Hal Tompkins Photon October 30, 2007 1 LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

1 Enhancements to the Linac Coherent Light Source.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
October 30, 2007 Heinz-Dieter Nuhn, SLAC / LCLS Undulator Commissioning Plans 1 Undulator Commissioning Plans Heinz-Dieter Nuhn,
James Welch October 30, FEL Commissioning Plans J. Welch, et. al. FEL Commissioning Plans J. Welch, et. al. Accelerator.
Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
John Arthur X-ray November 11, 2008 SLAC National Accelerator Laboratory 1 X-ray Overview LCLS Directorate structure.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
J. B. Hastings LUSI Overview LCLS FAC March 20, 2007 LUSI Overview J. B. Hastings January 2007 Lehman Review Response to Lehman Review.
John Arthur X-ray June 17, X-ray Overview XTOD current status XES current status Schedule to first experiments.
1 Stefan Moeller 1 AMO Instrument Schedule ARR AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009.
Donn H. McMahon XTOD Breakout: XTOD FY07 October 12, 2006 UCRL-PRES XTOD FY07 Plan LCLS FAC Review October 12, 2006.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
X Ray Transport / Optics / Diagnostics Overview Richard M. Bionta Facility Advisory Committee Meeting April 29, 2004 Richard M. Bionta Facility Advisory.
John Arthur Photon October 18, 2005 LCLS Photon Systems Status John Arthur SLAC.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project NEH status and XFD operations Hal Tompkins, John Arthur LCLS Experimental Facilities.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
John Arthur X-Ray Optics October 12, 2004 X-Ray Prototype Optics Specifications John Arthur.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
1 Michael Rowen 1 SXR Instrument FAC SXR Instrument Michael Rowen – Engineering Physicist June 9, 2009.
John N. Galayda LCLS Facility Advisory 29 October 2007 Linac Coherent Light Source Overview 29 October 2007  Project.
John Arthur X-Ray Endstation April 29, 2004 X-Ray Endstations Overview John Arthur.
Richard M. Bionta X-Ray Transport, Diagnostic, & Commissioning September 22, 2004 UCRL-PRES Two Problems... LCLS Diagnostics.
Opening Comments and Charge 19 January 2004 Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear.
Richard M. Bionta XTOD Layout and Diagnostic October 12-13, 2004 UCRL-PRES-XXXXX XTOD Layout and Diagnostic Systems Facility Advisory.
9/22/04J. Welch, LCLS Commissioning Worskhop, SLAC LCLS Commissioning Schedule and Startup Plan LCLS Commissioning Schedule and Startup Plan.
John Arthur X-ray April 20, 2006 X-Ray Beamline and Experiment Layout John Arthur LCLS Photon Systems Manager.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Richard M. Bionta XTOD Beam and Detector October 12-13, 2004 UCRL-PRES-XXXXX XTOD Beam and Detector Simulations Facility Advisory.
R. M. Bionta SLAC November 14, 2005 UCRL-PRES-XXXXXX LCLS Beam-Based Undulator K Measurements Workshop Use of FEL Off-Axis Zone Plate.
LCLS Undulator Systems TDR Charge Linac Coherent Light Source Stanford Linear Accelerator Center Technical Review, March 3, 2004.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
Status of LCLS A. Brachmann, SLAC National Accelerator Laboratory.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
John N. Galayda DESY October 8, LCLS Commissioning in 2008 J. Galayda, for The LCLS Construction/Commissioning.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
Experimental Facilities Planning
LCLS Ultrafast Science Instruments
Hal Tompkins – Photon Beam Systems Deputy June 8, 2009
LTU/Undulator Installation Status
John N. Galayda – Director of LCLS Construction March 30, 2009
Installation of Photon Beam Transport to FEH
X-Ray Transport, Optics, and Diagnostics WBS Alan J
Overview Pre-Beam Checkouts
John Arthur – LCLS Experimental Operations
FEE Diagnostics and Commissioning
The Transition to User Operations
Coherent X-ray Imaging Instrument WBS 1.3
Conventional Facilities Status
Shutdown Planning & Installation Schedule
LTU/Undulator Installation Status
X-ray Correlation Spectroscopy Instrument
Hal Tompkins – Photon Beam Systems Deputy May 14, 2009
Photon Systems Breakout Lehman Review July 11, 2007
Linac Coherent Light Source Project Update
Installation Status & Operational Readiness Process
X-Ray Endstation Systems (XES) 2006 Schedule
LINAC System Engineering / Design Status C.E. Rago
LCLS Photon Systems Overview
Presentation transcript:

