1 Deputy Executive Director, Operations Virginia Port Authority
Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 352 July 31, 2013 Jeff Florin Deputy Executive Director, Operations Virginia Port Authority

2 Agenda NIT Gate Improvements PMT Rail Upgrades
CBP Screening Area OCR Portals Truck Canopy – New Lane Truck Canopy – Gate Automation PMT Rail Upgrades APMT Trench Drain Repairs APMT Reefer Plugs Craney Island Eastward Expansion

3 NIT Gate Improvements Security, interchange, and transfer zone automation, personnel shifted to remote facility Automation, appointment system and remote processing Improves cargo velocity, safety & efficiency Estimated combined project cost: $10 M Includes $4.1 M software

4 NIT Gate Improvements Project 2 Inbound OCR Portals Project 3
Truck Canopy Completed Chassis Service/Customer Service Areas Project 1 Completed Outbound Corridor Project 2 Completed Outbound OCR Portals Completed Transfer Zone

5 NIT Gate Improvements CBP Screening Area and Outbound OCR Portal Building are complete Truck canopy – new lane scale installed Estimated project cost : $3.5 M Contractor: EV Williams Project is 75% complete Project completion in September

6 NIT CBP Screening Area

7 NIT Outbound OCR Portals

8 NIT Truck Canopy – New Lane
Truck scale frame being set

9 NIT Truck Canopy – New Lane
Truck scale platform

10 NIT Truck Canopy Gate Automation
Infrastructure for gate automation Estimated project cost : $300,000 Contractor: Homeland Contracting Pre-construction and metal fabrication underway Project completion by October 2013

11 NIT Truck Canopy Gate Automation

12 PMT Rail Upgrades Replacement and upgrade to Class I railroad standards of the East and West rail leads into PMT On hold pending tunnel contractor work Estimated project cost : $900,000 Contractor: H&B Railroad Project completion by December 2013

13 PMT Rail Upgrades East rail lead West rail lead

14 Reefer plug installation
APMT Projects Reefer plug installation Trench drain repairs

15 APMT Trench Drain Repairs
Localized repairs of APMT storm drains Contractor: Eastern Waterproofing & Restoration of VA Co, LLC Estimated project cost : $150,000 Some demolition remaining Project is 80% complete Project completion mid-August

16 APMT Trench Drain Repairs

17 APMT Reefer Plugs Installation of 60 reefer plugs
Discussions with APM ongoing Estimated project cost : $915,000 Contractor: JC Driskell

18 Craney Island Eastward Expansion
Cross Dike Stage 2A is complete Placed 1.54 MCY of sand on south and division cross dikes to +5 feet MLLW Next steps Bid package for $4 M PVD installation on cross dikes will be advertised in September 2013 16-acre oyster reef construction at Hoffler Creek to begin in August (Corps funded)

19 Craney Island Eastward Expansion
Aerial taken May 8, 2013 Cross Dike Progress - June 25, 2013

20 Craney Island Eastward Expansion
Aerial taken May 8, 2013 Cross dike as seen from the June 20th Craney Island boat tour

21 Thank You