1 UCSB Module Assembly Week of 5/16-5/20
2 UCSB Parts Inventory 5/23/05 Hybrids Sensors Frames STHPKITSTHPKIT L12pu L12pd L12su L12sd L34pu /60~1002 L56p ~1002 R5N103222pr248 pr080 R5S65022pr248 pr080 R pr0255 R pr0198
3 US Module Assembly Weekly Cumulative ABFABF% A or B L12pu % L12pd % L12su % L12sd % L34p % L56p % R5N % R5S % R % R % Total %
4 UCSB Module Assembly Problems Past Week –Minor problem with one glue dispenser. Will test and switch to back-up. Can then modify current one. –200 storage plates assembled. 200 more plates machined, but are waiting to see need before assembling. –Replaced one of out 2 curing pumps with a larger one. Will enable us to cure up to 10 plates at a time.
5 Wirebonding This Week –A few TOB modules require up to rebonds on the PA. Problem seems to come and go. –Bonding has kept up with module assembly.