Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT25 Update To:DCIT25 Plenary From: Matt Maki Date: 07.18.2013.

Similar presentations


Presentation on theme: "Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT25 Update To:DCIT25 Plenary From: Matt Maki Date: 07.18.2013."— Presentation transcript:

1 Federal Aviation Administration Data Communications Program MEM/EWR ATCT DCL Trials DCIT25 Update To:DCIT25 Plenary From: Matt Maki Date: 07.18.2013

2 Federal Aviation Administration Agenda MEM / EWR Operational Trials Status MEM / EWR Trials Results Patch 5 / Build 7 Status MEM FDIO Test NCP Extension Status 2

3 Federal Aviation Administration MEM Trials Status Update Full 24x7 Operations proposed for August 13 start: -B777 full functionality -MD11 only CAF until DTAP modification in place (send double TO points on UM79) -All MD11 flights affected – Domestic and International -MEM ATC will process only MD11 CAF UL -Non Route Revision UL to MD11 will be sent (DEP FREQ, EDCT, Etc.) -Pending final approvals/procedure training (CMO, MEM ATC, FDX) -EWR UPS AND FDX MD11 DCL OPS STILL FULL FUNCTIONALITY (Limited Trials Mode) 3

4 Federal Aviation Administration EWR Trials Status Update Airbus researching FMS issue affecting current SAS A333 operations: -UL/DL latency issues with older FMS configurations -SAS currently standing down until analysis complete Active participants utilizing the service: -UPS (MD11) -BAW (B777) -DLH (A343, A346) -SAS (A333) -FDX (MD11, B777) – Starting July 20 -UAL (B767) – Starting July 21 Draft MOUs sent to BAW, SAS, DLH: -Execution planned by end of SWAP season (Fall) 4

5 Federal Aviation Administration MEM DCL Ops Since 4/17/13 - Start of Limited Ops Trials AircraftAirline Total DCL Flights CAF Initial UM79 Initial UM80 UM79 Rev UM80 Rev Total UM WILCO MD11FDX3029015439 B777FDX109014014 5 Current Up Thru 7/17/13

6 Federal Aviation Administration MEM DCL Ops Since 4/17/13 - Lessons Learned 6 Current Up Thru 7/17/13 Unplanned Voice Clearance/ PDC Issued FRC DCL Filing Issues (Not Filed or Within First 22 Characters) and/or Crew Status (Not DCL Approved) DTAP Automation – FANS Avionics Issues/Testing HADDS/ CSP/ Network Issues ATC/FD Coordination AC Mechanical/ Diversions 20123221

7 Federal Aviation Administration EWR DCL Ops Since 5/16/13 - Start of Limited Ops Trials AircraftAirline Total DCL Flights CAF Initial UM79 Initial UM80 UM79 Rev UM80 Rev Total UM WILCO MD11 UPS44004210 FDX3210003 B777BAW7700007 A333SAS2110002 A343/6DLH2200002 7 Current Up Thru 7/17/13

8 Federal Aviation Administration EWR DCL Ops Since 5/16/13 - Lessons Learned Unplanned Voice Clearance/ PDC Issued FRC DCL Filing Issues (Not Filed or Within First 22 Characters) and/or Crew Status (Not DCL Approved) DTAP Automation – FANS Avionics Issues/Testing HADDS/ CSP/ Network Issues ATC/FD Coordination AC Mechanical/ Diversions 1765312 8 Current Up Thru 7/17/13

9 Federal Aviation Administration DTAP Patch 5 and Build 7 Status DTAP Patch 5 Requirements Updated: -Addition of requirement to send double TO point in UM79 uplinks (MD11 issue) -EWR ATC Requirements (Dual Contact / Drop Down Remarks, NONE ALT and SID) -Subject to SE2020 approval -Estimated Fall delivery Build 7 Scope, Schedule Cost Proposal from Harris by 7/25: -FAA options to select specific functionality based on schedule/cost consideration -Build Contract Acceptance and Delivery to FAA currently TBD 9

10 Federal Aviation Administration MEM FDIO Test NCP Extension Approved to NAS CCB NCP number assignment Notification at 07/16/2013 09:14 AM CDT ID: Case File JW925-FDIO-1003 NCP/CCD: P34982 Title: MEM ATCT Data Communications Trials Automation Platform (DTAP) Connection to a FDIO/PCRCU Echo Port (Extension of JW925-FDIO-1001/T34501) Message: NCP number: 34982 has been assigned to Case File: JW925-FDIO-1003 and submitted to NAS CCB for processing. 10

11 Federal Aviation Administration Questions ? KUSA