Springbrook Estates Sewer Improvement Area Informational Meeting

Slides:



Advertisements
Similar presentations
1. I. Review Objective of Tonight’s Meeting. II. Review History of Project. III. Review Proposed Wastewater Treatment Plant & Sewer System Layout. IV.
Advertisements

Floyd County Board of Commissioners Special Town Hall Meeting Topic: Update on status of Georgetown WWTP.
2009 Wyoming Street and Utility Improvements Neighborhood Informational Meeting December 18, :00 P.M. – 8:00 P.M. 6:00 P.M. – 8:00 P.M. Mark A. Erichson,
1 Informational Meeting March 5, 2003 Perry Township Administration Building Delmar Addition/Glenn Avenue Sewer Improvement Area.
Timeline of Key Milestones and Dates DateKey Milestone February 2007Washtenaw County Drain Commissioner’s Office authorizes a project to identify opportunities.
Vance County Water District Overview and Update Jordan McMillen Director Vance County Planning and Development Department 156 Church St. Suite 3 Henderson,
December 4, 2014 Macon, Georgia Georgia Mountains Regional Commission.
RETROFIT POLICY FOR GRANT FUNDED PROJECTS Utilities Department Orange County Board of County Commissioners September 23, 2014.
Holden Heights Community Improvement Project Update Orange County Board of County Commissioners December 17, 2013.
Board of County Commissioners Allen County, Ohio Tuesday, May 1 st, 2001 Presented By: Stephen M. Kayatin, Sanitary Engineer Ryan Rase, Business Manager.
Hide-A-Way Lake, Inc. Low Pressure Sewer System Prepared by Dungan Engineering, P.A.
Utility Extension Project
BITHLO COMMUNITY WATER Utilities Department Orange County Board of County Commissioners December 18, 2012.
Board of County Commissioners Allen County, Ohio Detailed Planning Assessment Hearing Wednesday, May 30 th, 2001 Presented By: Stephen M. Kayatin, Sanitary.
Broadview Second Access. Parlette Annexation What has changed? Parlette has asked for reconsideration –Recitals in agreement are not operative provisions.
MORRIS MILL PROPOSED URBAN SERVICES DISTRICT Presentation to County Council September 17, 2013.
1 Construction Assessment Hearing October 3, 2002 Shawnee Middle School Cafeteria.
Board of County Commissioners Allen County, Ohio Pre-Construction Public Informational Meeting April 27, 2005.
5/29/021 Informational Meeting May 29, 2002 Perry Township Administration Building Fourth Street/Bowman Road Sewer Improvement Area.
1 Construction Assessment Hearing May 23, 2001 Shawnee Middle School Cafeteria.
Southwood Waterline Project Shawnee Twp. House 7:30 PM November 29 th 2000.
Potential Sources of Financial Assistance to Connect to the New Sewer PRESENTED BY SHERYL FLORES AND ALMA AGUILAR 11/5/2015.
Proposed FY 2016 Budget Town of Lisbon Presentation to Board of Selectmen October 7, 2015.
Ordinance Amending Chapter 37 Orange County Code Utilities Department October 21,
Heritage Park Area Mandatory Connection Final Information Meeting March 14, 2016.
Mandatory Connection 1 st Information Meeting. Review project Explain mandatory connection process via Frequently Asked Questions Answer questions Supply.
City of Franklin Department of Building and Neighborhood Services Transitioning from Private Sewage Disposal to Public Sanitary Sewer September 30, 2010.
Alpine County Government Center Board of Supervisors Presentation October 2, 2012.
Finance Department Environmental Services City of Superior Superior Water Light & Power Wastewater Billing.
Mandatory Connection 2 nd Information Meeting November 17, 2015.
Ordinance Amending Chapter 37 of the Orange County Code Orange County Board of County Commissioners Public Hearing April 3, 2012.
Duquesne University’s Payroll Transition: Salary Entitlement to Payment in Arrears.
PARK STREET/CAMPANELLI PARK SEWER EXPANSION PROJECT Public Meeting Wednesday, June 22, 2016.
Public Information Meeting St. George Road - Oak Hill Road Intersection Reconstruction Project.
PROPOSED CITY OF STOCKTON WATERFORD ESTATES EAST PHASE II ASSESSMENT DISTRICT PUBLIC HEARING Stockton City Council January 6, 2004.
Finance Department Environmental Services
Marquis Hills Area Information Meeting December 7, 2016
Quail Valley Subarea 9, Phase 1 Sewer Award of Construction Contracts
Marquis Hills Area Information Meeting December 7, 2016
Tax Budget – Putting the puzzle pieces together
Audie Murphy Road Sewage Lift Station Award of Construction Contracts
Christopher M. Quinn, MACC, CPA, CFE, CGFO, CGMA
FY Proposed Budget and Rates
FY 2018 Budget Review Process and Schedule
PROPOSED MARCH LANE / HOLMAN ASSESSMENT DISTRICT
Because, My Belief Determines my Destination
Valley & Third Streets Redevelopment
GOMER SEWER IMPROVEMENT AREA
Amelia County FY19 Budget Draft
Joshua Basin Water District Revised Rate Recommendations
FY19/FY20 Detroit Collective Impact Funding
BUSINESS OWNER MEETING
WASHINGTON COMMUNITY HIGH SCHOOL BUDGET PRESENTATION
Iowa College Aid Processing System (ICAPS)
Due Dates subject to change. Watch for dashboard updates.
FY 2019 Close Schedule Bi-Weekly Payroll governs close schedule
San Luis Obispo County Integrated Regional Water Management (IRWM) Region Regional Water Management Group (RWMG) Meeting SLO City/County Library Community.
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Octorara Area School District
Delta Water Supply Project
Octorara Area School District
Octorara Area School District
PLANNING LOOKING AHEAD…. Long Term Goals (Assigned to…)
Biltmore C Proposed Water & Sewer Improvement Project
Village of Naples New Sanitary Sewer System Final System Layout
PLAYMATES LEARNING CENTER CALENDAR
Town of Bergen Water District (WIBA No
Budget Planning Calendar
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Ward Park Restroom Timeline
Presentation transcript:

