Presentation is loading. Please wait.

Presentation is loading. Please wait.

Overview Pre-Beam Checkouts

Similar presentations


Presentation on theme: "Overview Pre-Beam Checkouts"— Presentation transcript:

1 LTU & Undulator Commissioning Plans Heinz-Dieter Nuhn, SLAC / LCLS May 14, 2008
Overview Pre-Beam Checkouts LTU to Dump Commissioning (No Undulator Segments) Undulator Segments Commissioning Characterization of Spontaneous Synchrotron Radiation Characterization of SASE May 14, 2008 1

2 LCLS Installation and Commissioning Time-Line
First Light in FEE First Light in FEH LTU/Und/Dump Install PPS Cert. LTU/Dump FEE/NEH Install Undulator Seg. Install X-Rays in NEH FEH Hutch BO CD-4 (7/31/2010) PEP-II run ends FEH Install now J F M A S D O N Down PPS Linac/BC2 Commissioning Re-commission Inj/BC2 to SL2 LTU/Und Comm. NEH Operations/ Commissioning FEE Comm. April 18, 2008 May 14, 2008 2

3 Beam-Based Commissioning
2008 2009 Beam-Based Commissioning A B C A: LTU – Dump B: Undulator Segments C: Spontaneous X-Rays D: SASE e--Beam D X-Ray May 14, 2008 3

4 LTU/Undulator e--Beam Commissioning Blocks
Installation and Conventional Alignment (=>Nov 08) All beamline components except Undulator Segments Pre-Beam Checkouts (Checklists will be prepared) (Nov-Dec 08) LTU Section Magnet Polarities / Motion (OTR, Collimators, Wire-scanners) / etc. Undulator Section Magnet Polarities / Motion (Girder, BFW, Slide) / ADS Calibration / etc. Pre-Undulator Commissioning with Beam (Jan 09 – Mar 09) Beam-Based Alignment / Motion Control / Beam Containment / etc. Beam Dump Section Installation of Undulator Segments (Mar 09) Undulator Commissioning with Beam (Mar 09 – Apr 09) Beam Based Alignment / Undulator Slide Functions / Beam Stability A B May 14, 2008 4

5 LTU-to-Dump Pre-Beam Checkouts (Nov-Dec 08)
Undulator Hall HVAC System checkout (before Girder installation) ADS (WPM & HLS) commissioning ADS Control System checkout EPICS Control System Checkout Network Configuration of IOC's Timing System Communication with ADS Checkout Verification of individual Device Operation Magnet Power Supplies and Interlocks Magnet Polarity Checkout Dipoles Quadrupoles Correctors (where power supplies available) BPM Cable Checkout Motion Checkouts Movable Collimator motion Wire Scanner motion & calibration Beam Finder Wire In/Out motion (BFW01 – BFW33) Girder Motion Control checkout (33 Girders using external pos. sensors) CAM Mover motion checkout Transverse slide motion checkout Compound motion checkout (Smooth beamline motion, System re-pointing) May 14, 2008 5

6 LTU Commissioning with Beam (Jan-Mar 09)
Perform radiation surveys in FEE, etc with beam in the dump (Stan Mao, et al.) Checkout BPMs (timing, scale, sign errors, etc.) Test MPS (toroid collimators, BPMs, loss monitors, magnets, trip the beam, etc?) Checkout optics using beam oscillation data (does a betatron oscillation fit the model well everywhere? – backwards quads?) Test/checkout BYKIK and its abort dump and logic (MPS). Test/checkout new OTR screens/cameras (OTR30, OTR33, and OTRDMP). Test/checkout new wire scanners (WS31, 32, 33, 34). Test/checkout new adjustable collimators (CEDL1, CEDL3, CX31, CY32, CX35, CY36) Commission new energy and launch feedback loops. Characterize beam, etc. May 14, 2008 6

7 Undulator Beamline Commissioning to Main Dump with Beam but without Undulator Segments (Jan-Mar 08)
Commission Radiation Monitors Get Beam through Undulator vacuum pipe with minimum losses. Calibrate RF Cavity BPMs Including sign determination. Commission Girder Motion with Beam Verify and calibrate steering effect of quadrupole motion Calibrate motion parameters (gain, pivot points etc.) Check BPM offset tracking Commission RF Cavity BPMs Check charge dependent response over entire charge range Use Girder Motion to calibrate position vs. readings Check and correct optics matching over entire operational energy range Commission Beam Based Alignment (BBA) Develop saved configurations for three different energies. Commission BBA GUIs and BBA procedure. Commission Beam Finder Wires Calibrate PMT signals. Commission BFW GUIs (Alignment and scanning capabilities) Commission ADS-based girder position stabilization feedback systems. Commission Tune-Up Dump in preparation for commissioning with Undulator Segments May 14, 2008 7

8 Install Undulator Segments (Mar 09)
Mount Undulator Segments onto girders Segments will be stored in Undulator Hall before installation System is designed to be Self-Aligning Re-check girder motion control Expect to install 3 Segments / day May 14, 2008 8

9 First Beam Through Undulator Segments (Mar 09)
Conditions for First Beam: All Undulator Magnets Rolled-Out Single Shot Operation (low charge) Send single electron bunch through undulator Read and evaluate as much diagnostics as possible along undulator (such as BPMs, beam loss monitors, toroids) Identify and remove sources of beam loss – if any Iterate Goal: Get beam through vacuum chamber with minimum losses. Reminder: Main Constraint is to Protect Undulator from Radiation Damage May 14, 2008 9

