D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Heinz-Dieter Nuhn, SLAC / LCLS Undulator Checkout and Startup Plans November 12, Undulator Checkout and Startup Plans Heinz-Dieter.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
FAC 4/20/06 D. Schultz 1 The SAD and ARR for Commissioning The Status of the SAD Being written as a part of the SLAC Linac SAD The Status of the ARR Design.
Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
John N. Galayda LCLS Facility Advisory November 11, LCLS Update November 11, 2008 Construction Status LCLS Instruments.
Kathleen Ratcliffe LTU Installation October 30, LTU Installation Coordination Kathleen Ratcliffe.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
Paul Emma LCLS Commissioning Status Nov. 11, 2008 SLAC National Accelerator Laboratory 1 LCLS Commissioning Status P. Emma for The.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
M. Reichanadter LCLS Project June 2008 FAC Meeting Report to the LCLS Facilities Advisory Committee Project Management.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
D. Schultz FAC 6/17/08 1 Undulator Travel and Girder Assembly Undulator commissioning Translation limits Interference The plan.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 E. Carrone 1 FEE PPS Status FAC FEE PPS Status Enzo Carrone June 8, 2009.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Geoff Pile LCLS Und. System FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Update FAC Review October 29 th (30 th.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Hal Tompkins Photon October 30, LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Arturo Alarcon Undulator Controls Module Status 11/12/2008 SLAC National Accelerator Laboratory 1 Undulator Controls Module Status.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
John Seeman LCLS December 2, Conduct of LCLS Accelerator Operations John Seeman Assistant Director LCLS Directorate.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
Patrick’s Updates - 8/30/11 (one slide for each of the following) 1.XTCAV Project 2.ASTA Gun Test Facility Instrumentation & Controls 3.Fast wire scanner.
Experimental Facilities Planning
Injector Performance Requirements Conventional Facilities Update
Undulator System Installation
Beam Finder Wire Assembly Undulator System
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LTU/Undulator Installation Status
e-Beams Systems Update
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
Project Status Review May 13-15, 2008.
Electron Beam Systems Wrap-up
LCLS Undulator System Production Management
Conventional Facilities Status
Shutdown Planning & Installation Schedule
E-Beams Systems Manager
LTU/Undulator Installation Status
LCLS Operation in 2009 Roger A. Erickson
Installation Status & Operational Readiness Process
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Electron Beam Systems ETC and Methodology
Undulators Subgroup Summary April FAC Review K. Robinson, J
LCLS e- Beams System Overview
e-Beams Systems Update
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
LCLS e- Beams Systems Manager
Presentation transcript:

D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator System Status Controls Status Installation Readiness Reviews Accelerator Readiness Review Schedule and Budget Linac and Undulator Risks David Schultz

D. Schultz FAC 6/17/08 2 New responsibilities Jim Krebs has joined LCLS as Deputy e-Beam Systems Manager. Enzo Carrone has joined LCLS and the Controls Department as the Deputy Controls Head for LCLS.

D. Schultz FAC 6/17/08 3 E-Beams systems since the last review Injector and Linac/BC2 commissioning is complete. The ‘07 downtime installation went very well. These systems, through linac sector 30, have been handed over to operations. The Undulator vacuum chamber crisis is behind us. The extruded Al chamber was adopted, meets all specs. All chambers and supports are at SLAC. Undulator tuning at the MMF here at SLAC is going well. All Undulators have been received from ANL

D. Schultz FAC 6/17/08 4 LTU and Dump status LTU installation is underway. Supports, cable plant, rack installation is ongoing. Magnet installation is underway. Components are RFI with few exceptions: Vacuum chambers are arriving from the vendor 2 of 3 dump magnets are in-house Dump vacuum assembly is nearing completion Spot shielding is in fabrication (and RP). Contracts are in place for dump steel and dump component installation.