Springbrook Estates Sewer Improvement Area Informational Meeting ___________________ Springbrook Estates Sewer Improvement Area Informational Meeting December 20, 2017 Presented By: Allen County Sanitary Engineering Department

Overview Of Tonight’s Meeting Project Introduction Meeting Objective Project History Proposed Sanitary Sewer Layout Procedure for Completion of Project Estimated Cost to Property Owners Easement Acquisition Tentative Project Schedule Questions

1. Project Introduction A public sanitary sewer project is proposed for the Springbrook Estates Sewer Improvement Area. The project is being initiated due to the following: 1) There is an existing health concern and water pollution hazard as documented by our department and the Allen County Health Department. Resident complaints. Failing on-lot systems. Since the meeting held August 28, 2013 the department has been researching financial assistance opportunities, completing detailed plans and specifications for the project.

2. Meeting Objective This meeting will provide information for completion of a sanitary sewer project serving approximately 84 property owners located within Springbrook Estates, Northwest Street, SR 65 and SR 115 areas. The meeting will also allow for a question and answer period following the presentation.

3. Project History October 6, 2011 Sampling and testing of ditches and catch basins were completed by the Allen County Health Department and Allen County Sanitary Engineering Department. May 15, 2012 Sampling and testing of ditches and catch basins were completed by the Allen County Health Department and Allen County Sanitary Engineering Department. July 13, 2012 The Allen County Board of Health made recommendation to the Board of County Commissioners to pursue the installation of public sanitary sewer to eliminate the existing public health issues and water quality violations. August 28, 2013 Conduct public Informational Meeting. August 28, 2013 to Complete detailed plans, specifications, complete Tonight income surveys and research financial assistance options. December 20, 2017 Conduct 2nd Informational Meeting

3. Project History – Sampling Locations

3. Project History – Sampling Test Results

4. Proposed Sanitary Sewer Layout

5. Procedure for Completion of Project Conduct 1st Informational Meeting on August 23, 2013. ORC 6117.06(A) - Commissioners adopted Resolution 523-13 on August 28, 2013 approving General Plan and Declaring Necessity of project. Research and make funding assistance applications. Conduct 2nd Informational Meeting on December 20, 2017. Proceed to the construction of the project once County has received Closing Instructions from USDA. Complete construction of the project. Finalize cost of project, mail billings with notice of Project Wrap-up Meeting to property owners. Conduct Project Wrap-up Meeting addressing property owner concerns, final billing and connection process. Notify property owners for connection to the project. Health Department will require in-house plumbing inspection before connection.

