Presentation is loading. Please wait.

Presentation is loading. Please wait.

Controlling Project Cost and Schedule

Similar presentations


Presentation on theme: "Controlling Project Cost and Schedule"— Presentation transcript:

1 Controlling Project Cost and Schedule
Protecting the Waters of the State…

2 What is GCA Political Subdivision of the state Established 1969
Governed by a 9 member appointed Board of Directors Can operate statewide Fully funded by services provided No ad valorem taxes Mission Protecting the waters of the State of Texas through environmentally sound and economically feasible regional waste management practices

3 GCA Operations Own and operate 4 regional industrial wastewater treatment facilities ~90 industries 50 mgd Blackhawk Facility is a regional municipal wastewater treatment facility POTW so operate a pretreatment program Odessa Facility supplies treated wastewater for O&G water supply

4 How to Produce a Poor Project Outcome
Lack of Clear Project Objectives Weak Project Management Processes Poor Change Management Ambiguity in Bid Package

5 “Benefits” of a Poor Project Outcome
Excessive Contractor Change Orders $$ Project Delays $$ Contractor Disputes $$$ Attorney Fees $$$$

6 Avoiding a Poor Project Outcome

7 Basic Elements of a Project
Scope Schedule Budget All exist in equilibrium- changing one changes the other two Key to maintaining Schedule and Budget is to define Scope early and control of Scope to the extent possible

8 How GCA Avoids a Poor Project Outcome
Formal Project Management Process that Requires: Clear Project Objectives Inclusive Project Team Specific Project Deliverables to Avoid Ambiguity in Bid Documents Strong Change Management Process

9 GCA Project Work Process (Stage/Gate)
Project is broken up in to clearly defined stages of work Each stage has specific expectation that need to be addressed before progressing to next stage Progression to next stage requires senior management approval

10 Project Objectives Defines what is the expected project result not what to build. What problem(s) will this project address? What are the expected performance outcomes? What is the required project delivery date? What are the know constraints?

11 Project Objectives- All Projects Must Address
Core Values Safety Reliability Compliance Cost Effectiveness Operability Maintainability

12 Project Objective Example
Provide a disinfection system upgrade to meet the new regulatory limits System to be in compliant operation by November 1, 2022 The system must be installed on the current plant site but not include the area reserved for future treatment expansion The system must be expandable to meet future planned capacity The system must be installed without interruption of operations The system must not include gaseous chlorine or other potential off site vapor release hazards Minimize operational and maintenance complexity. Control of capital cost is more important than operational cost

13 Project Execution Process
Strong Project Manager Authority to control the project Clear delineation of roles Inclusive Project Team Report to PM for project work Provide communication between the project team and respective area of representation

14 GCA Project Work Process- Project Team
Project Manager Project Engineer Facility Representative (Operations & Maintenance) Compliance Representative Engineering Consultants Other staff as necessary (Safety, Reliability, QA/QC Reviewers, etc.)

15 GCA Project Work Process Stages

16 Key Stage Deliverables
Stage 0- Needs Identification Clear objectives and preliminary justification. Stage 1- Planning Studies/Technology Selection Define initial Basis of Design Evaluation and selection of technology to meet objectives

17 Key Stage Deliverables
Process configuration, layout and key equipment needs Updated cost estimate Permitting requirements Equipment delivery issues Utility needs Plan of how to address obstacles to completion. Initial Transition Plan

18 Key Stage Deliverables
Stage 3- Detail Design Bid Package Detail of how to construct the project Complete specifications The more detailed the bid package the more likely to be able to build a partnership with the contractor rather than an adversarial relationship We use Best Value bid evaluation process Assure compliance with GCA standards Updated cost estimate Updated Transition Plan Startup and Commissioning Plan Identification of construction risks and associated costs Project turnover requirements

19 Key Stage Deliverables
Stage 4- Construction Complete construction of the project Careful review of contractor submittal Assurance of meeting design package requirements Maintaining up to date as-builts Stage 5- Commissioning Project team verifies work is ready for turnover to operations Complete Turnover Packages including warrantee documents All manuals and as-builts up to date Stage 6- Startup Training and support to operations Complete PSSR

20 Change Management Key element in maintaining cost and schedule targets
All projects will requires some changes due to unforeseen weather or site conditions Having a formal change management process valuable tool to meeting cost and schedule targets Avoid Scope Creep

21 Scope Creep

22 GCA Change Management Process
Key elements approved in one stage require formal approval to be changed in subsequent stages Guidelines for approval are defined in PWP documentation Two types of changes Project Changes Scope Changes

23 Project Changes Allows changes to completed work under certain conditions Needed to meet Project Objectives Needed for to meet a safety requirement Need to meet a regulatory requirement Change goes through Project Manager’s chain of command Requires justification of one of the above Requires definition of cost and schedule impact

24 Scope Change A change request that is not a Project Change
Change is approved through Facility Operations chain of command All Scope Changes require General Manager approval Requires technical and cost/schedule evaluation by Project Management Team Approval provides a change to the project budget and schedule

25 Summary A Formal Project Management Process can improve your ability to meet cost and schedule targets Key elements of good project management process include: Clear Project Objectives Inclusive Project Team Specific Project Deliverables to Avoid Ambiguity in Bid Documents Strong Change Management Process


Download ppt "Controlling Project Cost and Schedule"

Similar presentations


Ads by Google