LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Accelerator Schedules LHC and LHC Injectors Schedules MSWG meeting 16 January 2015 SPSC - 13 January 2015 Rende Steerenberg, BE/OP2 Rende Steerenberg,
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
Access zones and Training Steve Hutchins BE-ASR IEFC workshop 7/3/2012.
Major power converter issues for the restart of PS & SPS machines and their experimental areas in 2006 Jean-Paul BURNET for AB/PO PS&SPS days January.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
K.Hanke – PS/SPS Days – 19/01/06 K.Hanke - PS/SPS Days 19/01/06 Recommissioning Linac2/PSB/ISOLDE from CCC  remote operation from CCC  upgrades & changes.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.
SPS YETS 2015/2016 Planning meeting for BE-BI 09/12/15 David Mcfarlane EN-MEF D.Mcfarlane1.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Decommissioning of CTF3 Nothing has been studied on the cost, manpower needed, environmental impact (RP) etc. This is just to raise some points that may.
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
Status of the machines over X-mas standby period, services required and plans for rapid start-up OP Group Meeting KH.
Warm Magnets - LS1 Feedback J. Bauche, on behalf of the TE-MSC-MNC Team.
PS - SPS Day 18-Jan-2006 PS Ring by Ray Brown.. 2.
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
SPS start up 2014 SPS OP. SPS changes during LS1 New transformers and 18kV cables for MPS. New function generators (FGC’s) with lots of new and different.
Magnet activities in SPS during EYETS
LIU and TE/VSC activities Status September 2016 LIU-SPS aC coating & flange impedance reduction Paul Cruikshank on behalf of TE-VSC LIU & TE-VSC, 19/9/2016.
YETS & LS2 Works EN-EL / Power distribution
Linac4-PSB 160 MeV connection readiness review
Framework Schedule from EYETS 2016 to LS2
SPS LS1 Planning meeting (N019) 04/09/13
Update on the Critical Path of the PS Booster Schedule for the EYETS
SPS Winter stop Planning meeting (N06) 05/01/2011
NA61 news and plans (May 2013-October 2013) Publications:
TE-MSC activities in SPS during LS2
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
Injector De-cabling Project
Evolution and future of the Access safety and control systems
AD consolidation activities in LS2
TE-ABT Activities for LS2
Installations, modifications, consolidation in 2005:
PS Booster Hardware Tests & Cold Check-out planning 16th of March 2017
TE/EPC activities for LINAC 2, PSB, PS & TT2 during EYETS
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
High Radiation to Materials 16th Project Team Meeting – May 20, 2010
SPS Planning for the EYETS Meeting 8 (07/12/2016)
Renovation of the 45-year old PS magnets
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
SPS activities during LS2 TE-EPC (Power Converter Group)
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
EN-CV interventions during EYETS for PS and PSB
YETS & LS2 Works EN-EL / Power distribution
James Ridewood BE-OP-SPS
TE-MSC activities in SPS during YETS
East Hall under construction
YETS Dec 2017 – March 2018 LS Experiments requirements / Services (un)availability F.Butin / EN-EA EACM meetings outcome, thanks to all participants.
Alexander Herlert, CERN (PH-SME-IS)
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
ABP/RTL Main RTL Activities for 2007/8:-
SPS Planning meeting for LS2 #26 Vacuum sectors status
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1

LS1 Days: The Injectors Key Dates What will run in 2013? Reminder: What will not be done What will (should?) be done How are we organised? A few more outstanding questions AD, EAST Area & NORTH Area Conclusions LS1 Day: The Injectors2

Key dates at the start of LS1 PSB 3LS1 Day: The Injectors DescriptionDate Beam stop (end of Isolde Physics run)3 rd December 2012 PSB radiation cool-down period4 th to 14 th December 2012 PSB magnet HV tests12 th to 20 th December 2012 PSB ready for general access21 st December 2012

Key dates at the start of LS1 PS 4LS1 Day: The Injectors DescriptionDate Beam stop (end of FT Physics run)26 th November 2012 PS radiation cool-down period27 th November to 9 th December 2012 POPS & MPS tests27 th November to 12 th December PS Magnet tests10 th December to 20 th December PS ready for general access21 st December 2012

Key dates at the start of LS1 SPS 5LS1 Day: The Injectors DescriptionDate End of FT Physics26 th November 2012 SPS radiation cool-down period26 th November to 9 th December 2012 RP survey and patrol5 th December to 7 th December 2012 Magnets tests and inspections.10 th December 2012 to 18 th January 2013* General access21 st January 2013* All services must remain on until the 18 th January 2013! (ATLAS water?) Only works that do not require access and do not affect the operational mode of the SPS will be scheduled before the 21 st January 2013!

