LTU/Undulator Installation Status

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Rodd Pope, SLAC Undulator System October 12-13, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC.
Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Heinz-Dieter Nuhn, SLAC / LCLS Undulator Checkout and Startup Plans November 12, Undulator Checkout and Startup Plans Heinz-Dieter.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Ernest Williams FAC November 2008 Control Systems Software Section 1 Controls System Installation Status Ernest Williams for Controls Department.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
Geoff Pile FAC Review - Undulator 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
Joshua Stein LCLS Undulator 20 Feb 06 LCLS Undulator Controls ANL LCLS All-Hands Meeting February 20, 2006 Josh Stein Argonne.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
Josh Stein 29-Apr-08 Undulator Controls Undulator Controls Status Update Josh Stein LCLS Undulator Controls CAM/TL.
RF Systems and Controls for the LERF CM Tests
LCLS Undulator Undulator Controls Integration Network Status April 29, 2008.
Experimental Facilities Planning
Undulator System Installation
LCLS Cavity BPM Electronics Undulator Week January 22, 2008
LTU/Undulator Installation Status
Undulator Scope, Management, and Organization
Linac Ops Budget Review LCLS Overview / Org Structure / Legacies
e-Beams Systems Update
Installation of Photon Beam Transport to FEH
Electron Beam Systems ETC and Methodology
Undulator Controls Breakout
LUSI Controls and Data Systems W.B.S. 1.6
Overview Pre-Beam Checkouts
Undulator System Components Status Dean Walters
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Project Status Review May 13-15, 2008.
LCLS Undulator System Status and Schedule
FEE Diagnostics and Commissioning
LCLS Undulator System Production Management
NEH - Status Stefan Moeller.
2007 Downtime Controls Installation
Conventional Facilities Status
Shutdown Planning & Installation Schedule
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LCLS Undulator System Status and Schedule
Control System Overview Hamid Shoaee LCLS Control System Manager
LCLS Operation in 2009 Roger A. Erickson
Linac Coherent Light Source Transition to Operations 11 July 2007
Installation Status & Operational Readiness Process
Undulator Integration Test Status
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Electron Beam Systems ETC and Methodology
Undulator Assembly and Installation Planning
LCLS e- Beams System Overview
Undulator Alignment Plan
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
e-Beams Systems Update
LCLS Undulator Controls Status
X-Ray Endstation Systems (XES) 2006 Schedule
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
DOE Status Meeting of the LCLS Project
LCLS e- Beams Systems Manager
LUSI Controls and Data Systems W.B.S. 1.6
Presentation transcript:

LTU/Undulator Installation Status Enzo Carrone June 17th , 2008

Agenda Scope; Undulator Controls; Time Management - Installation; Status; Summary.

Install, Commission and Test Controls by JAN 09. Scope Install, Commission and Test Controls by JAN 09. Subsystems: BPM Cable Plant (monitoring) LTU Motion Control UCM (Undulator Control Modules) Magnet Power MPS Network PPS/BCS Timing Vacuum

LCLS Installation and Commissioning Time-Line First Light in FEE First Light in FEH LTU/Und/Dump Install PPS Cert. LTU/Dump FEE/NEH Install X-Rays in NEH FEH Hutch BO CD-4 (7/31/2010) PEP-II run ends FEH Install now J F M A M J J A A S O N D J F M A A M M J J A S O N D J F M A M J J 2008 2009 2010 Down AMO Experiment program begins PPS XPP Experiment program begins Linac/BC2 Commissioning Re-commission Inj/BC2 to SL2 LTU/Und Comm. FEE Comm. April 18, 2008

Phase 4 Installation

Ion Pump Undulator Magnet BFW QUAD Girder RFBPM WPM RF Receiver Box HLS Interface Cable Box 6

Undulator Segment (Wall side) EIA(Raceway) Vacuum chamber

Undulator Segment (Aisle side) BFW Undulator Segment (Aisle side) Quad/Corrector BPM Translation Stage Electronics Rack (UCM) CAM Mover

(Courtesy of Scott Doran, ANL)

UIR- (Undulator Instrumentation Rack)

Electronic Interface Assembly (EIA)

Electronic Interface Assembly (EIA)

Schedule Time Management Three levels of scheduling: System, Controls as a whole, Master Schedule. Owners: System Leads, LCLS Installation Manager, LCLS Project Office. Schedule structure: waterfall approach.

Schedule Control: Schedule Management Weekly Master Installation Schedule Management Meetings: review of schedule, action items, technical, personnel and safety issues. Same for Weekly Controls Schedule Management.

Milestones

Working Schedule

The outcome has been very satisfying: ANL Delivery Schedule A delegation of SLAC visited ANL in May, 08 (A. Alarcon, E. Carrone, E. Williams). The outcome has been very satisfying: An assembly line has been setup at ANL to populate the Undulator Instrumentation Racks (“Mini Racks”); EIA are manufactured outside; The whole manufacturing/subcontractor management process is very well organized; LTT is remarkably accurate; ANL has been doing heroic efforts to deliver in time.

UIR Assembly Line

ANL Racks shipping

Undulator Controls installation 16 pre-assembled UIR received from ANL on June, 12th; EIA will be shipped on next June, 24th. Installation is Davis-Bacon; Begin: 6/16/08 – End: 6/26/08. ANL has released a “Handover Plan”. SLAC has a Procedure Documentation for test and installation.

Undulator Motion Control Installation Schedule

Racks Readiness Status (weekly)

Rack Population Tracking System

LTT at ANL

SLAC On-Field Installation Management Daily tailgate meetings (by K. Ratkliffe/M. Zurawel) Review parts availability, deliveries, acceptance, inventories; Discuss daily work plan, technical and transportation issues, personnel issues and safety issues. Turner and LCLS meet weekly for co-occupancy schedule integration A set of procedures and documentation is available on line.

Vacuum Magnets Power Supply All LTU PLCs assembled and programmed; Complete: BTH: 7/25/08 UH: 10/2/08 Magnets Power Supply All Racks in B912 Installed; DataBase and displays ready; Complete: BTH: 12/09/08 UH: 10/7/08

Link Processor and Link Node complete; Beam Loss Monitor complete; MPS Link Processor and Link Node complete; Beam Loss Monitor complete; A nice test bench is in use. Complete: BTH: 10/28/08 UH: 10/29/08

50 BPM Chassis complete, tested and installed; Cavity BPM Receiver Power Supply and Signal Distribution Panels complete; Complete: BTH: 10/14/08 UH: 10/27/08

Chain B software complete; PPS/BCS PLC firmware update; Chain B software complete; A LION mockup has been installed in the Undulator Hall during last week; Complete: BTH: 10/6/08 UH: 9/30/08 Certification: 10/27/08

Cable Fibers are being pulled; Complete: Network Cable Fibers are being pulled; Complete: BTH: 6/30/08 UH: 9/18/08 Timing Complete: BTH: 9/23/08 UH: 10/28/08

Cable Plant Davis-Bacon contract. Complete: BTH: 9/9/08 UH: 9/23/08

Areas to watch carefully Tight Installation Schedule ANL is delivering in time. MPS, BLM (new systems); Motion Controls.

Summary Controls installation expected on schedule; Controls will not be in the way of the beam delivery to LTU in next Jan 09. SLAC can count on the assistance of ANL system experts on site, if needed.

Special thanks to the ANL team for working so hard to deliver in time!