FAIR March 20, 2007 D. Krämer GSI/FAIR Division Technical Status: status of layout status of civil engineering items under current discussions status of.

Slides:



Advertisements
Similar presentations
FAIR Status Report Hans Ströher NuPECC-Meeting Cracow June 9, 2006.
Advertisements

JINRs PARTICIPATION IN SIS100 & SIS300 JINRs PARTICIPATION IN SIS100 & SIS300 5 th WORKSHOP on the SCIENTIFIC COOPERATION between GERMAN RESEARCH CENTERS.
FAIR Synchrotrons SIS100/300
A.KOVALENKO SUPERCONDUCTING MAGNETS for NICA BOOSTER & COLLIDER NICA ROUND TABLE DISCUSSION - 3 JINR, Dubna, November 05, 2008.
Peter Spiller, IHEP, Protvino GSI, Peter Spiller IHEP FAIR in kind Contributions.
PLANS JINR PARTICIPATION for JINR PARTICIPATION FAIR PROJECT: in the FAIR PROJECT: - ACCELERATOR TECHNOLOGY A.Kovalenko 103 session of the JINR Scientific.
UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Sergey Kozub Institute for High Energy Physics Protvino, Russia SIS300 meeting 19 March, 2009 Sergey.
Helmholtz International Center for Oliver Boine-Frankenheim GSI mbH and TU Darmstadt/TEMF FAIR accelerator theory (FAIR-AT) division Helmholtz International.
FAIR GmbH and FAIR Project History, Status and Outlook
Introduction 1 Proposal for the structure of FAIR GmbH construction phase 2 Relationship between FAIR GmbH and GSI mbH construction phase Contract Site.
Applied superconductivity group L. García-Tabarés, F. Toral, I. RodriguezCIEMAT, I/2008.
Helmholtz Centre for Ion Research D. Krämer, 2nd Lab Directors Meeting, Protvino, January 15-16, 2008 Design and Engineering Issues; Standardization and.
BINP for FAIR Yu.Shatunov Moscow May Research and Development Contract between GSI and BINP 1. Kickers for synchrotrons and storage rings.
Status of FAIR Yuri Zaitsev (ITEP) Physics of Compressed Baryonic Matter 1-st CBM-Russia-JINR Collaboration Matter May 19-22, 2009, Dubna, Russia.
Progress Report Günther RosnerNuPECC, Copenhagen, 15/6/121.
FAIR – Facility for Antiproton and Ion Research
FAIR – Status Report Walter F. Henning.
D. Krämer - Tech. Discussions GB, Oct. 11 th, 2006 Workpackages and In-Kind Contributions to FAIR The FAIR Project Preparatory Phase - R&D for FAIR Workpackages.
Proton Linac, Workshop, December 3 rd - 4 th, 2007 The FAIR Proton Linac Outline Requirements to Proton Linac Source, RFQ, DTL, RF Beam Dynamics.
The new FAIR accelerator complex at GSI: Project, Challenges, First steps Ralph C. Bär ICALEPCS, 16. October 2007.
Helmholtz Centre for Ion Research G. Moritz, Cryogenic Expert meeting, GSI, September 19/ (courtesy of D. Krämer for the FAIR Design Team) Current.
FAIR – Facility for Antiproton and Ion Research Austria China Finnland France Germany Greece India Italy Poland Slovenia Spain Sweden Romania Russia UK.
IHEP participation in SIS300 production UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Institute for High Energy Physics Protvino, Russia FAIR meeting.
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt Status of the FAIR project Visit in Wuhan,China November 23, 2006 J.
SIS 100 main magnets G. Moritz, GSI Darmstadt (for E. Fischer, MT-20 4V07)) Cryogenic Expert Meeting, GSI, September 19/
P. Spiller, SIS18upgrade, Peter Spiller GSI, Darmstadt Kick off Meeting - EU Construction DIRAC Phase SIS18 upgrade.
FAIR Facility for Antiproton and Ion Research Guenther RosnerNuPECC, Prague,
1 Status of EMMA Shinji Machida CCLRC/RAL/ASTeC 23 April, ffag/machida_ ppt & pdf.
1 Plans for JINR participation at FAIR JINR Contributions: ● Accelerator Complex ● Condensed Baryonic Matter ● Antiproton Physics ● Spin Physics Physics.
