1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.

Slides:



Advertisements
Similar presentations
PROJECT RISK MANAGEMENT
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Chapter 14 Schedule Risk Management Dr. Ayham Jaaron Second Semester 2010/2011.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Procurement Methodology David Dale NLSL II Procurement Manager.
1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction Engineer Convention Facilities Advisory Committee Review.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Capabilities Presentation Please select the button above that best describes your interest to learn more about how Formare Technica, Ltd. can help you.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science OECM Limited-External Independent.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
Systems Engineering Management
Development plan and quality plan for your Project
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Readiness Stephen Sawch, Assistant Director for Construction Management Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
Project X RD&D Plan Conventional Facilities (Civil Construction) Russ Alber AAC Meeting February 3, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities NSLS-II PAC Review.
Project Risk Management. The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding.
Project Risk and Cost Management. IS the future certain? The future is uncertain, but it is certain that there are two questions will be asked about our.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Update Marty Fallier Director for Conventional Facilities NSLS-II PAC Meeting May 24, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Authorization Basis Plan Steven Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting December 10 – 11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
BSBPMG503A Manage Project Time Manage Project Time Unit Guide Diploma of Project Management Qualification Code BSB51507 Unit Code BSBPMG503A.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Plans for LOBs and Site Master Plan Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES CF Role in NSLS-II Operations Marty Fallier Conventional Facilities Advisory Committee Review October 5-6, 2009.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Status Update Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities CFAC Cost Review May 9, 2007.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
LCFOA Meeting at SLAC Linear Collider Forum of the Americas 1 LINEAR COLLIDER FORUM OF THE AMERICAS CONVENTIONAL FACILITIES OVERVIEW Victor R. Kuchler.
BSBPMG402A Apply Time Management Techniques Apply Time Management Techniques Unit Guide C ertificate IV in Project Management Qualification Code.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II Project Advisory Committee Meeting December.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities NSLS-II Conventional Facilities Update May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Steve Dierker Director, NSLS-II Conventional Facilities Division NSLS-II User Workshop July 17,
1 BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II CD-1 Cost Estimate Development Diane Hatton Associate Director for Administration.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
Project Risk Management Planning Stage
1 BROOKHAVEN SCIENCE ASSOCIATES CF FY09 Work Plan & Schedule Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review Conventional Facilities Update Marty Fallier Director for Conventional Facilities May 10, 2007.
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Overview Scope & Schedule Marty Fallier Director for Conventional Facilities.
GAO’s Cost and Schedule Assessment Guides U.S. Government Accountability Office Applied Research and Methods Cost Engineering Sciences Jason T Lee, Assistant.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Director’s Progress Review Closeout Meeting
Camera PDR/CD1 Planning 19 September 2008
Management Breakout: MREFC Budget Summary Victor L
Director’s Progress Review Closeout Meeting
Risk Management Process (Revised)
CONVENTIONAL FACILITIES LCLS Office Space Procurement
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008

2 BROOKHAVEN SCIENCE ASSOCIATES Outline CF Value Management –VE to date –Plans for T-II VE –Recommended Approach CF Risk Management –Risk Registry for CD-2 –Comments from CD-2 –Revised Risk Registry –Risk Assessment

3 BROOKHAVEN SCIENCE ASSOCIATES Value Engineering Extensive VE performed during Preliminary Design Identified and implemented 13 items prior to formal VE review Resulted in cost reduction of $ 9.0 M Performed formal VE review facilitated by VE expert Identified 48 possible items for consideration Evaluated 22 items worthy of further study Incorporated 9 items in current baseline worth $ 11.4M Identified 13 items worth up to $ 19.5 M for additional study and possible future implementation Additional formal VE review planned during detailed design

4 BROOKHAVEN SCIENCE ASSOCIATES Output From Formal VE Process

5 BROOKHAVEN SCIENCE ASSOCIATES Plans for T-II Formal VE Review VE study led by certified VE Expert provided by Design Phase CM to produce VE report based on 60% T-II design Review team will consist of: –NSLS II CF staff and interface managers for ASD & XFD –Design A/E architects and engineers –DOE observers –CM estimators, construction experts –PE engineers Will produce brainstorm list of VE opportunities Evaluate selected opportunities, provide data & recommendations NSLS II review and selection of recommended opportunities

6 BROOKHAVEN SCIENCE ASSOCIATES Issues with T-II Formal VE Review Next submittal is now 50% package instead of 60% Since design time is limited, focus of VE needs to be on specs, material and equipment selection rather than major building or system changes that could delay design Propose to use similar VE approach as before Does committee have any experience or recommendations on what works best in this situation? Should we wait to 80% for formal VE?

7 BROOKHAVEN SCIENCE ASSOCIATES Risk Management During T-I developed detailed risk registry for CF –See Handout CF Risks reviewed at CD-2 was found credible however EIR had issues with elements of overall Risk Mgt program –Risk model basis for allocating risk not substantiated –Method of application of Monte Carlo Analysis not optimal –Number and level of detail of risks too large to be effectively managed Risk Management Program being implemented –Assessment by consultant underway for continuing improvement –Goal is to have more streamlined usable system in place to effectively assess, update and present risk status, and manage risk

8 BROOKHAVEN SCIENCE ASSOCIATES Risk Assessment System Risk assessment is built into the cost estimating process Cost Estimate Database contains fields for inputting risk assessment for each WBS activity Assessment includes and considers: Risk types - Technical, Cost or Schedule, unknown unknowns, management adjustment Likelihood of occurrence – unlikely, likely, very likely Likely causes and expected consequence – marginal, significant, critical Mitigating actions that can/should be taken Whether activity in question is critical path or not The technical and estimate basis level of confidence

