1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 RAL Integration Issues MICE Collaboration Meeting, Osaka, August 1-3, 2004 Elwyn Baynham, Paul Drumm, Yury Ivanyushenkov, Tony Jones RAL.
1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Infrastructure issues Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
CMPB Alain Blondel 14 April STATUS OF MICE.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
M. Bonesini - MICE Inst Meeting M. Bonesini INFN Milano TOF installation plans.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
Francois and Lau EATM 17 July 2012
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Bunker Project Schedule/Budget
Presentation transcript:

1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report, have a look at: MICE VC, 17th July, 2008

2 Phase One Installations to date South shield wall: –Support structure now complete –Over half the plates fitted –Minor mechanical niggles, but nothing we can’t fix, but see later! –Based on current progress, we’ll finish mid-September –BUT: Charles Day have stopped work due to contractual dispute with RAL – supply of steel plates has stopped (they want another £5K due to steel price, but they took contract at a fixed price – letter from RAL Contracts on the way) Decay solenoid: –Re-worked compressor now installed, but still problems, serious oil spillage on 9 th July – a reported H&S incident. No running until this aspect is cleared –Solenoid functional by 28 th July – despite above, this date still holds Target: –New on & offline targets to RAL by 21 st July –Installation in R78 and ISIS over August shutdown –Current target still reliable – must fully understand need to change existing, now well-proven, target – formal meting with ISIS w/b 21 st July

3 Phase One remaining items North Shield Wall support structure: –Bottleneck with RAL Procurement now cleared – over two months delay –£50K firm quote –Order now placed, but +£10K revision to quote while RAL dithered! False floor –Magnetic modelling now verified – OK –Design and M/F drawings complete –Out for tender –£20K estimate DSA roof and walkways –Design complete – quotes expected in two weeks –£10K estimate

4 Phase One remaining items Upgrade compressed air supply: –In progress –Estimate £12K Roof-extract fan –Somehow escaped from previous estimates –Estimate £15K Fencing on R5.2 roof –Another ‘new’ thing, but a safety obligation –Estimate £10K Main Hall door upgrade –ISIS pays apparently RF refurbishment –Restoration/Installation costs - £30K, firm quote

5 Phase One Remaining items LH2 Installation: –No new information received –But September installation for prototype system will almost certainly slip to November/December 2008 –Manpower estimates need revising upwards –Second HAZOP review needed –Then formal RAL safety review –Both these in September –LH2 commissioning plan also required (Mike Courthold) to be submitted thro’ MICE-ISIS Safety Management meeting. –Prior approval for this from MICE TB

6 Progress with Phase Two Technical Status: –At CM21 I Promised draft of master project plan for each step by 4 th July, but I’ll be late –Step One is making reasonable progress: –TOF0 (in temporary location) and KL are installed, cabling is complete, commissioning of TOF0, starts 14 th July –Sliding beamstop is in manufacture – scheduled for August shutdown, but fallback is to use existing (manually placed) shield blocks. –Permission to run with existing beamstop blocks removed this week for one-off tests with KL & TOF granted –Fixed beamstop parts all here – assembly in August –Tracker #1 cosmic run with FNAL readout in R8 has gone very well –Steps 2 & 3 dependent on delivery of spectrometer solenoids at end August and October – currently on target, but some unforseen cooldown problems at vendor –Integration of these should not be under-estimated, is being worked into the above plan

7 Progress with Phase Two TOF0 in temporary position Tracker #1 cosmic Run in R8 KL In position

8 Worries Contractual problem with Charles Day –Potential for them to pull out, 70 tonnes of steel yet to be delivered –Theirs was the only sensible offer out of around twenty approaches –Don’t have a fall-back