Peter Spiller, CBM collaboration meeting GSI-Darmstadt 11. February 2004 Status of the future accelerator project.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
The FAIR Project Walter F.J. Müller, GSI, Darmstadt CBM Technical Coordinator FAIR Joint Core Team 2 nd CBM India Meeting, VECC, Kolkata, July 2007.
Peter Spiller, DIRAC Kick-off meeting Peter Spiller Design Study Group DIRAC kick-off meeting SIS100.
Status of the FAIR pbar Source K. Knie May 3, 2011.
Welcome to FAIR RF Review for TAC Meeting in June 2007.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Status of GSI-FAIR Project magnets - open issues - G. Moritz GSI CARE HHH AMT November
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt Introduction and Status EU Design Study Kick-off meeting April 14-15,
GSI Helmholtzzentrum für Schwerionenforschung GmbH LINK EXISTING FACILITY I n order to prepare the existing GSI accelerator facility (mainly the SIS18)
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt Introduction and Status EU CNI contract Kick-off meeting, December 1-2,
International Accelerator Facility for Beams of Ions and Antiprotons at Darmstadt Construction of FAIR Phase-1 December 2005 J. Eschke, GSI Construction.
Design and construction of Nuclotron-based Ion Collider fAcility (NICA) and Mixed Phase Detector (MPD) Design and construction of Nuclotron-based Ion Collider.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
Oct. 16, 20081CBM Collaboration Meeting, Dubna, Zbigniew Majka FAIR project status  Establishment of the FAIR GmbH  Accelerator construction  Civil.
Introdcution to Workpackage/Activity Reflection D. Schulte.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
1 The next steps – focusing points Define the scope, strategy and cost of the project implementation. Main input: The evolution of the physics findings.
WP2: Beam dynamics and optics Workflow between Work Packages 1 O. Brüning – BE-ABP WP2 HL-LHC meeting 17. November 2011.
CR: status and activities at BINP I.Koop, BINP, Novosibirsk O.Dolinskyy, GSI,Darmstadt , MAC, GSI, Darmstadt.
Oleksiy Dolinskyy 23 rd October, FAIR layout of accelerators Collector Ring.
O. Kester, NuSTAR annual meeting, 27/02/2013
Contents: -GSI organization structures -Tasks of GSI (accelerator) -Status of evaluations / technical developments -Overview -Note : (only) accelerator.
GSI Helmholtzzentrum für Schwerionenforschung GmbH GSI visitation W. Barth W. Barth, WAO 2014, Mainz/Germany.
MAC meeting (12-13 January 2010) Machine Advisory Committee participants: B.Sharkov (ITEP/FAIR) P.Belochitskii (CERN) S.Ivanov (IHEP, Protvino) M.Steck.
Progress Report Günther RosnerNuSTAR Annual Meeting, Darmstadt, 29/2/121.
Peter Spiller, November 2012, Structure and Tasks of the Project Division Primary Beams Peter Spiller Machine Advisory Committee Meeting.
O. Kester, 6 th MAC meeting, Darmstadt, 10/10/2011 FAIR ACC planning and schedule O. Kester 6th FAIR - Machine Advisory Committee Meeting
Status of FAIR D. Krämer Dec. 1&2, 2010 – 4th MAC Meeting 1.
CBM Timeline Walter F.J. Müller, FAIR, Darmstadt
Preparation Phase of the FAIR Project
Status of the FAIR Project
High energy beam transport.
Oleksiy Dolinskyy December 1st, 2014
ICE SECTION The coolest place to be! Elias Métral
Status of HESR 18th March Gießen Dieter Prasuhn.
FAIR ACCELERATORS Peter Spiller EMMI workshop
CLIC damping rings working plan towards the CDR
HESR for SPARC 25th November FAIR MAC Dieter Prasuhn.
ThomX – Commissioning Meeting – 25/01/2018
Presentation transcript:

FAIR March 20, 2007 D. Krämer GSI/FAIR Division Technical Status: status of layout status of civil engineering items under current discussions status of specs parameter list status of workpackages

Reference: FAIR Baseline Technical Report Approved by ISC in May

Project Costs Accelerator investment costs 533 M€ Civil construction costs 289 M€ Baseline experimental facilities ( incl Super-FRS) 180 M€ Investment budget 1002 M€ Manpower (2400 person-years) 185 M€ Total Construction Costs 1187 M€ Costs evaluated by CORE-A/E, TAC, STI and 7 mini-TACs, documented in Costbook Commissioning Costs 26 M€ Annual operation cost 118 M€/y ISC took note of costs 25% of cost to be funded by international partners - on-going negotiations by funding agencies

Time Schedule First experiments scheduled for beginning of 2012 (Super-FRS) – Phase I End of project scheduled for beginning of 2015 Schedule determined by civil construction progress (start of CC early 2007)

Technical Realization of FAIR 100 m UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Existing facility: provides ion-beam source and injector for FAIR Existing facility: provides ion-beam source and injector for FAIR New future facility: provides ion and anti-matter beams of highest intensity and up to high energies New future facility: provides ion and anti-matter beams of highest intensity and up to high energies FLAIR Accelerator Components & Key Characteristics Ring/Device Beam Energy Intensity SIS100 (100Tm) protons 30 GeV 4x U 1 GeV/u <10 12 (intensity factor 100 over present) SIS300 (300Tm) 40 Ar 45 GeV/u 2x U 34 GeV/u 2x10 9 CR/RESR/NESR ion and antiproton storage and experiment rings HESR antiprotons 14 GeV ~10 11 SuperFRS rare-isotope beams 1 GeV/u <10 9 Radioactive Ion Production Target Anti-Proton Production Target

Since FBTR: Deeper Planning of the FAIR-Layout (FAIR SR, FAIR SY Group) ∙Machine lattices have been re-optimized and are fixed now ∙HEBTs have been re-calculated ∙Optics was discussed and checked with external experts ∙TAC will review lattice and transfer line optics in June 2007 for final approval

Actual Activities: Synchrotron Items ∙HEBT p-bar separator – CR minimize losses due to chromatic aberration ∙ Synchrotron SIS 100 Performance limitations of NUCLOTRON magnets at 4 T/s ∙ Synchrotron SIS 300 Detailing of (2) straight sections for transfer SIS100 – 300 (injection) and extraction Corrector system

Actual Activities cont’d Storage Ring Items ∙RESR focusing structure - Simplify lattice for optimized stochastic cooling at fixed geometry ∙ Stochastic Cooling - Hardware procurement for test-stand ∙ Machine Experiments at ESR - Tests of beam accumulation schemes

FAIR-Topology Optimized and checked optics - 3D - all junctions matched - latest Super FRS layout - latest HESR layout - option for HESR upgrade - p-transfer line to NESR - option for p-bar transfer line to ER

Actual Activities cont’d R&D Items (FAIR MT Group) ∙SIS100 prototypes Curved full scale MARK I dipole magnet under fabrication at BINP (coil subcontracted to Dubna company) Straight full scale magnet under fabrication at BNG PDR with BNG and BINP – FDR scheduled for May 2007 Delivery scheduled for late this year followed by intense qualifications JINP working on MARK I quadrupole ∙ SIS300 dipole prototypes ∙IHEP Protvino: tooling ready, coil-end design ready, tests at CERN ∙INFN: PDR very promising, safe 1K margin and good field tolerances at 4.5 T ∙ CR/Super FRS superferric dipole FAIR China Group: die available, laminations punched, model coil under fabrication, cryostat design under preparation

