1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
CMPB Alain Blondel 14 April STATUS OF MICE.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Schedule and Milestones Colin Whyte STFC RAL Resource Loaded Schedule Review 5 th April 2016.
Muon Ionisation Cooling Experiment Overview
MICE CM28 Engineering Session Summary (On behalf of Wing)
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008

2 Contents: Achievements since CM20 Target & upstream beamline Muon beamline Cooling channel elements Infrastructure Preparations for Phase Two Project Organisation Open issues and concerns

3 Achievements since CM20 Briefly: –Reliable running of existing target in ISIS during machine physics shifts –Decay solenoid has demonstrated LHe capability with no obvious heat leaks –MICE now has ownership of the Linde plant and controls –The conventional magnet project is completed – string test successful –Physical start made on the magnetic shield walls –Contract for two AFC modules has been authorised with Tesla and contract has been faxed to them –Confirmation that UK funding for Phase Two will happen –PPS hardware installation largely complete –Control room operational

4 Target & Upstream Beamline Target: –More detail later, but: –Shorts found in actuator coils of both on & offline targets that were scheduled for installation earlier this year –New target assemblies underway by Sheffield Group with better understanding and QA of actuator coils –Insulation tested to 3KV at DL –ISIS encouraged us not to hurry to meet the May shutdown, but to do enough testing and confidence-building Installation of both in August 4 th -28 th shutdown –But installed target has been reliable. No evidence of coil problems, agreement to continue running –Dip depth has been increased 5-8mm with simple mechanical adjustment –New chiller and pipework to reduce cooling water inlet temp Also installed during August shutdown –Currently aiming for parasitic running in ISIS –Two shifts negotiated, 1 st & 2 nd June, possibility of 3 rd June also

5 Target & Upstream Beamline Other than target work in August and final placement of BPM, this area is ready for use Q1,2,3, D1 and all vacuum chamber installations are complete and aligned, magnets successfully tested

6 Muon Beamline Decay Solenoid –Problems with contamination in turbines and heat-leaks in cold box now fixed –But compressor performance not up to standard –It was good enough for a cold test though: LHe demonstrated in solenoid during April –Linde are currently uprating the plant; it returns end May, aim to be fully re-commissioned with solenoid by mid-June –The MICE project now owns the Linde plant – important as we can now do things on our own Q4,5,6 –Installation and testing is complete. Cooling water now run at approx 60% of original flow rate – less strain on pipework

7 Muon Beamline cKOV & TOF0 –cKOV A & B are installed and have been tested –TOF0 has missed the May shutdown, due to uncertainties with PM tubes – more detail from Maurizio –Current plan is we get TOF0 in late June –Then install it outside DSA behind Q7 on temporary frame –Then we fit it inside DSA at correct place in August 4 th - 28 th –Plan to collect KL, trolley, TOF & KL cables June 3-6 th –In time for installation start of Step One 9 th June

8 Cooling Channel Elements Spectrometer solenoid –Magnet no 1 at RAL end late August –Magnet no 2 at RAL late October –Cryostat & Tracker readout system shipped 2 nd June AFC Modules –Two modules are authorised, but some delay at RAL getting contract actually placed –More details from Tom & Wing RF Cavities –Design review this week LH2 Plant –Prototype system installed in September ‘08

9 Infrastructure Magnetic shield walls –Installation of South support structure is 75% complete, delayed by compressor removal –First 35 tonne batch of plates has arrived, some plates are fitted – relatively trouble-free so far!

10 Infrastructure North Wall: –Design complete, order about to be placed, but local admin problem at RAL Concrete ramp removal: –Completed in April, structural defect discovered, but signed off as OK DSA roof, walkway and roof –Design complete, but shortened May shutdown meant we could not start – will be OK for August shutdown LH2 vents and mound excavation –Difficult to make progress! Latest plan is for pre- fabricated ducts that we install and partly backfill – minimal excavation. Real difficulty is lack of design time/staff so we can work in parallel Electrical Infrastructure: –Now responsibility of Steve Griffiths at DL – tasks are all broken down and understood. Are being tracked by the weekly MICO meeting Tim Hayler will give general Infrastructure update to TB this week

11 Infrastructure False Floor –Design is essentially complete, but verification of forces on magnetic parts by magnetic modelling is more complex than first thought, but is converging –We believe that we have a design that is sufficiently flexible to allow the RF project to fit with the floor as it evolves Rolling platforms –There are seven platforms in total. We have ordered 1 and 7, due to be delivered end June. Platforms 2-5 are designed, but we decided not to make them due to cost - will need some cheaper solution

12 Steps Towards Phase Two Step One Construction Sliding beamstop, install August Q7,8,9 Operational now Fixed beamstop, parts here, but not assembled yet KL, KL & TOF cables arrive RAL 8 th June TOF 0 will go here end June – in DSA August TOF1 arrives end June

13 Steps Towards Phase Two Bottom-up estimate for UK phase two, with all forseen engineering detail has been completed –But unsurprisingly it exceeds guideline by a large margin We are now working on three versions: –(i) the above ‘ideal’ –(ii) one that fits the guideline (this allows for the two AFCs and virtually nothing else, ie we don’t have a project) –(iii) a compromise between the above two This is in progress, some version of version three almost certain – but cuts, de-scope or re-schedule very likely

14 Project Organisation Richard Apsimon (PM) and Paul Flower (Hall Foreman) both took early retirement in March –Too early to tell real effect on the project, but it’s clear that it’s left a hole, especially in the vital Safety/admin role Recruitment exercise for PM at RAL/DL has failed to find suitable candidate –Possibility of a suitable person from IC though –But in any case, two FTEs for the PM/TC post is probably unaffordable for the likely UK Phase Two funding profile So it might be a problem! Good news is that the Hall working team under Willie Spensley is highly motivated and capable – essential that we keep it together, or at least the core for Phase Two

15 Open Issues and Concerns –Delivery of false floor – it has to be installed by September to allow steps 2 &3 –Overloading due to Richard’s and Paul’s departure –The UK Phase Two funding – our aspirations might not match the money available – uncomfortable. –Retention of existing design and technical staff (pressure from other projects)