Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #32 PLENARY DCL Trials.

Similar presentations


Presentation on theme: "Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #32 PLENARY DCL Trials."— Presentation transcript:

1 Federal Aviation Administration Data Communications Implementation Team (DCIT) Data Communications Implementation Team (DCIT) DCIT #32 PLENARY DCL Trials Update 4/16/2014 Matt Maki DCL Trials Lead

2 Federal Aviation Administration DTAP Build 7.1 Schedule Update Build 7.1 Limited Climb Via SID Compliance: -Interim Build with KEWR focus -UM169 CVS UL when MAINT ALT Set to NONE -AJV-8 ATP issued KMEM/KEWR 7110.113 CVS DTAP Trials waivers (April 2, 2014) -Fixes PTR 179 (Revised Dispatch Message EXPALT Header/Data) and PTR 180 (Dual Index Rollover Crash/DTAP Restarts) Build 7.1 Estimated Schedule: April 14-15:FAT at Thales April 16:Install/SAT at FAATC -April 16-25:Testing at FAATC -April 28 - May1:Install and SAT at MEM and EWR (Parallel installs)

3 Federal Aviation Administration B7.1 Climb Via Sid – CAF, Dispatch Message

4 Federal Aviation Administration B7.1 Climb Via Sid – Revised ALT (NONE), Dispatch Message Note: Revised DP listed in DM header due to B7.1 configuration to utilize CLIMBOUT field. B7.2 corrects this and just Revised ALT will be listed in the header

5 Federal Aviation Administration DTAP Build 7.2 Schedule Update Build 7.2 Full Climb Via SID Compliance: -Compliance with full 7110.113 CVS Changes -CVS, CVS Except Maintain, Maintain ALT Selections -Arrival/Departure Loadability, FD DL Response to AOC -Longer WJHTC lab testing period granted Build 7.2 Estimated Schedule: -June 11-12:B7.2 FAT at Thales -June 13:Install/SAT at FAATC -June 16 - July 3:Testing at FAATC -July 7-10:Install and SAT at MEM and EWR (Parallel installs)

6 Federal Aviation Administration KEWR DCL Trials Status Update UAL, FDX, UPS Daily Ops Ongoing: -UPS MD11/B767 daily operations commenced March 15 -Open OPR reports continue to be stable/diminish -Working with UAL to schedule remaining 9 B767 Fleet qualifying operations (May dates under consideration) -Legacy COA B757/B767 fleet Sabre/FANS upgrades start this summer – expanded KEWR participation expected International Participation Update: -BAW UK CAA approval letter received by FAA -DLH, SAS CAA approval letters pending -AFS-50 scheduling final approval briefing meeting with NY International POI reps to cover BAW, SAS, DLH ops -Airline AOCs standing by to resume DCL ops

7 Federal Aviation Administration KEWR DCL Trials Status Update March 26 EJA Global 5000 CPDCL Testing Complete: -Rockwell Collins Pro Line Integrated Avionics -CAF, Initial/Revised UM80 successful UL/loads -Initial/Revised UM79 not loadable – Rockwell reseaching KEWR HADDS, FDIO Test NCP Extensions Approved: -Via the 4/16 NAS CCB -Space NCP Extension not required until equipment removal April 7 Briefing with ZNY Automation, TMU: -Seeking ATOP DB ingest into DTAP for expanded SWAP Route processing -TMU briefed on Field 6A ‘EWR’ vs ‘KEWR’ DTAP processing effects

8 Federal Aviation Administration KMEM DCL Trials Update DCL Operations Running Well -DTAP Processing 20-40 FDX DCL ops per push -Route Revisions remain minimal/none in #s -Server 1, 2 Re-starts On-going (Tues/Fri) until B7.1 installed on April 28 Boeing DCL KMEM/KEWR Stats Reporting

9 Federal Aviation Administration Questions ? KUSA