1 MICE CM31 Schedule summary
Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 30/1011

2 Key Schedule drivers for Step IV
Spectrometer solenoids: Very encouraging progress; reassembly is coming on well We have a realistic and achievable delivery schedule All major technical issues appear to be closed MAP and MICE reviews have been signed off Injection of manpower is clearly paying dividends AFC modules: AFC #1 is in final stages of manufacture at Tesla Eng Pressure point is the OVC (outer vacuum can assembly) Coils for both modules wound, experts agree they are very high quality But delivery date has slipped to end February, 2012 This date urgently needs to be reviewed very carefully with Tesla

3 Key Schedule drivers for Step IV
Hall Infrastructure: Floor plates will be complete in Early December, 2011 AFC moving platform is complete and being tested Much work to be done on South Mezzanine, but not critical to Step IV Liquid hydrogen system: Mechanical, civil and electrical installation of system A is essentially complete Major pre-hydrogen operation safety review on October 4th Went well, formal feedback expected soon This should be the ‘green-light’ for hydrogen testing

4 MICE Top-Level Project Schedule
Step IV Step V Revision date: 30th October, 2011 Note: items in red text are key schedule drivers Items in orange text are high risk items Items in Green text are complete

5 STEP IV Step IV ready...Q4, 2012 Subsystem Date
Spectrometer solenoid #1 + #2 June’12 Fibre tracker #1 + #2 Ready Focus coil #1 Feb’12 LH2 system A Dec ‘11 Solid absorber(s) June ‘12 Liquid absorber Diffuser Aug’12 Virostek plate Feb. ‘12 Substation upgrade EMR installation May’12 Radiation shutter AFC Moving platform #1 Step IV ready...Q4, 2012

6 STEP V Step V ready... Subsystem Date Step IV data-taking complete
Q1 2013 Absorber Focus Coil #2 Q3 2012 LH2 system B RF Amplifiers Q3 2013 RF Infrastructure Successful test of first CC coil RFCC delivery plan complete AFC Moving platform #2 Q4 2012 RFCC Moving platform #1 ISIS Long shutdown start Aug 2014 ISIS Long shutdown end Feb 2015 Step V ready...

7 Milestones prepared by Alan Grant with all latest known data
Only look at Step IV please Steps V & VI cannot be predicted until RFCC delivery plan is known

8 Comment on Step V First coupling magnet is a key component:
First coil has been shipped to US, test plan is taking shape Should be tested by Summer 2012 Represents a major decision point Cryostat and other part drawings should be ready for production readiness review in January 2012 Fabrication of cryostat(s) with US vendors is being explored Discussion in early stages of sharing the MICE CC assembly somehow A CC delivery plan, including the above points, is a vital milestone Early guidance on the first magnet’s destination – MuCool or MICE is required before we can plan Until we know the above two questions, we cannot make any firm statement about the delivery of Step V

9 Step VI Important news: the experiment is now approved financially to Step VI But it has to fit within a flat-cash profile that implies an extended timescale, for example the third FC arrives in However, we have an opportunity to review the situation at the completion of Step IV and to request a more aggressive funding profile As with Step V, it is unwise at this point to publicise any delivery dates that we might not be able to meet