1 Progress Report Günther RosnerNuPECC, Copenhagen, 15/6/121

2 FAIR @ Darmstadt Günther RosnerNuPECC, Copenhagen, 15/6/122

3 Facility for Antiproton & Ion Research Günther RosnerNuPECC, Copenhagen, 15/6/123 Dense Bulk Plasmas (Ion-beam bunch compression & petawatt-laser) Dense Bulk Plasmas (Ion-beam bunch compression & petawatt-laser) Materials Science & Radiation Biology (Ion & antiproton beams) Materials Science & Radiation Biology (Ion & antiproton beams) Accelerator Physics UNILAC SIS18 SIS100/300p-Linac HESR CR & RESR NESR Cryring Rare-Isotope Production Target Anti-Proton Production Target 100 m QCD-Phase Diagram (HI beams 2 to 45 GeV/u) QCD-Phase Diagram (HI beams 2 to 45 GeV/u) Hadron Physics (Stored and cooled 14 GeV/c anti-protons) Hadron Physics (Stored and cooled 14 GeV/c anti-protons) Nuclear Structure & Astrophysics (Rare-isotope beams) Nuclear Structure & Astrophysics (Rare-isotope beams) Fundamental Symmetries & Ultra-High EM Fields (Antiprotons & highly stripped ions) Fundamental Symmetries & Ultra-High EM Fields (Antiprotons & highly stripped ions)

4 Civil Construction Günther RosnerNuPECC, Copenhagen, 15/6/124

5 CC Planning Activities 02 / 1203 / 1204 / 1205 / 12 Checking/Approval of CC Phase 3 & Cost Calculations Inclusion of requirements of fire department /building inspection Statics / Layout Drawings (CC Phase 5) Technical Execution Planning (CC Phase 5) Announcement Logistics Günther RosnerNuPECC, Copenhagen, 15/6/125

6 Licensing III /11IV /11I /12II / 12III /12 Building Application Afforestation Appl. Water rights Appl. Environmental Compatibilty Water Rights Appl. (ground water management) 31.08.11 19.01.12 21./23.11 12.02.12 07.03.12 02.02.12 Günther RosnerNuPECC, Copenhagen, 15/6/126

7 Preparatory Work 02 /1203 /1204 /1205 /12 Stripping of Topsoil (area tree felling) Site Roads (Messeler Parkstr.) Site Roads (southern traffic link) Site Roads (northern traffic link) Alternative routing pedestrian Günther RosnerNuPECC, Copenhagen, 15/6/127

8 Aerial View Günther RosnerNuPECC, Copenhagen, 15/6/128

9 Fast acceleration High gradient, variable frequency Ferrite & MA loaded cavities Compact & cost effective accelerators Fast cycling superconducting magnets dB/dt ~ 4T/s Precision beams Electron & stochastic cooling XHV @ high beam intensities Extremely high vacuum ~10 -13 mbar Accelerator Challenges Günther RosnerNuPECC, Copenhagen, 15/6/129

10 Compact & cost effective Fast cycling superconducting magnets dB/dt ~ 4T/s Accelerators 113 SIS100 dipoles ordered from Babcock Noell in Jan. 2012 (German in-kind contribution) Many other parts of SIS100 and CR in preparation. HESR ready to be submitted for tender. IKRB meeting at FAIR on 28/3/12 MAC meeting at FZ Jülich on 2/4/12 Günther RosnerNuPECC, Copenhagen, 15/6/1210

11 FAIR Experiments Günther RosnerNuPECC, Copenhagen, 15/6/1211 CBM PANDA NuSTAR Super- FRS APPA

12 Experiments Collaborations finish R&D phase Collaborations submit complete sets of TDRs to FAIR FAIR establishes Expert Committee Experiments, ECE – TDR Review Panels: ECE members (+ external experts) FAIR organises/monitors the co-ordination of experiments with – Civil construction & setup of accelerators/storage rings Collaborations identify critical pathways regarding – Timelines, milestones & deliverables Collaborations submit risk management plans – To be assessed by FAIR & integrated into Risk Reports to AFC and Council Funding Issues – FAIR establishes Resources Review Boards for each Collaboration consisting of all Research Councils participating in the experiment(s) Funding Agencies, Collaborations and FAIR negotiate Construction MoUs Günther RosnerNuPECC, Copenhagen, 15/6/1212

13 OrgChart Günther RosnerNuPECC, Copenhagen, 15/6/1213

14 Timeline Günther RosnerNuPECC, Copenhagen, 15/6/1214 201220112013 201620152014 6 Building permits Site preparation Civil construction contracts Building of accelerator & detector components Completion of civil construction work Installation & commissioning of accelerators and detectors Start Data taking 7 10 8 2017 20182019 12 6 7 8 9 11 12 10 11 9

15 Thank you very much Günther RosnerNuPECC, Copenhagen, 15/6/1215