24. Long hauls from Sector-24 BCS Rack to the beam line devices in Sector-24 (2 cables per PIC, 1 cable per LION, 1 cable per Flow Switch or Pressure Switch) Use BCS PIC system in Sector-28 (Depends on being able to drive PIC/LION HV and signal four sectors) Long hauls from Sector-28 to the beam line devices in Sector-24 (2 cables per PIC, 1 cable per LION, 1 cable per Flow Switch or Pressure Switch) For either configuration… Install VME Crate and associated hardware/software/network Install new LION Gas system. AC Power to Sector-28 & Sector-24 racks.

28 BC2 BCS Schedule Check out 11/23

29 Magnet Power Supply Control
The software design is mature and will require little if any changes for BC2 Procurements are well under way and orders have been placed for power supplies, racks, etc. There is a detailed schedule covering bench testing, rack loading, wiring, pre-installation checkout, through field installation The system will be ready 11/30

30 11/30/07

31 Vacuum controls uses BC1 design, with detailed procurement list in place

32 Vacuum controls check out by 11/20/07

33 Wire scanners, Collimators and BC2 motion control use the same design as BC1, and will be available 11/20/07

34 Networks will be ready early in October to allow Controls checkout

35 The system can be split into two parts
Timing System The scope is to deliver triggers and timestamp data to all subsystems requiring such. The system can be split into two parts Long-haul distribution of triggers from the EVG to EVRs in Linac and beyond Short-haul back end consisting of the HW & SW to receive the EVG timing signal and generate triggers. This is well-understood and defined. We have a procurement for the "back end" of the timing system consisting of all the HW (fan-outs, EVRs, crates, cables) to deliver triggers to the end subsystem. The long haul procurement is in progress

36 Timing System Schedule

37 Beam Instrumentation & Diagnostics
Profile Monitors There are 3 OTRs in the LINAC: OTR21, OTR22, OTR_TCAV – These use BC1 designs and electronics Design in April, procurement in May, system test July ~ August. Toroids There are two toroids in linac: IMBC2I and IMBC2O We need to re-spin the data acquisition board for small revisions to the artwork Electronics will be ready in August for system testing Bunch Length Monitor BL21 and BL22, similar to BL11 and BL12 in BC1 Procurement in April and test in May ~ June. Dumps and Stoppers SL2 might need some new data monitoring.

38 Beam Position Monitors
The linac BPMs have to be upgraded for better resolution for undulator commissioning in May-June ‘08 Do we need to upgrade for the BC2,L2,L3 commissioning? Do the existing BPM electronics work at 200 pC? Do they trigger reliably at low charge? What resolution do they provide? If we need the linac BPM upgrade Install 20 racks Design and install cable plant for 79 BPMs Re-spin BPM analog front-end design Fabricate and test 120 BPM chassis Install 79 BPM chassis If we can defer the upgrade We still have to install the cable plant for all of the linac BPMs in this down time Of the 17 BPMs in switchyard we will connect to only 2 And one BPM in BC2

39 LLRF Schedule

40 BC2 Controls Risk Matrix

41 Testing & Checkout Strategies
For each subsystem, we will use test stands to verify the complete system Test stands currently in place include: Timing Vacuum Magnet power supplies Motion control – wire scanners, collimator, etc. Rack loading & testing Need to accomplish as much as possible in B024 prior to Sept. transport to field site. In-field loading (Davis-Bacon) and intra-rack cabling is less efficient.

42 Rack Assembly Area

43 Issues & Concerns Schedule & Resources System Functionality
Schedule is very tight, just fits in down time Controls is the systems “integrator” – delays in other systems directly impact our installation Cable Plant Installation Coordination of activities with other installation groups is very important and could jeopardize schedule Linac BPM upgrade could be an added challenge System Functionality Timing System – small concern BPM, Toroid – need verification of design

44 Summary Controls in general is in good shape for 2007 installation No major design or production issues dominate the plan The schedule is challenging with little float While a large number of sub-systems will be installed on time, some will need attention to stay on schedule


Download ppt "2007 Downtime Controls Installation"

Similar presentations


Ads by Google