1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.

Slides:



Advertisements
Similar presentations
East Hampton High School July 2013 – July 2014 Design Phases.
Advertisements

Construction Management. Players Owner – owns project upon completion of construction –Private – owner owns land and pays for construction of facility.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
David Saenz CM/GC April 8, 2005 CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
Activities CTC-415. Activity Consumes Time Usually consumes resources (cure time for concrete) Definable start and finish Assignable – V. important –
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
Javier A. Sevilla MMF FAC Review October 27, Magnetic Measuring Facility (MMF) Outline Summary of Facility Requirements.
David Saenz Far Experimental Hall - June 17, Far Experimental Hall - Hutches Scope Budget Schedule.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
David Saenz CF Schedule and Oct 12, 2004 CF Schedule/Organization CF Schedule Title II Title III CF Organization.
Jess Albino / David Saenz / Facility Advisory Committee October 30, 2007 FACILITY.
1 Jess Albino 1 Conventional Facilities Status FAC Review – Breakout Session CONVENTIONAL FACILITIES STATUS Jess Albino – Associate.
David Saenz FAC CF Oct 12-13, 2004 Conventional Facilities Overview SLAC Site Plan Systems Description Construction Schedule.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
David Saenz CF Oct 30, CF MEP Commissioning.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
ESTIMATING By Laith Jacob.
Jo Beth Folger FAC - CF Breakout – Sector April 8, Sector 20 Project Overview Sector 20 Site Plan Description Schedule.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Javier A. Sevilla April 5, Magnetic Measuring Facility (MMF) Outline Organizational Chart Facility Design Criteria,
David McGiven FAC: Construction April 2006 Facility Advisory Committee (FAC) Construction Procurement David.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
1 E. Bong 1 XCS Final Instrument Design Review Engineering Status April 21, 2009 LUSI WBS 1.4 X-Ray Correlation Spectroscopy Final.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
1 BROOKHAVEN SCIENCE ASSOCIATES CCW Plant Expansion & CCW Piping Thomas F. Joos, PE Lead Civil/Structural Engineer CFAC Review March 10-11, 2009.
David Saenz FAC Review CF Design, Cost and Schedule Oct 27, 2005 CF Overview & Status Design Status CMGC Status Latest.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
CENF CIVIL ENGINEERING UPDATE : - SITE INVESTIGATION - CALL FOR TENDER FOR DESIGN & CONTRACT ADMINISTRATION SERVICES - 3D VISUALS FOR SURFACE STRUCTURES.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
IT-4135/EN Supply of Air Handling Units for Industrial HVAC Projects at CERN Technical Specification Paul Pepinster / EN-CV.
Director’s Progress Review Closeout Meeting
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
CF Organization & Schedule
Director’s Progress Review Closeout Meeting
David Salazar, Chief Facilities Executive
Far Experimental Hall Hutches Civil Construction
Controlling Project Cost and Schedule
Far Experimental Hall Hutches Civil Construction
CONVENTIONAL FACILITIES STATUS
CONVENTIONAL FACILITIES LCLS Office Space
Conventional Facilities (WBS 1
CONVENTIONAL FACILITIES LCLS Office Space Procurement
Far Experimental Hall - Hutches
Conventional Facilities WBS 1.9
Conventional Facilities Status
CONVENTIONAL FACILITIES
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
CF Scope, Management & Organization
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
Presentation transcript:

1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager June 08, 2009

2 David Saenz 2 Hutch Construction in FEH June 08, 2009 Scope Design Status/Deliverables Schedule Estimated Construction Cost Present Status Summary

3 David Saenz 3 Hutch Construction in FEH June 08, 2009 Scope Approximately 7,000sf of new facilities for (3) Hutches, (3) Control Rooms and (1) Common Room Specifications have been developed, are well defined, and present no major challenges

4 David Saenz 4 Hutch Construction in FEH June 08, 2009 Scope – Cont’d Utilities (MEP) Process chilled water Chilled water Compressed 100psi HVAC 72° ± 1 °F RH 45% ± 10% 24” cable trays Standard lighting Surface mounted conduits Standard 110V and 208V outlets 1 ton capacity cranes Radiation protection Standard door sizes Existing common floor Standard wall/ceiling finishes No acoustic requirements

5 David Saenz 5 Hutch Construction in FEH June 08, 2009 Engineering Specification Documents LCLS ESD’s approved by key stake-holders. ESD Hutch 4 ESD Hutch 5 ESD CXI Room ESD XCS Room ESD Common Room ESD