Actual Activities cont’d Magnet R&D Items ∙Super FRS Large aperture quad prototype ready for contracting (Toshiba) ∙NESR/RESR magnets ELYT study in favor of nc solution (as proposed in FBTR)  TAC ∙18 Tm/100 Tm nc HEBT magnets Parameters fixed, design starts now ∙Test GSI GSI001 cooled down, magnetic measurements performed, AC losses determined; check of measurement equipment Aim: install and test SIS100 1 m model dipole in June ‘07 ∙ Cryostat design Magnet cryostats and cold-warm intersections under design at GSI

Actual Activities cont’d Theoretical items (FAIR AT Group) ∙SIS dynamical tracking simulations with field errors ∙Impedance (resistive wall effect due to thin vacuum chambers) ∙Landau damping by octupoles – alternative to active FBs ∙Beam stability / beam losses - at given intensities, working point - non-linear effects - stability of ultra cold beams - … Other items (GSI Beschleuniger Gruppe) RF prototype cavity Diagnostics ….

FAIR-Buildings – General Procedure ∙BMBF, BMVBS & BMF: decision to follow RZBau procedure §44 BHO/LHO, i.e. ZBau procedure as is applied for public buildings in Germany. ∙This means: ∙Consultation by civil construction administration, i.e. OFD and hbm ∙Consultation in preparation of contract awarding ∙Preparation of application for building permit ∙Consultation of application and documentation ∙Determination of extent of documentation ∙Verification of scope of task ∙Review of execution of construction work ∙ Report on expenditure of funds Step 0: Proposal to BMBF to start the process Step 1: Room program (scope of the work) has to be approved by OFD Step 1a: Contracts to PS and PP companies together with hbm Ultimate definition of what to realize Step 2: Complete pre-planning approved by OFD Step 3: Start construction work and detailed implementation planning RZBau = Richtlinien für die Durchführung von Zuwendungsbaumaßnahmen (BMVBS) ZBau = Baufachliche Ergänzungsbestimmungen zu den Allgemeinen VV zu § 44 BHO BHO/LHO = Bundeshaushaltsordnung/Landeshaushaltsordnung

Detailing FAIR-Buildings (FAIR CC Group) ∙Details of optics layout require adaptation of buildings ∙HESR moved to the South by 30 m ∙Optimization of p-bar – CR transfer line ∙Re-confirmation of building requirements in progress ∙i.e. space, media, transportation …  “room-” and “load list” ∙FAIR CC is collecting data ∙Discussions with all “building owners” on costs savings ∙EU wide tender on project steering (PS) in Dec expect contract until May 2007 ∙EU wide tender on project planning (PP) (on halt) ∙Draft proposal to start ZBau procedure in Jan. 30, 2007 Preparation of planning possible within FAIR preparatory phase Formal start of ZBau procedure only with approved funding

FAIR-Topology Building location according to optical layout - Buildings under revision - Prepare input for formal building procedures Step 1.. n

Workpackages ∙94 WPs defined according to WBS, FBTR and Cost Book schematics 13 subprojects 15 technical systems No decision up to now – awaiting expressions of interest Finally contracts between partner and FAIR GmbH interest to take WP indicated

Specification of Workpackages ∙All 94 WPs need to be specified - to allow FAIR partners proper realization of the contribution, e.g. a magnet - basis: scope of work is FBTR and approved optimizations - technical detailing of specs under way, according to R&D results, simulations and progress in enlarged planning depth ∙Aiming for functional specs and/or full technical specs of components available late 2007 – process in on-going. ∙Presently: CERN EDMS has been implemented also to spread specifications, follow-up and document evolution to final design, production of components and life-cycle management of components.

Parameterlist An updated version of the Oct Parameterlist is at print (request by TAC) (FAIR beam parameter committee) System co-ordinators (FSR: M.Steck, FSY: P. Spiller) are preparing machine specific detailed parameter lists as part ofthe specifications Detailed TDRs planned in future

Thank you