10 First Undulator Segments Commissioning (Mar – Apr 09)
Undulator Segments still in Roll-Out position Run BBA Roll-In Individual Undulator Segments Transport beam through individual Undulator Segments Start at slot #33 (last Undulator Segment) Check and correct trajectory change. Run BBA with Undulator Segments inserted. Check Segment alignment with BFWs B May 14, 2008 10

11 Commissioning of X-Ray Diagnostics (May – Jun 09)
Direct Imager Slit Solid Attenuator Gas Attenuator Gas Detector Beam-Based K Measurement Components Minimum Requirement X-Ray Diagnostics is located after last Undulator Segment in Front-End Enclosure (FEE) See presentations by Tompkins and Bionta May 14, 2008 11

12 X Ray Diagnostics (FEE)
5 mm diameter collimators Gas Detector Soft X-Ray Offset mirror system Hard x-ray Monochromator (K Spectrometer) Direct Imager Solid Attenuator NFOV Slit Total Energy Thermal Detector Hard X-Ray Offset mirror system e- WFOV Gas Detector Start of Experimental Hutches Muon Shield Gas Attenuator May 14, 2008 See presentations by Tompkins and Bionta 12

13 Characterization of Spontaneous Radiation (May – Jun 09)
Initially at 1.5 Å to reduce damage issue Start at low charge Repetition rate of 10 Hz or lower will be sufficient Start to characterize radiation at last undulator Measure: total spontaneous energy / pulse spontaneous beam direction temporal variation in spontaneous beam parameters spatial distribution around first spontaneous harmonic spontaneous radiation spectrum wavelength of first harmonic first harmonic wavelength spread Characterize radiation from each individual Undulator Measure relative K of Undulator pair. C Limited capability using K Spectrometer May 14, 2008 13

14 K Measurement: 2-Segment Scheme
Measure synchrotron radiation spectrum produced by two undulator segments, and scan K of one segment K’s are matched when spectrum has the steepest slope on high energy side of 1st harmonic peak. Match segments pair-wise until all segments are measured. C undulator segments (33 total) segments under test May 14, 2008 14

15 Dj = 0 Dx = 3 mm DK/K = +0.2% ~106 photons/nC/0.01%BW DK/K = 0%
Angle-Integrated Spontaneous Spectrum for 2 Undulators with DK/K = -0.2 to +0.2% C Dj = 0 Dx = 3 mm DK/K = +0.2% 0.1% rms e- energy jitter 0.003% rms e- energy meas. resolution 2% rms charge jitter 0.5% charge meas. res. 0.5s rms angle jitter 105 photons/pulse/0.01% 100 photon noise 100 beam pulses with natural energy jitter only DK/K = 0% ~106 photons/nC/0.01%BW DK/K = -0.2% May 14, 2008 15 Simulations P. Emma

16 Characterization of SASE (Jul – Aug 09)
D Initially at 15 Å to maximize SASE gain Start with reduced number of undulators Redo BBA after change of undulator configuration Verify that electron beam meets requirements Use Laser-Heater modulation to control gain (7 Hz Lock-In Detection) if necessary Repetition rate of 30 Hz (to support Lock-In Detection) Find SASE signal using Direct Imager Optimize gain (through electron beam quality and BBA) Measure gain length etc… May 14, 2008 16

17 FEL Measurements D Measurements along undulator
Intensity (LG, Saturation) Measurements after undulator Photon wavelength Photon wavelength spread Pulse intensity Pulse duration Pulse centroid and direction Spatial distribution Jitter Saturation Exponential Gain Regime Undulator Regime 1 % of X-Ray Pulse Electron Bunch Micro-Bunching May 14, 2008 17

18 SASE Characterization with FEE Diagnostics
X-ray beam diagnostics located in FEE, down stream of last Undulator Segment Obtain necessary z-dependent information through SASE gain shut-off at selectable points along undulator line by Introduction of trajectory distortion or Roll-out of individual undulator segments May 14, 2008 18

19 Measurement of SASE Gain Length with Trajectory Distortion
Quadrupole Displacement at Selectable Point along Undulator GENESIS Simulations by Z. Huang May 14, 2008 19

20 Measurement of SASE Gain Length Using Rollout
D Undulator Segments can be rolled-out by remote control. Roll-out will start at the last Segment. Roll-out Segments will not effect radiation produced by earlier segments. May 14, 2008 20

21 Plans for LTU/Undulator commissioning have been worked out and include
Summary Plans for LTU/Undulator commissioning have been worked out and include Detailed pre-beam checkout LTU-Main Dump commissioning without Undulator Segments installed. Installation of Undulator Segments. Undulator Segment Commissioning Characterization of Spontaneous Radiation will be combined with commissioning of X-Ray diagnostics suite in FEE Beam based K-measurement method included. Characterization of SASE will start at 15 Å Gain length measurements will use FEE x-ray diagnostics combined with z-dependent SASE gain cut-off A B C D May 14, 2008 21

22 End of Presentation May 14, 2008 22

23 Application Software Development
LTU Emittance Measurement (Loos – extension of existing GUI) Undulator Steering and re-Pointing (Nuhn) Beta-Matching into the Undulator – with variable mean beta (Limborg) Beam-Based Alignment of the FEL Undulator (Loos) Beam-Finder Wire Application – Centering & Emittance (Loos/Nuhn) K-Measurement Application (Emma/Nuhn) There will probably be more … May 14, 2008 23

24 Undulator Segment and TLD Replacement Program
2009 2010 May 14, 2008 24


Download ppt "Overview Pre-Beam Checkouts"

Similar presentations


Ads by Google