Hybrid Testing Status 10 new hybrids brought by Lenny all tested

Slides:



Advertisements
Similar presentations
1 US Testing Update-Anthony AffolderTracker Meeting, Feb 10, 2004 Faulty Channel Sources (TOB) Fault Sources (excluding cable breaks and CMN)  Hybrid-0.004%
Advertisements

1 Hybrid & Module Testing Status Week of 4/25-4/29.
May 13, FNAL Hybrid Thermal Test Status  Hybrid Thermal Test Procedure  Test Results Eva Medel FNAL CMS Group June 22, 2004.
Slide 1US silicon group meeting 5/6/2003 Hybrid Testing Status 10 new hybrids brought by Lenny all tested à 9 tested with no flaws à 1 had 1 chip + 1 wirebond.
1 Hybrid & Module Testing Status Week of 6/6-6/10.
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
1 US Testing Update-Anthony AffolderTracker Meeting, Feb 10, 2004 US Module Testing Update Anthony Affolder (On behalf of the US testing group) Update.
Ladder QA Status. Ladder QA Summary Ladder Remarks 1XXXXXXXXOOOOOXOO left : short (via-GND) right chip3 : cannot mask 2OOOOOOOOOOOOOOO.
Tracker Week, CERN, Oct Oct 2003Tracker Week - Module ProductionSalvatore Costa - Catania Executive summary from Bonding WG Meeting 21 Oct.
Fermilab PMG - Results from module testing - April 9, 2004 – E.Chabalina (UIC) 1 Results from module testing E.Chabalina University of Illinois (Chicago)
Electrical Tests of Modules and Ladders Markus Friedl (HEPHY Vienna) 2 October 2014.
Origami, PA 2015 Sep. 10 Koji Hara (KEK).
UCSB Hybrid Bonding & Testing
FNAL Production Experience
APV Lectures APV FE Basic Building Blocks How Our Testing Works
On behalf of the US TOB testing group
UCSB Testing Status Anthony Affolder
Hybrid & Module Testing Status
Update of US Testing Status
APV Lectures APV FE Basic Building Blocks How Our Testing Works
Executive summary from Bonding WG Meeting 21 Oct 2003
UCSB Short-term Testing Plan
UCSB Testing 3 Stereo Modules Tested 1 SS6 Module Tested
Results from module testing
Unexpected Failures of Modules on Rods
Recent TOB Developments
Vienna Module Production
Module Failures on RODs
Module Failures on RODs
FNAL Module Testing Status
On behalf of the US TOB testing group
US Testing Update Anthony Affolder (On behalf of the US testing group)
UCSB Short-term Testing Plan
The measurement set-up
Noise in TOB modules and sensor quality
FNAL Module Testing Status
UCSB Qualification Module Grading
Hybrid & Module Electrical Testing
Hybrid Status/Deliveries
Sensor probing (Summary)
First UCSB TEC Module (Pictures)
Hybrid & Module Testing Status
FNAL Hybrid Testing Status
Module Testing Status Week of 6/14-6/20.
Class B Ladder assembly
Noise in TOB modules and sensor quality
Production Status 39 modules produced
Hybrid & Module Testing Status
Is Increased Bias Current and CMN Correlated?
TOB Module Production Overview and Plan
FNAL module testing summary
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Recent TOB Developments
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Module Failures on Rods
Module Testing Status Week of 3/14-3/18.
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
FNAL Hybrid Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
Hybrid & Module Testing Status
FNAL Bonding Since our last report we have built and bonded an additional 10 TOB 4-chip modules 3 RMT pitch adapters 7 Planar pitch adapters By adjusting.
FNAL Hybrid Testing Status
FNAL Hybrid Testing Status
FNAL Hybrid Testing Status
Presentation transcript:

Hybrid Testing Status 10 new hybrids brought by Lenny all tested 9 tested with no flaws 1 had 1 chip + 1 wirebond smashed Looks like finger (most likely FNAL) FNAL agreed to change packing technique 10 new hybrids just arrived from FNAL Plan to visual inspect first Test to keep up with production

Ladder Testing Status 8 modules bonded so far 1st module had 3 opens between PA-sensor and 2 opens between sensor-sensor for testing Gluing at edge of PA Removed all bonds from problems found in sensor probing Two channels found to have high noise which increase with voltage Damage found on sensor 2nd-4th module had bias return bonds missing Damage to bulk unrepairable Draw ~80 mA, ~600 mA, ~800 mA 2 opens between APV-PA found in one module, otherwise no other bonding problems Will turn into x-calibration pieces with shorts and pinholes added on purpose 5th and 6th modules perfect Three channels have high noise which increases with voltage Damage found on sensor 7th module had wirebond damage on ~40 channels between APV and PA Not clear how or when 8th module had no bonding problems Channels found bad in sensor probing pulled 2 channels has increasing noise vs. voltage Neighbors of pinhole found in probing

Ladder Testing Summary Bias Current Sensor Bad Channels Bonding Bad Channels Testing Bad Channels Total % Bad Channels Grade Comments 876 1090 nA 1.5+2 3 1 1.4% B 2 channels with high noise not in sensor probing 0018-P1 613 mA 1.5 Bulk damage 5.5 F Missing bias bonds, turn into x-calibration piece 0019-P1 758 mA 9.5 2.1% 0024-P1 89 mA 4.5 Bulk damage+2 1.2% Missing bias bonds, turn into x-calibration piece; 2 opens during APV-PA bonding 877 930 nA 0 (1??) 0.0% A One channel has increasing noise with voltage; sensor damage seen 878 1100 nA 0 (2??) Two channels have increasing noise with voltage; sensor damage seen 879 ~ 40 smashed wirebonds APV-PA, reconverable 880 720 nA 2(+2??) 0.3% Neighbors of pinhole noisy @ 550 V

Summary 4 of 8 bonded modules good Of 4 good modules 3 had bias return bonds missing 1 has ~40 APV-PA bonds smashed Can be repaired Of 4 good modules All have channels with increasing noise vs. voltage 2 channels on 1 ladder due to inherit pinhole 5 channels total on 3 ladders due to lithographic errors in sensor production Not seen in wafer probing