Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead.

Slides:



Advertisements
Similar presentations
Federal Aviation Administration International Civil Aviation Organization INFORMATION PAPER AERONAUTICAL COMMUNICATIONS PANEL (ACP) 20th MEETING OF WORKING.
Advertisements

Federal Aviation Administration Data Communications Program DCIT Update MEM ATCT DCL Trials To:DCIT Plenary From: Matt Maki Date:
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #24 En Route Route Clearances Draft Use Case Introduction Boeing –
Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #26 Plenary From: Matt Maki / DCL Trials Lead.
Federal Aviation Administration Data Communications Program DCL Trials DCIT Update MEM ATCT To:DCIT Plenary From: Matt Maki Date:
Federal Aviation Administration Data Communications Implementation Team (DCIT) Departure Clearance Trials (DCL) Test Status DCIT Meeting # 22 Washington,
Federal Aviation Administration Data Communications Implementation Team (DCIT) Trials Activities/DTAP Update Schedule Timelines Matt Maki.
Federal Aviation Administration AOC/FOC Interface for Data Comm Production System To: AOC WG From: Data Comm Production Sub-Team Date: 07/11/12.
Federal Aviation Administration Data Communications Program Data Comm Trials and Production Requirements: High Level Impact Presented To: DCIT #23 Plenary.
Federal Aviation Administration Data Communications Program DCL Trials DCIT Update MEM ATCT To:DCIT Plenary From: Matt Maki Date:
Federal Aviation Administration Data Communications Integration Team (DCIT) DCL Trials test activities Presented to:DCIT # 15 By:Peter Muraca FAA Date:May.
Harris.com Michael Earl Systems Engineering, Trials and OPR Trials Status and OPR Update.
Presented to: DCIT #12 Plenary By: Andy Fry, Thane Inc. Date: January 12, 2012 Federal Aviation Administration Data Communications DCIT Update Flight Deck.
Data Link Communications
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #25 Agenda 07/17-07/18/2013 Harris Corp – Washington, D.C.
Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT23 Update To:DCIT23 Plenary From: Matt Maki Date:
Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca.
Presented to: DCIT FDWG Breakout Session By: Andy Fry, Thane Inc. Date: July 11, 2012 Federal Aviation Administration Data Communications DCIT #16 Flight.
Federal Aviation Administration Data Communications Program Operational Trials in Domestic Airspace Presented to:Data Comm Implementation Team (DCIT) By:Jerry.
Federal Aviation Administration Data Communications Program Departure Clearance (DCL) Trials DCIT17 To:DCIT Plenary From: Matt Maki, Trials Lead Date:
Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig.
Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT25 Update To:DCIT25 Plenary From: Matt Maki Date:
BOEING is a trademark of Boeing Management Company. Copyright © 2011 Boeing. All rights reserved. OMWG and All Working Groups DCIT-39 report out 11 March.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #33 Agenda 6/4/2014 Harris – Washington, DC.
EWR DCL Flight Tests Capt Gregg Kastman MD-11 Flt Trng Sup.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #24 Agenda 06/12-06/13/2013 Boeing – Arlington, VA.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #21 Plenary 02/01/2013 To: DCIT By: Gregg Anderson.
EWR DCL Trial Update Capt Gregg Kastman MD-11 Flt Trng Sup.
Presented to: By: Date: Federal Aviation Administration DCIT 41 Plenary Mark Patterson, FAA, AFS June 2015 Flight Standards Update.
Presented to: By: Date: Federal Aviation Administration DCIT 40 Plenary Mark Patterson, FAA, AFS April 2015 Flight Standards Update.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT Meeting 08/24/2011.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #23 Plenary 05/09/2013 To: DCIT By: Gregg Anderson.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT En Route Services Survey Results A Review 5/8/2013.
Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT Update To:DCIT Plenary From: Matt Maki Date:
Presented to: By: Date: Federal Aviation Administration DCIT 44 Mark Patterson, FAA, AFS Nov 2015 Flight Standards Update.
Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #44 Plenary DCL Trials.
Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig.
Presented to: DCIT By: Andy Fry, Thane Inc. Date: September 26, 2013 Federal Aviation Administration Data Communications DCIT FDWG Climb Via Discussion.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT 37 Plenary Agenda December 10, 2014 Harris Corp Washington, DC.
GROUND-GROUND STRINGAIR-GROUND STRING AVIONICS CSP AOC DTAP NESG HADDS.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #15 Plenary 05/31/2011 To: DCIT By: Gregg Anderson.
| 1 harris.com Matt Maki DCL Trials Lead DCL Trials Decommissioning Plan 29 Sep 2015.
Federal Aviation Administration AOC/FOC Interface for Data Comm Production System To: AOC WG From: Data Comm Production Sub-Team Date: 08/22/12.
Federal Aviation Administration Presented To: IPACG/39 Presented By: Dennis Addison, FAA Date: February 5-6, 2014 IP06: ADS-B In-trail- Procedure (ITP)
Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #31 PLENARY DCL Trials.
Federal Aviation Administration AOC/FOC Interface for Data Comm Production System To: DCIT AOC WG From: Data Comm Production Sub-Team Date: 2/1/13.
Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status Updates To:DCIT21 Plenary From: Matt Maki Date:
Federal Aviation Administration Data Communications Program Final Investment Decision (FID) – Update on May 30, 2012 Presented to:SC-214/WG-78 Plenary.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #9 Meeting 09/21/2011 To: DCIT By: Gregg Anderson.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCL Trials ”T e s t S t a t u s” Presented to:DCIT, Meeting #18 Presented.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #22 Plenary 03/14/2013 To: DCIT By: Gregg Anderson.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #16 Plenary 05/31/2011 To: DCIT By: Gregg Anderson.
Federal Aviation Administration Subscriber Database (SDB) and Web Access To: DCIT AOC WG From: Data Comm Production Sub-Team Date: 3/13/13.
Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT24 Update To:DCIT24 Plenary From: Matt Maki Date:
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #25 Agenda 07/17-07/18/2013 Harris Corp – Washington, D.C.
Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #32 PLENARY DCL Trials.
Presented to: DCIT Flight Deck Working Group By: Andy Fry, Thane Inc. Date: October 12, 2011 Federal Aviation Administration Data Communications DCIT #10.
Federal Aviation Administration Data Communications Implementation Team (DCIT) DCIT #12 Plenary 01/12/2011 To: DCIT By: Gregg Anderson.
International Civil Aviation Organization
EWR DCL Flight Tests Capt Gregg Kastman MD-11 Flt Trng Sup
Ops Metrics.
Data Communications Implementation Team (DCIT)
Data Communications Implementation Team (DCIT)
Data Comm Departure Clearance End To End Summary: (DCIT #27 WG)
Data Communications Implementation Team (DCIT)
Data Communications Program
Outreach & Communications Committee Task Force Update
Presentation transcript:

Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead Date:

Federal Aviation Administration DTAP SW Patch 5.0 Update Included Requirements: -SID NONE (EWR ATC) -MAINT ALT NONE (EWR ATC) -Double TO (MD-11 UM79 Map Redraw) -Dual Contact/Drop Down Remarks (EWR ATC) Discovered automation issues being corrected: -PTR #171 – Early P+30 AH processing -PTR #172 – AGDS Index Management (3000 limit) FAT scheduled for Thales CC: -Early Thales Test Book look 2

Federal Aviation Administration DTAP SW Patch 5.0 Schedule WJHTC Install/SAT – 10/8: -Start of Data Comm lab Functional Testing -Thales and PO Ops Support -MEM/EWR Site Install Go/No-Go Trigger MEM Install/SAT – 10/14-16: -Holiday install -Pre-SAT/SAT procedure development (Airline support) -10/16 PM FDX will fly MD-11 UM79 DCT TO flight as part of SAT (voice read back) -Goal is DTAP RTS for 10/17 FDX AM push EWR Install/SAT – 10/21-23: -Pre-SAT/SAT procedure development (Airline support) -10/21 PM UPS will fly B767 flight as part of SAT (voice read back) -Goal is DTAP RTS for 10/23 evening DCL ops 3

Federal Aviation Administration Build 7 Req Update Down selected Requirements Proposal Evaluation Underway: -Harris/Thales proposal response pending 4 Requirements under consideration: -Flight Deck Response to AOC -Climb Via -Departure Processing -Arrival Processing Formal Harris Task Order CSP Trials Services and DTAP license pick up Oct 1 4

Federal Aviation Administration 5 Running 76% success FDX Crew DCL Familiarity Increasing 2 Performance Issues Discovered: -Early P+30 AH causes inactive SEND button -AGDS Index Management Over 3000 Causes Random DM25 UL Fails FDX GOC Revert to PDC Ops Success Proven Upon DTAP Outage (9/20 AM Push) Continued weekend ZME ERAM Testing: -HADDS Recons triggered -9/ Hr ERAM run planned (0530z z)

Federal Aviation Administration EWR DCL Limited Ops Update UAL 10 Revenue DCL Ops Complete (9/3-17): -B767 ops (LSZH/ZRH, LTBA/IST, SAEZ/EZE) -UAL 757/767 Fleet Tech Mgr/Flight Standards on-site to brief each crew -Agreement with FAA AFS to complete DCL ops before expanded UAL ops (B777 Oct +) DLH, UPS, BAW, FDX Continuing DCL Ops: -DLH 2/day schedule (EDDM, EDDL) -UPS, BAW, FDX continued limited ops -SAS no longer actively participating (Airbus CLR7+ FMS issue) Seeking expanded Airline Participation 6

Federal Aviation Administration Additional Misc. MEM/EWR Items 10/1 Outreach Briefing to the Newark International Carrier Committee (NICC): -Provide Trials overview to attending International Carriers -Solicit interest in new EWR Trials participants 9/18-19 Additional MEM Tech Ops technicians received DTAP Cert Training: -3 techs now certified at MEM -Expands DTAP Re-Cert time options MEM DTAP FDIO Connect Extension Out of Board Approval 9/13: -NAS CCB meeting acknowledge – 9/30 7

Federal Aviation Administration Questions ? KUSA