6. Estimated Cost to Property Owners Cost to property owners can be broken down as follows: Cost for design and construction of sanitary sewer mainline paid back as a monthly debt service to be added onto the sewer bills. Miscellaneous out-of-pocket cost: Abandonment of septic and connection to sanitary sewer. County sewer bill with debt service charge. County Health Board permit and potential modifications to plumbing.

6. Estimated Cost to Property Owners (cont.) Funding Assistance Sources:

6. Estimated Cost to Property Owners (cont.) Estimated Principal Debt Service Estimated Total Project Cost Breakdown: Construction (9,581 lf of sewer) $1,239,746 Design 167,400 Easement acquisition 20,000 Administrative 44,000 Miscellaneous 43,000 Contingency (10% Construction Cost) 123,976 Total $1,638,122 Estimated Principal Debt Service (PDS) per User Equivalency (UE): PDS per UE = (PDS – USDA Grant – County Participation) ÷ 84 UE =($1,638,122 - $400,000 - $405,800) ÷ 84 UE =$832,322 ÷ 84 = $9,909 per UE Note: The $9,909 principal debt service may be paid in cash within 30-days of billing.

Principal Debt Service = $9,909, Interest Rate = 2.75% 6. Estimated Cost to Property Owners (cont.) Estimated Principal Debt Service Summary of Principal Debt Service Broken-down into a Monthly Charge: Principal Debt Service = $9,909, Interest Rate = 2.75% 20-year repayment 30-year repayment 40-year repayment Monthly Debt Service $53.95 $40.60 $34.17 Payback $12,948 $14,616 $16,402 Additional Financing Cost Over 20-year Plan - $1,668 $3,454

6. Estimated Cost to Property Owners (cont.) Estimated Out-of-Pocket Cost to Property Owners Abandonment of existing private sewage system/tanks and installation of a sanitary sewer lateral to the project. Approximate Cost - $1,500 to $2,000. Once a property owner has connected to the sewer line he or she will receive a quarterly sewer bill which may be billed monthly EFT. Month’s Billed Billing Date Due Date Cost Jan-Feb-Mar May June $148.50 Apr-May-June Aug Sept July-Aug-Sept Nov Dec Oct-Nov-Dec Feb March Allen County Board of Health Permit ($100 to be covered in project cost), and any plumbing modifications

SUMMARY OF ESTIMATED COST 6. Estimated Cost to Property Owners (cont.) SUMMARY OF ESTIMATED COST Principal DS Monthly DS Charge to be billed with sewer bill (40 yr-20yr) On-Lot out-of-pocket Quarterly Sewer Bill (monthly) $9,909 $34.17-$53.95 $1,500-$2,000 $148.50 ($49.50) The total monthly sewer bill is estimated to be between $83.67 (40-year) to $103.45 (20-year).

7. Easement Acquisition USDA will not allow the County to proceed with bidding the sewer improvement until all easements have been secured. The climate for receiving the best bid pricing is now. Therefore, in an effort to obtain the best possible pricing for construction the County needs to wrap-up the easement acquisition process. Your cooperation working with our representatives is greatly appreciated. All property owners will benefit from a lower final project cost. All savings will be passed along to the property owners. There are a few easements that have not been secured from property owners. However, checks are being created for all property owners that have signed easements. Checks and copies of recorded easements shall be mailed to all property owners.

8. Tentative Project Schedule 1st Informational Meeting August 28, 2013 Income Surveys Sent Out January 24, 2014 2nd Informational Meeting December 20, 2017 Begin Construction February-March 2018 Complete Construction December 2018 Project Wrap-up Meeting January 2019 Initial Principal DS Billing February 2019 First DS Billing on Sewer Bill April 2019

Questions