DECKS
Square Corner Framing square
Square Corner triangle
Square Corner Diagonals
LEVEL Water level r12l904owhttps:// r12l904ow
LEVEL String level
LEVEL Builder’s level
POSTS Concrete footings Provide Structural support but NOT lateral Pier blocks
POSTS Pier blocks (continued)
POSTS Concrete footings Provide Structural support but NOT lateral Galvanized post anchor
POSTS Galvanized post anchor (continued) 87Dkw1M
POSTS Galvanized post anchor (continued) How not to…
POSTS Direct burial Provide Structural and lateral support Footing at bottom of hole –Blocks or Concrete
POSTS Direct burial Provide Structural and lateral support Backfill around post –soil or crushed aggregate –dry concrete –wet concrete (must brace post until set) – pCSxD0GYhttps:// pCSxD0GY
POSTS
POST AND BEAM DECK Ledger Attachment to existing building
POST AND BEAM DECK Ledger Use 3” lag screws to anchor into rim joist Expansion bolt if concrete slab foundation
POST AND BEAM DECK Ledger Attach directly to rim joist of house
POST AND BEAM DECK
Beam –Grab beam –Cap beam Beam supports joists Level with bottom of ledger
POST AND BEAM DECK
Joists Joists support deck boards Joist hangers attach to ledger Anchor joists to beam with rafter ties
POST AND BEAM DECK Joists Splice long joist over beam –Overlap –Gusset
PLATFORM FRAMED DECK Constructing freestanding deck
PLATFORM FRAMED DECK Locate posts with batter boards and string
PLATFORM FRAMED DECK Install outside (rim) joists to form box using ½” bolts Rim joists act as the beam, holding joists on hangers
PLATFORM FRAMED DECK Install interior joists
BLOCKING For additional support Blocking: short blocks of wood between joists
DECK BOARDS 2 x 4, 2 x 6, or 5/4 boards Installed at angle to joists –90 degree or 45 degree
DECK BOARDS
Orientation of grain with bark side up
DECK BOARDS Space using a nail or pencil?
RAILING Extend posts
RAILING Bolt to rim joist
Deck Construction Estimating deck construction –$20 to $24 / square foot