Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Accelerator Schedules LHC and LHC Injectors Schedules MSWG meeting 16 January 2015 SPSC - 13 January 2015 Rende Steerenberg, BE/OP2 Rende Steerenberg,
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Summary DCS Workshop - L.Jirdén1 Summary of DCS Workshop 28/29 May 01 u Aim of workshop u Program u Summary of presentations u Conclusion.
CERN Accelerators Topology Configuration and Change Management Engineering Department Thomas Birtwistle, Samy Chemli – EN/MEF/DC.
Injector De-cabling Project Project Team Meeting #
Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on.
Roles Committees Meetings
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
TS, Length of YETS EYETS LIU & CONS Project
Stephane Deghaye (AB/CO) ATC/ABOC days.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
CLIC Project breakdown structure: organization, documentation and cost estimate Beam Instrumentation Workshop, June 2-3, 2009 CLIC Project breakdown structure:
Access zones and Training Steve Hutchins BE-ASR IEFC workshop 7/3/2012.
1 EARLY SAFETY MANAGEMENT OF PROJECTS AND EXPERIMENTS HSE UNIT PH DSO EDMS No
Linac2 Review  L2 operated with 99 % uptime in 2010 and 98% in the last 10 years  Systems review: all under control even for L2 till LS2 if ‘nightmare’
Status Report – Injection Working Group Working group to find strategy for more efficient start-up of injectors and associated facilities after long stops.
International Standards and Regional Regulations.
IEFC WS March 2011 Middle-Long Term Needs for Ion Beams S. Maury 111 Middle-Long Term Needs for Ion Beams S.Maury Thanks to T. Bohl, C. Carli, D.
R. Garoby 3/03/2006PAF progress1 PAF Progress 3/03/2006 M. Benedikt, R. Garoby, F. Ruggiero, R. Ostojic, W. Scandale, E. Shaposhnikova, J. Wenninger 
Plan. 12/05/ Who are we? PM (Project Management and Resource Planning) – APT – IMPACT – PPTEU2 – Plan LS1 – 2012 –…–… Plan V2 – From LS1 to LS2.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Injector De-cabling Project Enlarged project meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Samy Chemli – Configuration Management - S. Chemli EN-MEF – Contents Configuration Management Hardware Baseline Change Management.
CLIC Cost at 3 TeV and 500 GeV CDC meeting, Hans-H. Braun for CLIC cost & Schedule WG Mick Draper, Katy Foraz, Claude Hauviller, Bernard Jeanneret,John.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
Planning & Installation meeting New working group EDMS th October 2014LIU PLI meeting - J.Coupard1.
Session 7: I-LHC Organization: Chamonix Summary Session7; Oliver Brüning 1 -session organized in collaboration with D. Manglunki and all speakers.
Feedbacks from EN/STI A. Masi On behalf of EN-STI Mathieu Donze` Odd Oyvind Andreassen Adriaan Rijllart Paul Peronnard Salvatore Danzeca Mario Di Castro.
LS1 – View from Applications BE-CO LS1 review – 1 December 2015 Greg Kruk on behalf of the Applications section.
– Machine Controls Coordinators (MCC): team and role – Overview of renovations during LS1 – Proposal for after-LS1 Commissioning organization ACCOR PROJECT.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Agenda 1 BOSS Meeting - 27/5/ : :10 Introduction and aims of the workshop 10‘ 09: :25 Priorities from OP for PSB and transfer lines 15'
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Proposal: Use of ECRs for “Controls” Changes and Renovations Rende Steerenberg, Samy Chemli, Marine Gourber-Pace, Klaus Hanke, Verena Kain, Bettina Mikulec,
The OP Viewpoint on the Accelerator Complex Controls Renovation R. Steerenberg on behalf of the OP group Accelerator Complex Controls Renovation Workshop.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
Dr. José Miguel JIMENEZ LS2 Project Leader, CERN 1 LS2 Days 30 th September2015.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
TCR Remote Monitoring for the LHC Technical Infrastructure 6th ST Workshop, Thoiry 2003U. Epting, M.C. Morodo Testa, S. Poulsen1 TCR Remote Monitoring.
Contents  Samplers and OASIS  New Controls Platform & Strategy  CTF3 Mini Pilot Project  Concluding Remarks IEFC Workshop, March 2011 Rende.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
AB-CO Exploitation 2006 & Beyond Presented at AB/CO Review 20Sept05 C.H.Sicard (based on the work of Exploitation WG)
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
H2LC The Hitchhiker's guide to LSA Core Rule #1 Don’t panic.
LS1 Review BE-CO-SRC Section Contributions from: A.Radeva, J.C Bau, J.Betz, S.Deghaye, A.Dworak, F.Hoguin, S.Jensen, I.Koszar, J.Lauener, F.Locci, W.Sliwinski,
Operations Coordination Team Maria Girone, CERN IT-ES GDB, 11 July 2012.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
PS Complex Controls Renovation S Baird AB/ABP ATC/ABOC Days: Session Jan 2008.
LS2 Safety Preparation Thomas Otto, LS2 Safety Support Officer for LHC
Framework Schedule from EYETS 2016 to LS2
Update on the Critical Path of the PS Booster Schedule for the EYETS
Status and Plans for InCA
Injector De-cabling Project
Evolution and future of the Access safety and control systems
LINAC4 50 MeV phase BIS STATUS
Looking back on 2014 and Perspectives for the MPE Group in 2015
Installations, modifications, consolidation in 2005:
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
LIU, ABP-CWG, PBC, miscellaneous
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
How to run ions in the future?
James Ridewood BE-OP-SPS
Overview & baseline of LS2 and roadmap for CRG
CF Scope, Management & Organization
Radiation Working Group RADWG
Presentation transcript:

Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities after long stops V. Kain, B. Mikulec, members of IRWG 1

Introduction  Chamonix ‘14: rocky injector start-up after LS1  Injector Re-commissioning Working Group was put in place by the IEFC to ensure more efficient start-up after the next long shutdown  Members of each machine/facility (often shifters) and EN/MEF worked together for a year to come up with “new/different” strategy for the re-commissioning after long stops –2 members per machine/facility –LINACs, SPS, PS, PSB, ISOLDE, LEIR, AD, experimental areas –Also had input from the LHC –EN/MEF: thanks!!!  Meetings in indico: 2 IEFC - Injector Re-commissioning WG

Main proposed improvements 1. Preparation of check lists –Skeleton prepared by working group –Each machine fills in check list  Polarity checks will become obligatory. Convention to be established OP 2. 1 (or 2) person per machine/facility in OP responsible for machine preparation –Re-commissioning Coordinators 3. Start testing earlier –With equipment experts in dry runs: “full” vertical slices with “all” interfaces IEFC – Injector Re-commissioning WG3

Status of check lists  Work in progress  To be finished with the end of the YETS IEFC - Injector Re-commissioning WG4 Example from PS check list

Re-commissioning Coordinator  At the heart of the OP machine preparation: re-commissioning coordinator(s)  Role definition: EDMS ; distinction from MEF super-intendant definedEDMS Summary:  Contact person for EN/MEF before and during shutdown  Follow all modifications/activities during shutdown –And prepare the testing period accordingly  Establish planning of dry runs with equipment experts and EN/MEF –Dry runs/ machine tests will be part of the MEF planning  During hardware tests: organize daily coordination meetings to plan activities of the day  Check lists: ensure completeness of check list before each machine preparation; track evolution of tests during machine preparation period 5IEFC - Injector Re-commissioning WG

Re-commissioning Coordinators  LINACs: D. Kuchler  PSB: A. Akroh & B. Mikulec  ISOLDE: M. Lozano Benito & J. A. Rodriguez Rodriguez  PS: M. Delrieux & O.Hans  AD: B. Lefort  LEIR: J. Axensalva  SPS: S. Cettour-Cave & J. Ridewood 6IEFC – Injector Re-commissioning WG

A propos: Start to test earlier  tests from control room with operational interfaces as early as possible  collaboration of experts and OP:  provide ideal testing environment  extra coordination effort: re-commissioning coordinator  end result:  big upgrades less risky  equipment better prepared, better tuned, better integrated 7 Machine Preparation: tests, dry runs Beam Check out Beam Hardware Tests Shutdown Access Restricted Access No Access foreseen time In the schedule When to re- commission EN/MEFOP Responsible IEFC - Injector Re-commissioning WG

Feedback from equipment groups  Better testing environment and coordination to guarantee better testing environment: –Very welcome  Planning will have to be established early enough before shutdown –Impact on infrastructure readiness can be big IEFC - Injector Re-commissioning WG8

Open issue from last IEFC status report  How to deal with modifications?: upgrades instead of downgrades –controls interfaces (e.g. FESA classes) for equipment  How to guarantee that all requirements are still fulfilled after “upgrade”? –Fulfills all hardware specifications –Fulfills all operational requirements –Fulfills controls standard  Solution: new proposal from CO3 committee: –Prepare “controls change request document” –One part to be written by equipment expert –One part to be written by controls expert –One part to be written by OP IEFC - Injector Re-commissioning WG9

Summary and final remarks  The IRWG had a mandate for a year and has used this time to propose a different (better) re-commissioning strategy for the injectors (proposal also for experimental area, but not enforced) –check lists –re-commissioning coordinators –be proactive: OP starts testing earlier and helps equipment teams to have optimum test environments  The challenge now will be to finish check lists, define typical test order per machine and help re-commissioning coordinators to grow into their roles.  The IRWG has come to an end  From next year onwards: regular re-commissioning coordinator meetings IEFC - Injector Re-commissioning WG10

IEFC - Injector Re-commissioning WG11