Hal Tompkins Photon October 30, LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory Committee October 29, 2007 Hal Tompkins LCLS Photon Systems Deputy Manager

Hal Tompkins Photon October 30, Important Dates Beam Dump Co-occupancy - 12/5/07 FEE and NEH Co-occupancy - 12/21/07 FEE and NEH Beneficial Occupancy - 3/21/08 (NEH elevator - 4/08?) X-Ray Transport Tunnel Co-occupancy - 1/08/08 FEH Co-occupancy - 3/24/08 Tunnel/FEH Beneficial Occupancy - 6/23/08

Hal Tompkins Photon October 30, FEE Layout

Hal Tompkins Photon October 30, NEH Layout

Hal Tompkins Photon October 30,

Hal Tompkins Photon October 30, Beam Dump Installation Electron beam dump installations are critical. Must install two electron-photon stopper systems, fast shutter, collimator, penetration tube, and backfill steel and concrete in Muon Wall 1. Expect to certify PPS though electron beam dump in 10/09. This allows electrons into BTH, UH, etc.

Hal Tompkins Photon October 30,

Hal Tompkins Photon October 30, FEE Installation Fixed Mask, Adjustable Slits, Gas Detectors, and Gas Attenuator make up phase 1 (June 11-July 1, 2008). Calorimeter, K-spectrometer, Soft X-ray imager, and Direct imager make up phase 2 (July 2-23, 2008). Soft x-ray Offset Mirror System (SOMS) is phase 3 (Jan. 16-Feb. 5, 2009). Note the gap between phase 2 and phase 3. This is driven by deferring purchase of the FEE Mech/Vac (mainly collimators) and pop-in monitors to FY09 for budgetary reasons. It is not driven by delivery date of SOMS mirror substrates. Hard x-ray Offset Mirror System (HOMS) is phase 4. This is close to being delivery-date dependent (Feb. 6-26, 2009). PPS/BCS installed by 2/09.

Hal Tompkins Photon October 30, NEH Installation Vacuum transport through hutches 1 and 2 will be installed. Anticipate LUSI will handle vacuum transport in hutch 3. XES laser installation begins with NEH B.O. and is expected to be complete in 5/09. Commissioning the laser diagnostics and controls follows immediately afterwards. AMO experiment installation begins with NEH B.O. and is slated to be complete in 7/09.

Hal Tompkins Photon October 30,

Hal Tompkins Photon October 30, Tunnel/FEH Installation X-Ray Tunnel and Far Experimental Hall component purchases also delayed until FY09. FEH hutch construction estimated at 8-9 months.

Hal Tompkins Photon October 30,

Hal Tompkins Photon October 30,

Hal Tompkins Photon October 30, FEL Commissioning Timeline

Hal Tompkins Photon October 30, Commissioning Nominal first beam to FEE is 5/14/09 Commission the X-ray diagnostics simultaneously with commissioning the undulator. Start with Direct Imager, then move on to Adjustable Slits, Gas Detectors, the Attenuators, and the Calorimeter. Then do K-spectrometer and Soft X-ray Imager. Align and characterize the spontaneous radiation beam Measure photon flux per pulse Find SASE and optimize gain (first at low energy) Deliver beam through offset mirror systems to experiments in NEH hutches.

Hal Tompkins Photon October 30, Commissioning Stabilize FEL for User Run User Run SLAC shutdown Recommission upstream pieces of LCLS If ready, transport x-rays into Tunnel and Far Hall Detect x-rays in Far Hall - complete CD 4 Continue working on lasing at higher energies Alternate machine work with experiments

Hal Tompkins Photon October 30, Summary Very tight schedule between first beam to FEE and User Run - driven by FY08 budget limitations. Very tight schedule between AMO experiment installation and User Run - driven by FY08 budget limitations. We think we have a good shot at lasing at 1.5 nm for the User Run - stability is a bigger question. Operation at.15 nm for the User Run will likely be with spontaneous radiation.

