DUNLEITH LANE DRAINAGE SYSTEM Justin Lyle and Cody Binder Senior Design Advisor: Mohamed Zeidan Construction ET 10/08/2014.

Slides:



Advertisements
Similar presentations
Site Grading Site Grading Civil Engineering and Architecture
Advertisements

Robert Adkins Et 494 Instructor: Dr. Cris Koutsougeras Advisor: Mr. Rode 12/04/2013.
Robert Adkins Et 493 Dr. Kris Koutsougeras Advisor: Dr. Rodi.
Documentation and Analysis of Flash Flood Prone Streams and Subwatershed Basins in Pulaski County, Virginia Anthony Phillips Department of Geography Virginia.
ET-493 Senior Design By: Brian Toomer Advisor: Mr. Rode’
MSc project specification Unit PJ45P Dr Jim Briggs
Steel Building Apartment- Design and Build
Architectural Drawings
ET 493 – Senior Design Southeastern Louisiana University Jarrett Johnson Mechanical Engineering Technology Instructor: Cris Koutsougeras Advisor: Mohammad.
Steel Building Apartment- Design and Build Sutton Yanosky ET494 – Dr. Cris Koutsougeras Advisor –Mr. Rode.
Design and Technology – Rain Gauge Project
 Hydraulic Log Splitter ET 493- Senior Design One Jordan Millet Ridge Bourgeois Marcus Millet Advisor: Dr. Junkun Ma Teacher: Dr. Cris Koutsourgeras.
Baldcypress and Water Tupelo Tree Pot Shelter By Clyde Walker Jr. INSTRUCTOR: DR CRIS KOUTSOUGERAS ADVISOR: DR. JUNKUN MA FINAL PROPOSAL PRESENTATION Southeastern.
Baldcypress and Water Tupelo Tree Pot of Protection (POP) By Clyde Walker Jr. INSTRUCTOR: DR CRIS KOUTSOUGERAS ADVISOR: DR. JUNKUN MA FINAL PROPOSAL PRESENTATION.
DUNLEITH LANE DRAINAGE SYSTEM Justin Lyle and Cody Binder ET 493- Senior Design Advisor: Mohamed Zeidan Construction ET 10/08/2014.
Steel Fabrication & Erection of Belle Chasse Primary School Belle Chasse, LA Derek Duhon ET Instructor: Chris Koutsougeras Advisor: Edward Rode’
By: Brian Toomer ET-494 Senior Design Dr. Cris Koutsougeras Advisor: Mr. Rode’
Jacob Ruiz W# ET Senior Design Instructor: C. Koutsougeras Advisors: R. Rode May 9, 2014 Jacob Ruiz W# ET Senior Design Instructor:
Chapter 4 The Project. 2 Learning Objectives Third phase starts after a contract is drawn up and ends when the project objective is accomplished; final.
Fluid Mechanics –I Surveying –I Mechanics of Solids Building Materials
Project Scoping Fundamentals Alan Lively Project Delivery Specialist Local Government Section April 6, 2010.
Category-2 Biology Denver Session 6 Changes to the exam structure.
Senior Design Project Office Building By: Heath Yeager ET – 493 Spring 2014 Advisor: Mr. Rudolph Rode.
“Do Green” Two Options: Prescriptive Custom Prescriptive- -Must be running a MODULATING ROTARY SCREW AIR COMPRESSOR -Must be 75 Horsepower or Less Custom-
RBM and Asset Strategy.
MARE 103 Finding (and Landing) an Advisor. MARE 103 Finding an Advisor.
BASICS IN IRRIGATION ENGINEERING 2.1. Planning Irrigation systems 2.2. soil-plant-water relation – over view 2.3. Crop water requirement 2.4. Base, delta.
1 Chapter 4 Analyzing End-to-End Business Processes.
Senior Design II proposal A step-by-Step review. What is Senior Design?  Senior Design is a sequence of two courses during two consecutive semesters.
HUNTING CAMP FACILITY BY: Ryan Fremin ET 493 Senior Design Construction Engineering Technology Professor: Dr. Koutsougeras Advisor : Mr. Rode.
Nathan Davis Steven Reid Kristen Ulmer Graduate Assistant: Nathan Dye.
HUNTING CAMP FACILITY BY: Ryan Fremin ET 494 Senior Design II Construction Engineering Technology Professor: Dr. Koutsougeras Advisor : Mr. Rode.
Visioning and Objectives. Forest Or Trees What did you see first?
Senior Project 24’x24’ structure By: Andrew LeBlanc ET-493 Fall 2013-Spring 2014 Advising by: Rudolph Rode and Byron Patterson.
Progress presentation
What is project management?
Managing programs that promote personal effectiveness.
Chapter 3 Facility Design and Construction. Chapter Objectives 1.Describe the process of facility design and construction 2.Demonstrate proficiency in.
What do you observe in the two pictures? AB Which seems well-levelled, A or B? Why? What are the benefits of a well- levelled field?
ET 493: Senior Design Design of a New Hammond Head Start Center By: Cody Menard and Taylor Bishop Instructor: Dr. C. Koutsougeras Advisor: Mr. R. Edward.
1% Sales Tax Commission Board Meeting June 3, 2015.
NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET Senior Design II.
NEW MEDICAL FACILITY BUILDING By: Vincent Cannatella and Shelbi Remy Advisor: Edward Rode Instructor: Cris Koutsougeras ET Senior Design 1.
Systems Analysis Lecture 5 Requirements Investigation and Analysis 1 BTEC HNC Systems Support Castle College 2007/8.
ET 493 – Senior Design Design of a Multi-Office Building BY: WOODROW WILSON INSTRUCTOR: DR. C. KOUTSOUGERAS ADVISOR: MR. R. EDWARD RODE.
© Goodheart-Willcox Co., Inc. Permission granted to reproduce for educational use only 1 UNIT 6 Fields, Careers, Work Skills.
Rob Connatser NSS Instrument Work Packages and XLPM.
Detailed planning for fish farm construction Once the site has been selected, then initiation of planning begins. There are two main related components.
Welcome to the Libertyville Stormwater Master Plan Open House
Commercial Office Building
Commercial Office Building
Design of a Commercial Shopping Center
Multistory Office Building
ET 494: Senior Design Design of a New Hammond Head Start Center
Site plan The plat map A plat map is the first step in development of a site plan. It delineates property lines with bearings, dimensions, streets, and.
Commercial Office Building
Project Based Research
Instructor: C. Koutsougeras
MODULE 2 – Project Introduction
Dunleith Lane drainage Spring 2015
Software Engineering I
ESTIMATION Estimation is the scientific way of working out the approximate cost of an engineering project before execution of the work. It is totally different.
By: Cody Menard and Taylor Bishop Instructor: Dr. C. Koutsougeras
NEW MEDICAL FACILITY BUILDING
Graphic Design Semester 1 Final Exam
Reportnet 3.0 Database Feasibility Study – Approach
Multi-Family Fourplex Apartment
NDC Denver Pilot Project- CASIS
Senior Design Project Prepared for: Dr. Koutsegeras Advisor: E. Rode
Presentation transcript:

