1 Federal Aviation Administration Data Comm 1 Federal Aviation Administration Key Site Timelines Hal Ludwig & Pete Muraca

2 Federal Aviation Administration Data Comm 2 Accomplishments Since Last DCIT SLC IOC Declared 8/7/2015 IAH and HOU upgraded to TDLS V.12 SW HOU TDLS-ERAM Direct Connect Interface is operational International Flights –Hyphen issue for non-US Flag carriers will be fixed in release on 9/10 –International flights for all carriers only CAF initially (revision by voice only) –Resolved prior to waterfall. Coordinated with first set of waterfall sites – –ZHU ZID ZNY – held first two coord mtgs – On track for IOC at MSY, SDF, and EWR. Aug. 25 kickoff with second set of waterfall sites (ZLA, ZME, ZBW, ZDV)

3 Federal Aviation Administration Data Comm 3 SLC Test Status-IOC Declared Operators Supported Testing leading up to IOC at Salt Lake City ̶ FedEx Express (MD11) ̶ UPS (B767 & MD11) ̶ United Airlines (B737-900) ̶ Southwest Airlines (B737-800) ̶ Harris Corporation (Falcon 9) ̶ US Air Force (KC-135)

4 Federal Aviation Administration Data Comm 4 Path to ISD 2015 10/22 JULAUGSEPTOCTNOVDEC ZLC/SLC IOC 8/7 ZHU IAH IOC 9/10 ZHU HOU IOC 9/30 ZLC ZTL Complete 11/30 IOA Complete 12/09 ISD Phase 3 EAD40 Phase 5 Milestones V12.0.4 11/6 EADXX = ERAM = TDLS = TIMS V12.XX ZLC SLC ZTL Draft v5.1 9/3 Field Activities ZLC/ZTL Nat’l Site Failover ZLC/ZTL Nat’l Site Failover CPDLC - SLC ZLC/SLC DFV Dry run & Conduct ZLC/SLC DFV Dry run & Conduct Phase 4 8/19 9/10 9/30 ZHU/IAH/HOU DFV Dry Run & Conduct ZHU/IAH/HOU DFV Dry Run & Conduct IAH/HOUEnhanced CHI ZHU EAD30 Install TDLS 9/18 V12.0.5 12/18 ZLC EAD30 Install 8/7 ARTCC EAD40 Install 8/27 Test only TIMS You are here P1 ZHU ERAM uplevel to DC ZHU ERAM uplevel to DC 7/6 - 7/9 P0 IAH TEDC IAH TEDC HOU TEDC HOU TEDC 7/1 8/13 V12.0.3.xxx 9/10 SLC BOI V12.0.2 Int’l Flights IAH HOU 7/21 ZLC/SLC TO & FM Testing ZLC/SLC TO & FM Testing 7/9-11 7/22 SLC BOI IAH HOU 7/23-25 9/10 P3 7/29 – 8/5 8/3-4 8/6-8/12 EAD30 7/30 - 8/1 ZLC/ZHU Parent/Nat’l Integration ZLC/ZHU Parent/Nat’l Integration P4 8/13-17 SLC BOI IAH HOU SLC BOI IAH HOU V12.0.2 7/15 SLC BOI 7/16-18 V12.0.2 TIMS V12.0.3 8/14 SLC BOI IAH HOU 8/15-17 11/21 Thanksgiving 11/3012/19 Christmas 1/4 8/18-20 ZTL EAD30 Install 8/17 ZTL Network Connectivity Testing & SSM-220 ZTL Network Connectivity Testing & SSM-220 8/31 9/4 8/5

5 Federal Aviation Administration Data Comm 5 KIAH – Carrier DFV Participation Lead-Up Timeline

6 Federal Aviation Administration Data Comm 6 KIAH Date Testing Window Tentative ERAM Dispatch (FPL Filing) Local Flight Deck Remote Flight Deck AOC System Testing w/ WJHTC 08/19 – 08/21 W, Th, F Mid-Shift Active and Back-Up mode Testing w/ Carrier 08/22 – 08/23 Sa, Su Mid-Shift Active and Back-Up mode Testing w/ Carrier 08/24 – 08/27 M, Tu, W, Th Mid-Shift or Day & Swing Shift (as Aircraft avail.) Active and Back-Up mode Carrier File and Fly 08/28 – 09/03 F, Sa, Su, M, Tu, W, Th Normal Ops Active and Back-up mode IOC9/3 Note: Mid-Shift is 2200-0300 or 0500 (Local)

7 Federal Aviation Administration Data Comm 7 IAH Test Status Conduct DFV field testing @ IAH with the following major carriers and test facilities: –UPS –UAL –FDX –FAA Technical Center Bench Avionics (B757 / 767, B737)

8 Federal Aviation Administration Data Comm 8 KHOU – Carrier DFV Participation Lead-Up Timeline

9 Federal Aviation Administration Data Comm 9 KHOU Date Testing Window Tentative ERAM Dispatch (FPL Filing) Local Flight Deck Remote Flight Deck AOC System Testing w/ WJHTC 08/24 – 08/26 M, Tu, W Mid-Shift Active and Back-Up mode Testing w/ Carrier 08/27 – 08/28 Th, F Mid-Shift Active and Back-Up mode Testing w/ Carrier 08/29 – 09/02 Sa, Su, M, Tu, W Mid-Shift or Day & Swing Shift (as Aircraft avail.) Active and Back-Up mode Carrier File and Fly 009/03 – 09/10 Th, F, Sa, Su, M, Tu, W, Th Normal Ops Active and Back-up mode IOC9/10 Note: Mid-Shift is 2200-0300 or 0500 (Local)

10 Federal Aviation Administration Data Comm 10 HOU Test Status Conduct DFV field testing @ HOU with the following major carriers: –UPS –SWA –UAL –FDX –FAA Technical Center Bench Avionics (B757 / 767, B737)

11 Federal Aviation Administration Data Comm 11 AOC Interface Scorecard Completed testing with UPS, FDX, and UAL Working with USAF TACC to test Interface SWA working based on SLC testing.

12 Federal Aviation Administration Data Comm 12 Discussion Items TDLS Updated IRD Review –IRD Rev A has NAS CCB approval Interface is available for test (WJHTC and IFCET) –IRD Rev B NAS CCB approval SDB Inputs –Web interface activation delayed for additional testing. SLC Daily Test Coordination Meeting Feedback