APRIL 2014 CPOC LIRR SANDY RESTORATION PROJECTS. Active LIRR Sandy Projects PROJECT EAC Traction Power Substations64.1M Long Beach Branch Systems 56.4M.

Slides:



Advertisements
Similar presentations
Piedmont Improvement Program NC Society of Engineers
Advertisements

Capital Program Oversight Committee (CPOC) May 23, 2011 Alok Saha, P.E., Program Manager, CPM Infrastructure and Facilities – Line Equipment, Shops & Yard.
Neighborhood Meeting No.2 Golden Gate Bridge, Highway and Transportation Districts San Francisco Mid-Day Bus Parking Facility Contract No BT-1 March.
Facts about King County Metro Transit Area served …. 2,134 square miles Population served …. 1,884,200 Coaches …. 1,301 (907 diesel, 235 hybrid, 159 electric.
Regulatory Proposal December We provide distribution services to 1.4 million residential and business customers We deliver electricity to.
Fill in Agency Name on Master
1 Wastewater Capital Improvement Program (CIP) Large Users Meeting March 15, 2010.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
Public Information Meeting #6 City of Fargo Flood Risk Reduction Projects Rose Creek Coulee October 9, 2012.
LIGHT RAIL PERMITTING ADVISORY COMMITTEE COMMITTEE MEETING Dec. 17, 2014|3:00PM -5:00PM | ROOM 1E-113.
1 TOWN OF NEWMARKET FLOODING ON SEPT. 13, 2006 Committee of the Whole February 5, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Power Status Thomas Nehring Conventional Facilities Advisory Committee Review October 5-6, 2010.
On-Call Signal Contract Options for Discussion March 13, 2015 Cape Cod Joint Transportation Committee.
Presentation to Maxwell Place Homeowners Association 1.
New York Building Congress November 13, 2014 Frederick E. Smith, P.E. Senior Vice President and Chief Engineer, CPM.
Major Construction Completed
Nelson Hydro Downtown Conversion July 26, 2010 Project Overview.
UPCOMING MTA CAPITAL CONSTRUCTION SOLICITATIONS
Project Management Richard Ravin NAU MBA Agenda  Background  Current Position Home Building Business  Project Management vs. Program Management.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Long Island Rail Road Capital Program New York Building Congress Transportation & Infrastructure November 13, 2014.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Thomas C. Nehring, P.E. Lead Electrical Engineer CFAC Review November 9-10, 2009.
PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract.
Railroad 101 Equipment April 9, Next Generation Corridor Equipment Committee  Established by Section 305 of the Passenger Rail Investment and Improvement.
North Metro Rail Line FasTracks Citizens Advisory Committee September 18, 2013.
WORKING IN THE DARK: Citizens Budget Commission October 20, 2009 IMPLEMENTATION OF THE METROPOLITAN TRANSPORTATION AUTHORITY’S CAPITAL PLAN.
04_0001 Elias Semaan Iraq Infrastructure Reconstruction Project Update.
1 Broken Hill Solar Plant Community Information Session 1 July 2015.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Transportation & Traction Power Programs
North Metro Rail Line Request for Proposals (RFP) Commerce City Council August 19, 2013.
Organization Date Alaskan Way Viaduct & Seawall Replacement Program 4 th Quarter 2009 Progress Report Meeting December 9, 2009.
1 Monthly Operations Report September 15, 2015 Presented to Boynton Beach City Commission Presented by Boynton Beach Utilities
September 26, East Side Access Status Report to CPOC September 26, 2011.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
Jeff Florin Deputy Executive Director, Operations Virginia Port Authority Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners.
Utility Engineers, PC.  Generation  Transmission  Distribution.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Procurements Thomas C. Nehring, PE Lead Electrical Engineer Conventional Facilities Advisory Committee - Review.
Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012.
Ipswich City Precinct. 6. ICC Precinct Installation Standards & Regulatory Compliance ICT Infrastructure Integration & Convergence 1. Pit & Pipe Underground.
US 36 Commuting Solutions Northwest Rail Westminster Segment/Eagle P3 Oct. 14, 2014.
Tempe Town Lake Downstream Dam Replacement NEW DAM ALTERNATIVES SELECTION January 5, 2012.
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
TOMMY OLIVER STADIUM John Bozarth February 23, 2016.
CTA CAPITAL IMPROVEMENT PROGRAM. FY FY 2019 CIP Preliminary Marks.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Regional Water Reclamation Facility 23-MGD Expansion Project Joe Mouawad, P.E. Senior Director.
PORT OF TACOMA. Contract Increase & Award Pier 7 Structural Repairs Request authorization to expand the scope of existing A/E Contract No and.
Water and Waste Department 2016 CAPITAL WORKS CONSTRUCTION PROGRAM Presentation to Manitoba Heavy Construction Association April 20,
The purpose of the US 53 project is to address the termination of the 1960 easement agreement that affects the current highway location in order to continue.
Update & Overview. August 12, : Assessment and Action Challenges: Understand RTD’s people, practices, projects, challenges Compare with others.
Big Cypress Basin Capital Project Update Jeffrey Kivett, P.E., Director Operations, Engineering and Construction Division Jeffrey Kivett, P.E., Director.
Meeting Nantucket’s demand for electricity, today and tomorrow. Upgrading Nantucket’s Electric Grid.
Module 11 -Cost Estimation This module covers how to estimate project costs including: –Equipment costs – combination of procurement and installation (including.
Pier Partial GMP Proposal for Marine Structural June 1, 2017
SUB-STATIONS.
Winchester Lift Station Odor Control Project
Eagle P3 Project Update RTD Board of Directors Sept. 2, 2014.
Deputy Executive Director, Operations Virginia Port Authority
Adoption of the FY Capital Improvement Program Budget & Amendments to FY 17 CIP May 8, 2017.
Long Island Rail Road Capital Program New York Building Congress Transportation & Infrastructure November 13, 2014.
Condominiums Association
New York Building Congress
Pacific Power Seismic Preparedness Update
AUTHORIZATION TO ENTER INTO A PURCHASE ORDER CONTRACT WITH ONESOURCE DISTRIBUTORS TO FURNISH AND DELIVER ELECTRIC UTILITY PARTS AND MATERIALS August 28,
25th Avenue Grade Separation
25th Avenue Grade Separation
INFRASTRUCTURE RENEWAL AT NEW YORK PENN STATION
Cost Containment Working Group Board Update
Cost Containment Working Group Board Update
Far Experimental Hall - Hutches
Presentation transcript:

APRIL 2014 CPOC LIRR SANDY RESTORATION PROJECTS

Active LIRR Sandy Projects PROJECT EAC Traction Power Substations64.1M Long Beach Branch Systems 56.4M Long Beach - Wreck Lead Bridge Systems 7.0M West Side Storage Yard 31.1M Long Island City Yard 4.2M Miscellaneous Infrastructure / Systems 6.0M Total $168.8M 1

Built-in Resiliency of New Assets Design Process 2 VULNERABILITY RESILIENCY OPTIONS RISK/COST LIRR’s design goal is to establish a design flood elevation (DFE) that incorporates FEMA Advisory Base Flood Elevation (ABFE), freeboard (wave action), and sea level rise equivalent to FEMA ABFE plus 4 Foot. However, exceptions to this goal may exist based on limited resiliency options, low risk to LIRR operations, and prohibiting cost of installation:

Traction Power Substations 3 PROJECT STATUS Full Substation Replacements on the Long Beach Branch: Oceanside Substation: Site work/foundations in construction. Delivery of prefabricated unit by Powell Industries forecasted for June Oil City Substation: Powell Industries commenced design of Oil City prefabricated unit. Demolition can not be initiated until Oceanside Substation is online. Long Beach Substation: Based on Consultants Best Value recommendation, the LIRR will replace the existing Long Beach brick-and-mortar facility with a prefabricated unit similar to Oil City and Oceanside. Design Documents to be complete 3 rd Qt BENEFICIAL USE FORECAST Oceanside Substation: January 2015 Oil City Substation: September 2016 Long Beach Substation: January 2017 SCOPE Scope consists of the replacement/restoration of five Substations in the following locations: Oceanside - Oil City - Long Beach – Long Island City - First Avenue

Traction Power Substations 4 PROJECT STATUS Component Replacements: Long Island City Substation Purchase Orders for component replacement are in place. Delivery of the High Voltage circuit breakers, and Transformers is scheduled for September First Ave. Substation Design-Build contract is scheduled for award in August SCOPE Scope consists of the replacement/restoration of five Substations in the following locations: Oceanside - Oil City - Long Beach – Long Island City - First Avenue BENEFICIAL USE FORECAST Long Island City Substation November 2014 First Ave. SubstationApril 2016

Long Beach Branch Systems Restoration SCOPE Replace all third rail components and switch machines. Replace damaged Signal System in accordance with current standards: o New huts, cases and equipment o Installation of a new pole line, communication cables and power drops o New signal supervisory software and hardware at Lead and Valley Towers o Reverse signaling on both tracks New grade crossings along the branch; including gate mechanisms and all associated equipment. 5 PROJECT STATUS. The following work is on-going: Installation of protection board, brackets, insulators, and anchors. Trenching and installation of Third Rail conduit and cable. Construction of negative cables and Third Rail splice bars. Installation of new Communication System. Consultant’s Design Documents for new Signal System are to be complete in June BENEFICIAL USE FORECAST April 2017 BUILT-IN RESILIENCY Consultant’s Best Value Analysis and proposed Resiliency Measures for the new Signal System are under review (including raising Huts, and other wayside equipment).