9 BROOKHAVEN SCIENCE ASSOCIATES Risk Assessment System Output Output is calculated by the model based on the previous factors Contingency value % and $ Risk categorization based on RMP criteria – Hi, Med, Low Mitigation plan where applicable Risk registry indicates all system input and output Available on web and as a handout Following tables summarize results

10 BROOKHAVEN SCIENCE ASSOCIATES WBS Dictionary: All phases of design, construction, and commissioning of the conventional facilities including the buildings, sitework, building services and utilities required to support installation and operation of the accelerator and experimental facilities. Conventional Facilities Total Estimated Cost ($ x 1000) WBS Description Direct $ Total Burdened & Escalated Bottoms up Contingency Total with Contingency FTEsLabor Non-Labor (Mtrl, Trvl, Act) %$ Value 1.05 Conventional Facilities 47.54,763197,952240, ,260309, Conventional Facilities Management40.3 3, , , Conventional Facilities Engineering and Design7.19 1,183 16,325 19, ,34323, Conventional Facilities Construction , , ,069274, Integrated Controls & Communications Standard Equipment008221, , Conventional Facilities Commissioning009001, ,121

11 BROOKHAVEN SCIENCE ASSOCIATES WBS Dictionary: Execution of engineering and design of NSLS-II buildings, utilities, and improvements to land by developing design requirements, preparing design drawings and specifications for construction contracts, and providing engineering support during the construction phase, to assure proper execution of the design and complete as-built documentation. Conventional Facilities Engineering & Design Total Estimated Cost ($ x 1000) WBS Description Direct $ Total Burdened & Escalated Bottoms up Contingency Total with Contingency FTEsLabor Non-Labor (Mtrl, Trvl, Act) %$ Value Conventional Facilities Engineering & Design7.21,18416,32519, ,34423, CF Title I Design.25492,0752, , CF Title II Design ,13011,957303,60115, CF Construction Phase Engineering ,1204, ,508

12 BROOKHAVEN SCIENCE ASSOCIATES WBS Dictionary: Construction of all NSLS-II buildings, utilities, and improvements to land, performed by multiple contractors and managed with the assistance of a Construction Management firm. Conventional Facilities Construction Total Estimated Cost ($ x 1000) WBS Description Direct $ Total Burdened & Escalated Bottoms up Contingency Total with Contingency FTEsLabor Non-Labor (Mtrl, Trvl, Act) %$ Value Conventional Facilities Construction00179,140211, ,069274, CF Construction Management005,6746,641281,8598, Improvements to Land007,9009,243312,86612, Operations Center005,3006,396251,5997, Injection Building007,5008,878272,39711, RF Building002,8003, , Ring Building0096,700114, ,344149, Lab – Office Modules0021,30025,984266,756 32, Mechanical Utilities009,20010,546272,84713, Electrical Utilities0013,60015,710304,71320, LN2 & GN2 Distribution System001,3661, , Chilled Water007,8009,135353,19712,332

13 BROOKHAVEN SCIENCE ASSOCIATES Risk Mitigation Plans Technical Risk Mitigation Plans Identified designated interface managers for CFD, ASD, XFD to assure technical integration of requirements between divisions Facility design includes flexible and adaptable approach that is tolerant of change where possible Design or construction of an item is deferred where possible to be tolerant of potential technical change –LOB interior design has flexible layout for labs and offices –LOB construction is deferred to start in FY12 when specific beamline User requirements are better understood

14 BROOKHAVEN SCIENCE ASSOCIATES Risk Mitigation Plans cont’d Cost Risk Mitigation Plans Perform active interface management with technical groups to reduce liklihood of changes –Interface managers assigned Seek independent estimate and market analysis for estimate confirmation and/or adjustment –CM Design Phase services in progress Use reasonable schedule duration for construction to reduce cost sensitivity of delays –CF schedule has substantial float even though it’s critical path Perform contractor outreach to encourage large pool of competitive contractors –In advanced procurement plan for FY08 Reduce exposure to differing conditions by thorough and early evaluation/confirmation of site conditions –Design process and Site Prep contract planned

15 BROOKHAVEN SCIENCE ASSOCIATES Risk Mitigation Plans cont’d Schedule Risk Mitigation Plans Use reasonable schedule durations to reduce cost sensitivity of delays in design, procurement, construction –CF schedule has substantial float even though it’s critical path Perform active interface management with technical groups to reduce liklihood of delays due to changes –Interface managers assigned Reduce delays due to differing conditions by thorough and early evaluation/confirmation of site and utility conditions –Design process and Site Prep contract planned Reduce potential delays due to safety incidents by implementing a “best in class” construction safety program –Construction safety plan in development Early procurement of critical items identified in schedule

16 BROOKHAVEN SCIENCE ASSOCIATES Current Risk Assessment – Title II CF Engineering & Design – Risks -Changes in requirements delay design and result in A/E change orders Allocation 20%, Current projected cost impact ~13% – CF Construction – overall allocation 30% Risks - Changes in design requirements affect cost –Allocation 8%, current cost impact ~ 5% Risks – Changes in material market availability/price –Allocation 4%, current cost impact ~4%

17 BROOKHAVEN SCIENCE ASSOCIATES Risk Management Summary Performed risk assessment for CD-2 Identified, planned and actively implementing risk mitigation strategies CF is active participant in risk management meetings Improved method of presenting, assessing and tracking risk status under development project-wide Design phase risks are tracking below predicted values Construction phase risks are tracking at or slightly below predicted values but higher than we’d like.