Hal Tompkins Photon October 30, End of Presentation

Hal Tompkins Photon October 30, Detailed FEE Vacuum Installation Schedule Install vacuum system65dThu 3/27/08Wed 6/25/08 install fixed mask/valve3dThu 3/27/08Mon 3/31/08 align fixed mask/valve2dTue 4/1/08Wed 4/2/08 install slit system4dTue 4/1/08Fri 4/4/08 align slit system2dMon 4/7/08Tue 4/8/08 install attenuators/gas detectors8dMon 4/7/08Wed 4/16/08 install K-spectrometer2dThu 4/17/08Fri 4/18/08 align attenuators/gas detectors4dThu 4/17/08Tue 4/22/08 install calorimeter3dMon 4/21/08Wed 4/23/08 align K-spectrometer1dWed 4/23/08Wed 4/23/08 align calorimeter1dThu 4/24/08Thu 4/24/08 install direct imager2dThu 4/24/08Fri 4/25/08 install isolation valve0.5dMon 4/28/08Mon 4/28/08 align direct imager1dMon 4/28/08Mon 4/28/08 install differential pumping section1dMon 4/28/08Tue 4/29/08 install collimator C10.5dTue 4/29/08Tue 4/29/08 align diff. pump. section1dTue 4/29/08Wed 4/30/08 install SOMS M1S2dWed 4/30/08Thu 5/1/08 align collimator C10.5dWed 4/30/08Wed 4/30/08

Hal Tompkins Photon October 30, Detailed FEE Vacuum Installation Schedule (cont.) align SOMS M1S1dFri 5/2/08Fri 5/2/08 install HOMS M1H2dFri 5/2/08Mon 5/5/08 install SOMS M2S2dFri 5/2/08Mon 5/5/08 align HOMS M1H1dTue 5/6/08Tue 5/6/08 install collimators C2S1dTue 5/6/08Tue 5/6/08 align collimators C2S0.5dWed 5/7/08Wed 5/7/08 install HOMS C2H0.5dWed 5/7/08Wed 5/7/08 align SOMS M2S1dWed 5/7/08Wed 5/7/08 install HOMS M2H2dWed 5/7/08Fri 5/9/08 align HOMS C2H & M2H1dFri 5/9/08Mon 5/12/08 install FEE/NEH beam pipes (3)2dFri 5/9/08Tue 5/13/08 align FEE/NEH beam pipes (3)1dTue 5/13/08Wed 5/14/08 backfill wall 1 window10dWed 5/14/08Wed 5/28/08 install C3H, C3S1, & C3S2 collimators 2d Wed 5/28/08 Fri 5/30/08 align C3H, C3S1, & C3S2 collimators 1dFri 5/30/08Mon 6/2/08

Hal Tompkins Photon October 30, Detailed FEE Vacuum Installation Schedule (cont.) fix collimator positions per RP2dMon 6/2/08Wed 6/4/08 install HXR stoppers3dMon 6/2/08Thu 6/5/08 Install SXR stoppers3dThu 6/5/08Tue 6/10/08 install HXR diff. pump. Section0.5dTue 6/10/08Tue 6/10/08 align HXR & SXR stoppers1dTue 6/10/08Wed 6/11/08 install SOMS M3S & M4S3dWed 6/11/08Fri 6/13/08 install isolation valves3dMon 6/16/08Wed 6/18/08 align isolation valves1dThu 6/19/08Thu 6/19/08 install vacuum piping2dThu 6/19/08Fri 6/20/08 install shadow wall3dMon 6/23/08Wed 6/25/08 install ion pumps3dMon 6/23/08Wed 6/25/08

Hal Tompkins Photon October 30, Commissioning Schedule

Hal Tompkins Photon October 30, Commissioning Schedule (cont.)

Hal Tompkins Photon October 30, Commissioning Schedule (cont.)

Hal Tompkins Photon October 30, Commissioning Schedule (cont.)