6 David Saenz 6 Hutch Construction in FEH June 08, 2009 Access Tunnel (looking south)

7 David Saenz 7 Hutch Construction in FEH June 08, 2009 FEH (looking west)

8 David Saenz 8 Hutch Construction in FEH June 08, 2009 FEH Floor Plan Hutch 4 – XCSHutch 5 – CXI Hutch 6 - MECi Existing X-Ray Tunnel Existing Restrooms Existing Access Tunnel

9 David Saenz 9 Hutch Construction in FEH June 08, 2009 Building Sections Building Section – Looking North Building Section – Looking South Hutch 4Hutch 6Hutch 5 Hutch 6Hutch 5Hutch 4

10 David Saenz 10 Hutch Construction in FEH June 08, 2009 TI/TII/TIII Status Design was awarded Oct 10, 08 Title I completed on Nov 6, 08 Title II 60% completed Jan 15, 09 Title II 90% completed for Mar 09, 09 Title II 100% completed for Mar 16, 09 Issue for Bid documents completed Mar 23, 09 Bidder jobwalk conducted on April 29, 09 7 General Contractors (Butler, Gordan-Prill, DPR, Rudolph Sletten, XL, Dome and Lyncon) 5 GC’s have performed work at SLAC/LCLS/DOE/SU) Bids received May 18, 09 Note: The structural steel design was advanced prior to final package for early release to bid.

11 David Saenz 11 Hutch Construction in FEH June 08, 2009 Design Deliverables √ Existing Conditions Report √ 30% Design Review √ Structural Design Review √ Preliminary Cost Estimate √ 60% Design Review √ Detailed Cost Estimate √ Value Engineering √ Structural 3 rd Party Peer Review √ Engineering Coordination Presentation √ 90% Design Review √ Updated Cost Estimate √ 100% Design Review √ Issue For Bid (IFB) documents √ 100% Cost Estimate Sufficient quantity of deliverables were established to manage progress and complete development of a final package ready for bid!

12 David Saenz 12 Hutch Construction in FEH June 08, 2009 Schedule Design Complete Mar 16, 09 Procurement 4/09-5/09 Construction Commence 5/26/09 Project Complete!! Steel package has been awarded and is being managed by LCLS direct Fabrication drawings have been approved by EOR Steel is currently under fabrication and scheduled for on site erection 6/15/09 – 7/3/09

13 David Saenz 13 Hutch Construction in FEH June 08, 2009 Construction Cost Estimate H4 and H5 Initial 30% AE estimate (Nov 5, 08) at $4.1M includes direct/in-direct cost, and escalation 60% AE estimate (Feb 2, 09) at $3.58M Value Engineering items included Strategy for construction delivery method is consistent with expectations Design → Bid → Build Structural steel package has been released early for bid and erection A cross-check estimate was provided by a GC at $3.1M Same GC successfully completed LCLS Sector 20 and MMF projects 90% AE estimate (Feb 20, 09) at $3.48M 100% AE estimate (Mar 23, 09) at $3.34M WBS ( ) budget is $3.4M for H4 and H5

14 David Saenz 14 Hutch Construction in FEH June 08, 2009 Construction Cost Estimate H6 60% AE estimate (Feb 2, 09) at $.77M A cross-check estimate was provided by a GC at $.70M Same GC successfully completed LCLS Sector 20 and MMF projects 90% AE estimate (Feb 20, 09) at $.76M 100% AE final estimate at $.67M Independent Cost Review provided by SMSI rec’d Mar 23, 09 Hutch 6 can be constructed in conjunction with H4/H5 without impacting schedule BCR CF-109 was approved ($800K) to include Hutch 6 construction as part of the CF WBS 1.9 in April 09.

15 David Saenz 15 Hutch Construction in FEH June 08, 2009 Independent Cost Review SMSI - Professional estimating consulting firm located in the bay area and familiar with bay area economy - Has experience with projects within DOE environment - Understand the requirements involved with DOE complex projects

16 David Saenz 16 Hutch Construction in FEH June 08, 2009 WBS WBS 1.9 for FEH Hutches $4.2M Steel awarded at $390K To be managed by LCLS CF group Concrete deck estimated at $75K Not yet awarded To be managed by LCLS CF group 4 bids received (range $46.7K to $87.8K) Remaining build-out construction balance in WBS budgeted $3,735K All bids received were < estimated budget Three bids received were 50% < estimated budget! Construction schedule is sufficient allowing for 26 weeks of construction (not including steel erection)

17 David Saenz 17 Hutch Construction in FEH June 08, 2009 Summary √ Design parameters are clearly defined √ Sufficient quantity of deliverables are in process √ Title I complete √ Value Engineering complete √ Title II complete √ Issue for Bid set complete √ Structural steel released for bid with favorable results Cost Safety Schedule √ Adequate resources are available for successful execution of the FEH hutches!

18 David Saenz 18 Hutch Construction in FEH June 08, 2009 end of presentation