DUNLEITH LANE DRAINAGE SYSTEM Justin Lyle and Cody Binder Senior Design Advisor: Mohamed Zeidan Construction ET 10/08/2014

Objective  To understand what the drainage problem is on Dunleith Lane in Mandeville, Louisiana.  Once the problem is fully understood, formulate the most cost efficient way to correct the problem.

Overall Vision  Repair the drainage issue on Dunleith Lane  Reduce the amount of standing water in the ditches after storms  Prevent any flooding from happening in the streets or the back yards of the occupants

Research on Drainage Correction  Research different ways that different drainage issues are corrected  See how this particular drainage problem compares to other common drainage issues  Research flow rate formulas and how they will apply to the drainage on Dunleith Lane

Deliverables  Through the use of surveying and soil mechanics we will be able to understand and evaluate the drainage issue  Drafting will also be required in order to get the drawing on paper with proper dimensions and elevations applied, AutoCAD will be the tool we use to do our drafting  Some fluid mechanics will also be required in order to calculate the flow rates of the drainage system we plan to establish  Estimating the amount of land that will be need to be cut and filled will also play a role in this project  Lastly, project management skills will be required to go about the project in the most cost efficient manner.

Photos Main drainage that carries water out of the neighborhood to an external drainage system

Photos (continued) Photos show how shallow the drainage system in the neighborhood is in some spots compared to others (causing standing water to accumulate

Timeline (1 st Semester)  10/8- Proposal/Power Point  10/13- Receive Permission from Homeowners  10/19- If possible receive any existing drawings of the land  10/27-Take detailed pictures of area  11/2-Measure Dimensions of neighborhood  11/10-Create Preliminary drawings with dimension  11/17-Survey the Area  11/24-Analysis of the collected data/establish problem  12/1- Complete final presentation (first semester)

Timeline (2 nd Semester)  1/27- Proposal  2/5- Establish flow rate of current system  2/16- Research correcting similar drainage issues  2/26- Create ideal drainage system  3/5- Calculate how much will be cut and filled  3/18- Create drawing of new system and cut and fill diagram  4/1- Estimate cost of project options  4/15- Create schedule for project  4/29- Establish most cost effective option  5/10- Final Presentation