Budget Project Organization, Activities Far Hall

2 LCLS - Estimated Cost, Schedule
$273M Total Estimated Cost $315M Total Project Cost FY Long-lead purchases for injector, undulator FY2006 Construction begins FY2007 FEL Commissioning begins September Construction complete – operations begins XFEL Commissioning Title I Design Complete CD-0 CD-1 CD-2a CD-2b CD-3b FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 2002 2003 2004 2005 2006 FY2008 FY2009 Project Engineering Design Long-Lead Procurement Construction Operation CD-3a CD-4

3 LCLS - Estimated Cost, Schedule
$315M Total Estimated Cost $379M Total Project Cost FY Long-lead purchases for injector, undulator FY2006 Construction begins FY2008 FEL Commissioning begins March Construction complete – operations begins XFEL Commissioning Title I Design Complete CD-0 CD-1 CD-2a CD-2b CD-3a CD-3b FY2001 FY2002 FY2003 FY2004 FY2005 FY2006 FY2007 2002 2003 2004 2005 2006 FY2008 FY2009 Project Engineering Design Long-Lead Procurement Construction Operation CD-3a CD-4

4 FY2005 – Start Long-Lead Procurements
Authorized FY2005 President’s Budget FY2006

5 LCLS Peoplepower / System / Lab
Critical Slots: Laser Group Leader Physics Team Leader Electron Systems Photon Systems SLAC/ANL Liaison Engineer Procurement Lead FY05 is key ramp-up year

6 LCLS a Division of SLAC 8/2004
Linac Coherent Light Source Division Associate director J. Galayda Chief Engineer M. Reichanadter

7 Inside LCLS LLNL

8 Staffing Hires ES&H Coordinator - Done – M. Scharfenstein
QA Coordinator – Interviews done Database managers – Interviews started laser group leader – Interviews done e-beam systems manager – Interviews done Accel Physics Group Lead – to be announced ANL Undulator Systems Chief Engineer – Done- G. Pile, ANL

9 1.4 Undulator Systems

10 Long-Lead Procurements, FY2005 - Undulator Systems
Undulator Hardware Magnet Blocks Magnet Poles Awarded Strongback Awarded Undulator Measurement Lab design complete, bid package in preparation for room On track for complete delivery of undulators by June 2007

11 Straight Ahead Spectrometer
LCLS Injector 10/2005 Shutdown RF Gun Load Lock L0-1 & L0-2 3-m SLAC Sections Gun Diagnostics Laser Heater Transverse RF Cavity DL1 Bend Straight Ahead Spectrometer

12 Undulator Magnet Measurement – Bldg 81
Test stand lay-out is driven by requirement to match the Earth Magnetic Field conditions in lab to Undulator Hall, i.e. azimuth and gap orientation need to be identical

13 Long-Lead Procurements, FY2005 - Linac
Selected Linac Systems X-band RF system – underway Klystron construction >50% Chicane Magnets vendor survey

14 Injector Building out for bid Laser bids in Gun in fabrication at SLAC
Preparations for October shutdown vacuum connection to linac Elev -35’-0” Elev 0’-0” Sector 20 Laser Facility

15 1.5 X-ray Transport, Optics, and Diagnostics Layout
FEH NEH Flipper Mirror FEE Tunnel Experiments: Atomic Physics Front End Enclosure Fast Close Valve Slits Attenuators Shielding Experiments Optics Structural Bio Nano-scale Femtochem FEL Measurements & Experiments: Low Power Imaging High Power Imaging Spectrometer Calorimeter FEH Optics: Pulse-Split-&-Delay Monochromator Experiments: Optics Warm Dense Matter

16 1.9 Conventional Facilities Title-II Kickoff 29-30 March 2005
Undulator Hall (175m) Beam Dump (40M) Front End (29m) X-ray Transport (250m) Far Expt. Hall Near Expt. Hall Linac-to-Undulator (227m) Far Expt. Hall 2nd Undulator Line 3rd Undulator Line Near Experiment Hall

17 1.9 Conventional Facilities Construction Manager Out for Bids
Undulator Hall (175m) Beam Dump (40M) Front End (29m) X-ray Transport (250m) Far Expt. Hall Near Expt. Hall Linac-to-Undulator (227m) Central Lab Office Complex (CLOC) Capacity ~300 72,000 GSF Total 150-Seat Conference Room

18 Alternate Far Hall Layout
14.6m 10-meter hutch length

19 LCLS Facility Advisory Committee
Membership Kem Robinson, Lawrence Berkeley National Laboratory (LBNL), Chair Harry Carter, Fermi National Accelerator Laboratory (FNAL) John Cleary, Stanford University (SU) John Corlett, Lawrence Berkeley National Laboratory (LBNL) Roger Falcone, UC Berkeley Josef Feldhaus, Deutsches Elektronen-Synchrotron (DESY) Paul Fouss, Argonne National Laboratory (ANL) Thomas Himel, Stanford Linear Accelerator Center (SLAC) Vim Leemans, Lawrence Berkeley National Laboratory (LBNL) Pat O'Shea, University of Maryland (UMD) Joachim Pflueger, Deutsches Elektronen-Synchrotron (DESY) Thomas Rabedeau, Stanford Linear Accelerator Center (SLAC) Jörg Rossbach, Deutsches Elektronen-Synchrotron (DESY) Keith Schuh, Fermi National Accelerator Laboratory (FNAL) Peter Siddons, Brookhaven National Laboratory (BNL) Thomas Tschentscher, Deutsches Elektronen-Synchrotron (DESY) Karen White, Thomas Jefferson National Accelerator Facility (TJNAF) Meetings 29-30 April 12-13 October 2004 7-8 April DOE (Lehman) Review May will cover PIXEL

20 What’s Next Events Calendar DESY XFEL Undulators 6-8 June Hamburg
DESY XFEL Commiss April Zeuthen DESY XFEL Undulators 6-8 June Hamburg FEL August Stanford

21 What’s Next Review Calendar FAC 7-8 April 2005 SAC 5-6 May 2005
Lehman May 2005

22 FFTB/SPPS Schedule Must preserve funds for FY boundary BUT
Acceleration of 2006 procurements considered Conventional construction – SPPS/FFTB schedule LCLS draft schedule shows May 2006 Shutdown SLAC “draft” schedule shows July 2006 Shutdown Linac Complete by end of shutdown FFTB shutdown pushes LCLS Commssioning Start May 2008 at this time Exploring possibility of an earlier start

23 George Carlin We have written a check to DOE with our Mouths… Time to cash the check

24 With DOE support, LCLS design has
Summary With DOE support, LCLS design has More extensive research infrastructure Greater flexibility for the future LCLS is underway

25 End of Presentation

26 Near Experimental Hall
by 2012 Soft X-ray Station AMO Physics Magnetic imaging Hard X-ray Imaging Station Coherent imaging Hard X-ray Diffraction Station Pump-probe dynamics Hard X-ray Diffraction Station XPCS Hard X-ray Station Extreme states of matter (assumes funding found) Far Experimental Hall

27 Near Experimental Hall
2008-9 Soft X-ray Station AMO Physics (funded by LCLS) Hard X-ray Imaging Station Coherent imaging (funded by PIXEL) Extreme states of matter (funding?) Hard X-ray Diffraction Station Pump-probe dynamics (funded by PIXEL) XPCS (funded by PIXEL) Green applications do not have full capability, but can do preliminary experiments Far Experimental Hall


Download ppt "Linac Coherent Light Source Project Update"