D. Schultz FAC 6/17/08 5 LTU system installation 6/10/08

D. Schultz FAC 6/17/08 6 Control racks in service building 911 6/10/08

D. Schultz FAC 6/17/08 7 Undulator status Most of ANL deliveries are complete, or soon will be. Quads, Vac chambers and supports, Girders and supports, bellows, ion pumps, … Quad measurement underway at SLAC 17 RFI (6/11), all RFI by 6/30 16 Controls racks here, the rest are due 6/23 Girder assembly is underway 2 RFI, + 3 assembled, + 3 partially assembled

D. Schultz FAC 6/17/08 8 Undulator girder assembled at SLAC 4/15/08

D. Schultz FAC 6/17/08 9 Undulator supports installed in the tunnel 6/12/08 64 pedestals installed, 15 aligned

D. Schultz FAC 6/17/08 10 Undulator status RF Beam Position Monitor Have had productions problems with developing the process attaching the vacuum windows onto the body. Now have a process which works. Developed and done at ANL (not at the vendor). 11 BPMs RFI at SLAC, all (40) BPMs at SLAC 7/31

D. Schultz FAC 6/17/08 11 Undulator status Beam Finder Wire Have had problems with wire position reproducibility. Solution is in hand, production at ANL is steady. 15 BFWs at SLAC, 7 RFI, all BFWs at SLAC 7/6.

D. Schultz FAC 6/17/08 12 Controls status Cable plant installation for the LTU, Undulator and Dump is underway, the schedule is tight. Power supply racks are RFI. I&C racks have arrived (late). Now loading and testing the racks in the lab. Undulator controls racks arriving from ANL. 16 this week, the rest next week. Software has been checked out at ANL. Safety and protection systems (PPS, MPS) are on track.

D. Schultz FAC 6/17/08 13 Installation Readiness Reviews Installation Readiness Reviews were held 2/26/08 for the LTU and Dump. 4/17/08 for the Undulator. Recommendations: Appoint an oversight person for Undulator integration. Jim Krebs has been appointed Review cable plant  girder installation conflicts. Installation sequence has been altered to minimize impact.

D. Schultz FAC 6/17/08 14 LCLS Accelerator Readiness Review Safety Assessment Document A SAD and ASE is being prepared to include the LTU through the electron dump. Writing has started, due date is July The SAD will need revision in 2009 for the FEE, and NEH through FEH. Accelerator Readiness Review (ARR) The ARR will be held this November for commissioning to the electron beam dump. Bob Casey of BNL to Chair Readiness Reviews for the FEE, NEH and FEH hutches will be done later.

D. Schultz FAC 6/17/08 15 LCLS installation and commissioning time-line LTU/Und/Dump Install LTU/Und Comm. Re-commission Inj/BC2 to SL2 First Light in FEE PEP-II run ends FEE/NEH Install PPS Cert. LTU/Dump FEH Install CD-4 (7/31/2010)X-Rays in NEH First Light in FEH NEH Operations/ Commissioning J J F F M M A A M M J J J J A A S S D D J J F F M M A A M M J J J J A A S S O O N N D D J J F F M M A A M M J J J J ON A A Down PPS A A M M now Linac/BC2 Commissioning FEE Comm. April 18, 2008 FEH Hutch BO

D. Schultz FAC 6/17/08 16 Issues Beneficial Occupancy is late. We have begun Vacuum system assembly anyway Of particular concern is temperature stability and cleanliness in the Undulator Hall. We will not be able to install girders until these concerns are satisfied. Dump installation is also starting to suffer. Component deliveries from vendors (LTU vacuum chambers, BYD magnets) and from ANL (BFW, Quad spools) continue to be worrisome, but not show-stoppers

D. Schultz FAC 6/17/08 17 Summary Installation is underway in the LTU, Undulator and Dump Late: area co-occupancy and D-B contract release. Component availability will not be a limiting factor. Undulator components are at SLAC awaiting installation. Parts are arriving now in sufficient quantity to support girder assembly. Girder assembly is near the Project critical path, and ahead of that schedule. Controls installation is underway but, as usual, all else must be done before controls checkout can be concluded.