1 Hybrid & Module Testing Status
Week of 4/25-4/29

2 UCSB Hybrid Testing Status
Weekly Cumulative Pass Fail % Pass L12pd 0.00% L34p 49 1 368 5 98.66% L56p 19 366 98.65% R5N 65 2 97.01% R5S 47 100.00% R6 87 98.86% R7 Total 68 932 13 98.62% Failing Hybrids Over-counted

3 UCSB Hybrid Testing Failures
This Week 1 Too Many Opens Damaged PA Cumulative 3 with Shorts in PA Repairable 1 Major Scratch in PA 1 Smashed APV-PA Bonds 2 Failed Inspection Never should have sent 1 Broken Ceramic 1 Bad Bond Feet 1 Weak Wirebonds 1 Too Many Opens 2 with unknown failure

4 UCSB Hybrid Testing Issues
Need to finish validation of new software Bruno contacted about bugs/features Need to add automatic upload of data to new software Hybrids with shorts need repairing Once repaired need to keep bookkeeping straight

5 UCSB ARCS Testing Status
Weekly Cumulative A B F % A or B L12pu 0.00% L12pd L12su L12sd L34p 85 1 2 97.73% L56p 40 277 99.29% R5N 6 38 97.50% R5S R6 44 68 100.00% R7 Total 90 468 3 5 98.95%

6 UCSB ARCS Testing Failures
This Week None Cumulative 1 with >2% Bad Channels Debris on sensor 1 Bad DCU 1 HV Shorted to CF Frame 2 with >20 mA Bias Current 1 leaky pinhole 1 scratched sensor

7 UCSB ARCS Testing Issues
Need to confirm cuts on TEC modules Getting some confusion between 1SO/2SO Have not produced TEC R6 modules in a year Still need to validate ARCS 8.0 Currently using ARCS 7.2bugfix

8 UCSB LT Testing Status Weekly Cumulative Pass Fail % Pass L12pu 0.00%
Pass Fail % Pass L12pu 0.00% L12pd L12su L12sd L34p 84 100.00% L56p 36 259 R5N 5 39 R5S R6 28 43 R7 Total 69 425