1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: General Technical organisation and status Target update Decay solenoid update Infrastructure.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 MICE Funding Agency Committee Technical Status of the MICE Project Contents: Technical organisation of project Target Decay solenoid Infrastructure Moving.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 RF Power infrastructure Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Infrastructure issues Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
Technical Board and Safety Summary Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE PM Report Outcome of Reviews held at CM22 –Motivation for holding them –Outcomes & actions –Observations & follow-ups MICE Video Conference, 20.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
Muon Ionisation Cooling Experiment Overview
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: General Technical organisation and status Target update Decay solenoid update Infrastructure Detectors and beamline Progress with the cooling channel elements Risks and critical areas Coping with limited resources Andy Nichols, STFC, 27th January 2009

2 Technical Organisation Project organisations seems to be on an even keel: –PM/Technical Co-ordinator – Andy Nichols –Hall Manager/Principal Contractor – Willie Spensley –Hall Foreman – Ash Jamdagni –ISIS liaison – Chris Rogers –MICE Operations Manager (MOM) – rolling monthly post, currently Marco Appolonio –And we have a stable group of well-motivated technicians from both STFC and the widerCollaboration Communication and meetings: –Technical Board – now monthly –Weekly Hall planning meetings – very ‘hands-on’ –Now-weekly MICO (Mice Installation and Commissioning) meetings – each sub work-package has defined milestones that are tracked each week –Project progress is also reported regularly to PSAG & CPMB meetings- –And monthly video-conference to MICE

General Status Since the last OsC meeting, work has continued as fast as possible in order to: –Meet MICE deadlines –Accommodate the experimental programme –Fit with the ISIS calendar –And meet the needs of external collaborators The infrastructure workpackages have dominated last year –Staff usage in these areas has been heavy to meet the above –But it’s just about finished MICE-UK has also had to accommodate some unforseen workload and associated costs: –Serious problems with target and decay solenoid –Remanufacture of rolling platforms –Construction of sliding beamstopper Manufacture of spectrometer solenoids is a concern Production of AFC just starting RFCC coil winding has started Tracker #1 ready for use

4 Target Still have problems with target: –Earlier in 2008, the offline target shaft seized in its bearings –A major problem! –Target group reinforced with more engineering effort –Weekly highly focussed technical meetings now held –Cause of seizure has been investigated, high-speed camera studies show evidence of lateral displacement of shaft during acceleration – could cause unforseen side force on bearings –But no ‘smoking gun’ –Plan in place to design more rigid shaft (for same mass) and simplified bearings –Plan to be ready by April/May 2009 Then in December, the installed ISIS target failed…….

Target Shaft – cross to cyl Stiffer for similar mass Simplified bearings Better aligned Bearings, machined In one setting

Target The ISIS target also appears to have failed mechanically – a magnet retaining piece on the shaft might have vibrated loose and jammed and bent the shaft –But too early to tell for sure The blade tip was melted – not clear of cause or effect Two bits of good news: –No visible dust was generated –The planned upgrade – redesign will address what we believe caused this Redesign will focus on: Shaft cross section – cruciform to cylindrical Simpler bearings – given by above DLC QA – surface finish very important Bearing alignment and profile Generally more rigorous engineering

7 Decay solenoid PSI (Decay solenoid) –Problems with Linde compressor & cooling plant are now fixed –But cooldown earlier in 2008 exposed problem with solenoid: –There are two sets of five S/C coils (1-5) (6-10) with 10 at the downstream end –Coil 10 is normally conducting –Better instrumentation introduced –Much voltage data analysed –Possibility of unforseen radiant heatload on coils at downstream end –Can fix by re-working MLI Multi-layer Insulation –But need to remove cryostat end cap in DSA during ISIS run –MUST finish by March 31 st …

Decay solenoid Decay Solenoid –When it’s fixed, we need to really know it works, so include testing and quench protections, etc, this will take some time –Fixing the solenoid has to take place during next ISIS user run –23 tonnes of fixed shielding has been fixed inside the synchrotron to allow this – a major achievement in a very short time by the installation team. 8

9 Infrastructure Few problems to report: –Both shield walls are complete, except for four plates at North wall – due this week –All galleries and stairways complete –Mound excavation & LH2 ductwork is done –False floor fabrication is done, installation delayed due to hard pieces in concrete and striking water when drilling anchors –All fixed now – every effort bring made to complete by 31 st January –Extract fan on order – non MICE cost –Main door replacement on order – mostly non-MICE cost –Air conditioning, NE corner only – tender for installation started – must complete before 31 st March

10 Infrastructure Rolling platforms 1 & 7 were delivered late 2008 –Unfortunate error by manufacturers – needed re-making –Delay bad but not showstopper –Agreed to contribute to part of cost to maintain progress Electrical work has made good progress –Very clear leadership by DL staff –They initiated user-friendly monthly meetings, all tasks documented and progressed methodically, seamless link with mechanical WPs –Both electrical and mechanical infrastructure WPs in very good technical shape –Now moving to Phase Two tasks…….

