1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 MICE Funding Agency Committee Technical Status of the MICE Project Contents: Technical organisation of project Target Decay solenoid Infrastructure Moving.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Subsystem Reviews Reviews this week: RFCC modules RF Power Infrastructure MICE Infrastructure LH2 system.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
CMPB Alain Blondel 14 April STATUS OF MICE.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Project manager report paul drumm CM16 October 2006.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE Collaboration meeting (CM20) At RAL 10 – 13 Feb 2008 AFC Magnet – Status and Progress W. Lau, Oxford University.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Norman McCubbin1 Report from the Collaboration MICE Project Board (CMPB) Norman McCubbin Director, Particle Physics Department MICE/UKNF Oversight Committee.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
U.S. Muon Accelerator Program: MICE Milestones & Resource-Loaded Schedule M. A. Palmer, Director October 31, 2012.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.
MICE CM35 Status and Goals Alain Blondel 1 WELCOME TO MICE CM35! – Status and Goals - Many thanks to Chris Rogers, Debbie Loader and Rose Hayes for taking.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
MICE – UK Plan Roy Preece STFC RAL DOE Review of MAP Brookhaven National Laboratory 13 th August 2014.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
RLSR 16/4/2015 UK Financial Plan & Risks. Content Finances – FY 2014/15 – Cost to Completion Risks – Top level to completion – R9 working space – Summary.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
UK Project Plan Roy Preece STFC RAL RLSR 26 th October 2015.
MICE CM28 Engineering Session Summary (On behalf of Wing)
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a detailed status report, have a look at: MICE CMPB, 24 th October, 2008

Completion of Infrastructure Very good progress last few weeks: –South wall complete –North Wall, 75% plates fitted –Quench reaction block being cast today –False floor in progress off-site –Believable completion date of 12 th December –Negotiated our way out of fireproof painting - good 2

Target & solenoids Target: –Decided we can re-design shafts and bearings –Get to a new starting point with ISIS –Be ready Easter time next year –Engineering help (Jason Tarrant) for Sheffield Decay solenoid: –No changes from last meeting –But worst case might be to remove complete solenoid Remove North wall Build shield on inside of synchrotron so work in Hall unaffected Do at Christmas Likely cost £25-30K Spectrometer solenoid: –Priority shifted to magnet#2 –Field map as originally planned –We get it late Jan ‘09 3

Phase Two planning We just had the Collaboration Meeting –Reviews of major Phase two subsystems included –Much useful information and milestones emerged –But a lot still to do –No excuses now not to make the project plan! –LH2 project is struggling badly though It’s still competing for effort with Decay solenoid and focus coils – engineering effort MUST be reinforced quickly –Focus coil final design review at Oxford 3 rd November –RFCC modules in good shape – cavities ready for manufacture –Coupling coil review early December 4

Non-MICE costs 2 MVA electrical upgrade will be required by Step Five –Various ways to do it, have budget prices between £200 & £600K –Two year lead time, which I can well believe –Need to worry about it now –RAL’s line on the WFL: ‘it was a CCLRC-specific fund and there’s no STFC equivalent.’ Discussed with Sean Stewart and Paul Hartley – predictable outcome! Requested to put it on the Capital Investment plan Watch this space….. Tony has provided cost centre for railings and door stuff –Does that mean I can use it? 5

Staffing, visitors & admin Transition to Phase Two has been a bit of a shambles –My fault for not being clear about cost centres –Have agreement with Finance that I will adjust staff bookings at end of each month myself –All UK project members being circulated with correct Phase two cost code for capital items Need some clarification of visa & work permits for US types Admin Officer, Rose Hayes starts 29 th October We need to agree her terms of reference/job description, does Susan do this? MICE has had its first lost-time accident – we’re now on the HSE’s radar 6