Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on.

Similar presentations


Presentation on theme: "Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on."— Presentation transcript:

1 Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on procedure for injectors for end of september  Machine responsible should come to meetings already NOW!!!! Injector Re-commissioning WG1 Machine Preparation Beam Hardware tests Beam Check out Access possible No access foreseen time Machine responsible point of view Equipment expert point of view Deadline: controls readiness

2 Feedback from MEF (II)  We will start discussing machine responsible per machine soon  Need name per machine for September Injector Re-commissioning WG2

3 WHAT TO TEST, HOW TO TEST Injector Re-commissioning WG3

4 As this was not clear last meeting…  Essentially: try to run the equipment in the same way, as you would with beam, without beam. Examples:  Power converters: –Timing cycle loaded –Generate operational function for a given cycle.  Optics loaded  Transfer functions OK –Drive (= load the settings with the operational application) –start and stop with operational application (timing, sequencer) –Current acquisition –Check ripple –Check whether power converter can follow well –Imin OK. –Check logging –Check fixed display, page 1 signals, OASIS acquisition, FEI and SIS –… Injector Re-commissioning WG4

5 A few more remarks concerning testing  Example: preparation for operation of HiRadMat: dry run –HiRadMat cycle, extraction events on –Extraction pre-pulse generation –Check acquisition of all BI in extraction region and transfer lines:  Operational applications: thresholds generated,…  Logging –Try to calculate kick in the transfer line with YASP  Check whether can send it…verifies generation, etc… –Check interlocks and obtain green light –Move TEDs (depends on access conditions) –Pulse extraction kickers with energy tracking system Injector Re-commissioning WG5