Infrastructure 11

12 Infrastructure LH2 R&D project –Has suffered badly due to the decay solenoid work (the same group does both) –Had review during October: R & D hardware had stalled at manufacturer Control system philosophy seemed to be stuck in a loop, blocking progress to full design and obligatory safety reviews But the real problem is lack of qualified manpower –So what’s happened? Visits to manufacturers by Project Engineer & STFC Procurement staff - R&D project has re-started Control system plan and revised milestones to be put to MICE Project at Large during January Authorisation to recruit has been obtained through Technology Dept at STFC – One graduate engineer and one engineer/physicist, interviews in Feb/March Internal ductwork and enclosures designed & ready to tender –Currently this work-package is ‘at risk’

13 Infrastructure & Phase One RF power amplifier refurbishment: –Two CERN units are complete, are now at DL –One DL unit is almost done –CERN units will be first to be tested, early this year –RF project is also suffering from manpower shortage, but VNs have been authorised –RAL staff have visited DL to start off how we actually in- stall the amplifiers in the Hall – not as easy as it looks (of course!) – part of Phase II though

14 Detectors, beamline & tracker Good progress: –TOF0 & TOF1 installed and working –Noise problems with Beam Profile monitors fixed –KL is still robust and working Tracker #1 is ready for integration Now have a dedicated tracker assembly/test area in R8 at RAL Tracker #2 ready for testing Diffuser is in final stages of testing at Oxford, comes to RAL during March 2009 Tracker patch panel has been successfully trial fitted with diffuser

15 Progress with Cooling Channel elements Spectrometer solenoid: –In assembly at Wang NMR in US. Then to FNAL for field map end Feb 2009, at RAL April-June 2009 – currently very late, problems with rad-shield cooling and vent system – a major worry RFCC –In early manufacture at Harbin, China and US. No real problems, successful reviews, delivery to RAL April 2010 AFC –Advanced design stage with Tesla Engineering in UK, problems with coil former design and quench protection mechanism – delivery end December 2009 – two months later than planned

16 Risks and critical areas Focus will remain on Target, Decay solenoid and spectrometer solenoid; the vital ingredients for Step II All of these subsystems have serious problems It is not clear that LH2 project can be delivered on time with the current level of manpower and certainly not with a cut A 2MVA electrical supply upgrade is essential if MICE is to run at steps III & IV –Detailed estimates have been made –It’s £75K –And we need it by early 2010 –Lead time of transformers is 30 weeks –Need to worry now, non-MICE cost, but WFL route has dried up –Last hope is RAL Ops Board…….

17 Coping with limited resources The current funding profile allows step IV running to start at April 2010 Depends on all subsystems being in place, but it’s the baseline we have It’s clear that Phase II is overspending fast, need to put brakes on: One idea: –FY 09/10 will be dominated by arrival of spectrometer solenoid, late spring 2009 –It’s the major part of step II, one way of slowing down is to only make step II in this period –& tailor the manpower profile to suit – we might need to make 50% cut –Capital would be reduced – some equipment already committed

Coping with limited resources Capital Requirement Until April 2009 – essential items –NE Air con system………………………………..62K –Rolling platform hardware…………………….2K –Spectrometer solenoid hardware…………….0.75K –Hall consumables, PPE & lifting……………...15K –Tent & frame for DS work………………….…1K –Bottles dry air, pipes & regulator…………...1.5K –MLI & tape for DS……………………………….1.5K –Service Linde plant………………………….....5K –Target re-manufacture………………………..20K –Fee for CDM consultancy…………………..…5K –Synchrotron steel shielding………………….16K –Compressor stands for tracker readout….10K –Step II electrical hardware…………………..78K Total, £217.75K

Coping with limited resources Non-essentials, or can be delayed –Extract fans & oxygen depletion monitors……10K –Spectrometer solenoid lifting frame……………5K –PPS hardware, main Hall…………………………2K –RF tubes…………………………………………..…144K –RF Co-Ax transitions………………………………12K –RF consumables……………………………………1.5K –MICE vac system pumping rigs…………………18K –Diffuser hardware…………………………………5K –TOF 2 support parts………………………………3K –LH2 ducting and enclosures…………………….30K –Payment for LH2 R&D hardware……………….52.5K –H2 system relief valves & cryocoolers…………9K –LH2 instrumentation………………………………10K –AFC payment to Tesla…………………………….364K Total, £666K

Coping with limited resources But there’s a big downside: –The International schedule will not be met and the UK’s reputation put at risk. If we make a staff effort cut: –It must be against some type of de-scope or slowdown, as above –We must not attempt the same project scope with half the staff, otherwise…… –Remaining project staff would be too highly stressed – this is a very serious concern –Clearly this is the start of a significant discussion