SCOPE Replace and elevate emergency generator Replace damage bridge electrical, signal and communications systems. Wreck Lead Bridge Systems Restoration 6 Wreck Lead Bridge is a single track bascule bridge that crosses Reynolds Channel on the Long Beach branch. PROJECT STATUS Engineering Consultant Contract is in the process of being awarded. The design for the raised platform for emergency generator has been completed, and materials are being procured. Generator is forecast to be delivered May The LIRR will coordinate with the Army Corp of Engineers and the Coast Guard to obtain all permits as Reynolds Channel is an active navigable waterway. BUILT-IN RESILIENCY Equipment and Termination will be above flood plain or protected BENEFICIAL USE FORECAST April 2017

West Side Storage Yard Restoration SCOPE: Replacement of the following: Third rail components including cables, disconnect switches and protection boards. Switch machines, signal cables and signal racks Tower Controls and Signal Equipment. Communication Equipment, Radio Base Station, Fiber Optic Distribution Panel and CCTV Recording System. Facilities Power, Lighting and Fire Alarm Systems. 7 PROJECT STATUS The field headquarters and on-site equipment/material storage facility have been set up including installation of high security fencing. Procurement of F/A material is underway and replacement of third rail and signal cables has begun. Replacement of third rail disconnects, and switch machines is progressing. BUILT-IN RESILIENCY Expose cable terminations will be protected to the extent possible. A future Resiliency Project includes perimeter flood walls. BENEFICIAL USE FORECAST July 2018

Long Island City Yard Restoration/Resiliency Project SCOPE Long Island City Yard Repairs & Replacements / Improvements : Underground Systems (power, lighting, and communications systems). Third rail system to Tracks Switch heaters and other wayside equipment Damaged facilities. Add Electrification to Tracks 7 and 8. New Drainage System 8 PROJECT STATUS Initial staging work consisting of the electrification of Tracks 7 and Track 8 is in process. Design contract for balance of work including Resiliency is expected to be award late April or early May BUILT-IN RESILIENCY Design includes study and design of perimeter flood walls. Resiliency Resiliency portion of Project valued at $26.8 Mil is pending approval. BENEFICIAL USE FORECAST April 2017

Miscellaneous Infrastructure / Systems SCOPE: Replacement of the following: Third rail power cable and switch machines at Shea yard and on the Far Rockaway Branch. Platform Shelter Shed at Westbury Station The roll-up gate at 34 th street Entrance to Penn Station HVAC units and Roof at Hillside Support facility Platform Lighting for Oceanside and Island Park Stations 9 PROJECT STATUS Small Business Mentor Program (MTA SBMP) Contractors will be used for a significant amount of this work. Bids are due on May 28. Hillside roof scope and document review meeting held on April 4 with Facilities, DPM and Estimating. Final review comments for documents currently are being generated for incorporation in Contract. LIRR Forces will be replacing the platform light poles damaged at Oceanside and Island Park Station. Delivery of new poles is expect in May BUILT-IN RESILIENCY Where possible termination will be above flood plain or protected BENEFICIAL USE FORECAST March 2016

10 Service Impacts LIRR continues to maintain the delivery of service while coordinating the demands of the Sandy Projects and other Capital Program Projects; as well as East Side Access; West Side Storage Yard Overbuild; and other construction activities. The Long Beach System Restoration: Work is currently being done under single off-peak track outage. This outage will continue through the November timetable and renewed as needed in Traction Power Substation Replacements: Replacement of Traction Power Substations/Components is being coordinated to ensure the Reliability of Service. West Side Storage Yard: All Sandy Yards Restoration Projects are being coordinated with on- going WSSY Overbuild Projects, the Gateway (Amtrak Tunnel) project, and other yard activities. LIRR is actively focusing their efforts on replacement of power systems in the western area of WSSY, away from the other contractor activities.

11 Resource Impacts Sandy Projects will require a combination of LIRR Engineering Force Account and Third-Party Contractors/Consultants. The use of LIRR Forces has permitted the early mobilization of a work force assigned to Sandy Projects. Third Party Contractors will work in areas that can be safely isolated from active Railroad Operations, and Systems. Third-Party Contracts will include the need to meet FTA Goals for Disadvantage Business Enterprises (DBE). Small Business Mentor Program Contracts will be let out for installation of specific component replacements including elevated platforms, and pedestals needed to raise equipment above the flood plain.