Key dates at the end of LS1 PS & PSB 6LS1 Day: The Injectors DescriptionDate End of shutdown work19 th February 2014 Commissioning new access system6 th January 2014 to 19 th February 2014 Hardware test period20 th February to 14 th March 2014 Patrols with new access system15 th March to 19 th March 2014 Beam to PSB20 th March 2014 Beam to PS10 th April 2014 Beam to SPS1 st May 2014

Key dates at the end of LS1 SPS DescriptionDate All Water circuits back online and in service31 st January 2014 SPS Ring Patrol3 rd to 5 th February 2014 HV magnet test6 th February Hardware test period7 th February to 17 th April DSO tests22 nd to 24 th April 2014 Start-up of the SPS25 th April 2014 Beam available from the PS1 st May 2014 SPS/TI2/TI8 Operational9 th June LS1 Day: The Injectors

Note for the end of 2014 LHC will restart with beam in autumn 2014 It is not planned to have a stop of LHC beam operation at Christmas 2014 – 1 week of standby for LHC & Injectors – Consequences for maintenance activities??? – FT programs will have a normal stop from December 2014 to April LS1 Day: The Injectors8

9 What will run in 2013? EN/MEF Coordination teams

What will run in 2013? Main constraint is CV maintenance – PS Complex water off in May, June & July LINAC3 – Test with new ions for NA operation – Mid-January for 13 weeks (Argon) – Early August for 13 weeks (Xenon) CTF3 – March to November – Stop 3 months in summer ISOLDE – REX-IBIS 3MeV test stand – February to April – August to December with a new source LS1 Day: The Injectors10

Reminder: What will not be done… LS1 Day: The Injectors11

Reminder: What will not be done… SPS Cable clean up around BA5 Replacement of irradiated cables BA1 Replacement of all irradiated cables TCC2 & TDC2 – Look at replacing a limited number of cables to avoid duplication of work and reduce overall dose? All preparations for the connection of Linac4 to the PSB before LS2 PSB cable clean-up (requested but never formally agreed) – Some preparatory work to at least identify cables? EAST Area cabling NA62 ventilation in NORTH Area – Must be done in the 2014/15 NORTH Area stop LS1 Day: The Injectors12

What will be done Consolidation and maintenance work – all groups Replacement of PS Complex access system – 28 access points, 100 doors – Both systems to run in parallel during 2014… – The time critical activity New PSB Interlock system Replacement of the PS tunnel ventilation system – Requires sealing of PS tunnel & TT2 (not a trivial exercise!) New PS beam imminent warning system (BIW) Addition of shielding over the Route Goward at the PS – Major Civil engineering project which will complicated access to the PS area. Removal of 4 PS main magnets TT2 magnet renovation LS1 Day: The Injectors13

Vertical re-alignment of SPS between 5 & 6 – Needs displacement of the support jacks Full re-alignment of all machines Replacement of the SPS main power supply transformers Replacement of approximately 15 SPS main magnets Change of 12 additional SPS main magnets for e-cloud vacuum chamber coating LS1 Day: The Injectors14 What will be done

How are we organised Now we have the list of things to do – Aim to produce a first resource loaded realistic schedules for Injectors – Planning and Coordination meetings – Detailed discussions with Groups (dedicated contact people) Machine Coordinators = the Usual suspects – AD & PSB: Nicolas Gilbert – (PSB: D Hay handover date to be defined) – PS: Ray Brown – SPS: David McFarlane – Other problems concerns: Vinod Chohan or Simon Baird LS1 Day: The Injectors15

How are we organised? We will start from the information already collected and all the approved activities entered into the PLAN database Please inform us about new activities Major new activities must also be entered in PLAN – Management approval IMPACT tool will be used as part of the planning once we have the baseline schedule – Access Control – Activity completion – Documentation control ECR’s etc LS1 Day: The Injectors16

How are we organised? LS1 Day: The Injectors17 A situation to avoid….

A few outstanding questions to be addressed No cable clean-up in BA5 – Is there an issue for cabling for new installations around BA5 (SPS) – BI requests…. No cable clean-up in PSB – Again is there an issue for cabling for new installations – BI equipment – EPC new power converters – Interlock systems – New ABT equipment… Renovation of TT2 magnets – Can we really remove renovate and re-install up to 39 magnets?? – Can we do this work in situ? LS1 Day: The Injectors18

AD (on top of “standard” activities) RF and Stochastic cooling consolidation Removal of a main dipole – Preparation of a magnet consolidation program for AD Removal of unused transfer lines (7000, 8000, ATP) and general clean up to prepare for ELENA A delay of AD shutdown 2014/15 is under discussion to allow for a delay of… – Additional works for ELENA & Gbar installation – New building (kickers storage etc…) LS1 Day: The Injectors19

NORTH Area NA62 ventilation separation is delayed until 2014/15 North area shutdown – 2014 run for NA62 will need RP mitigation measures – Reduced beam intensity – Long flushing periods before access to experimental cavern GIF++ installation in H4 NORTH Area long-term consolidation – Prioritized plan starts in 2013 and continues … – In 2013 TCC2 & TDC2 works (with a limited replacement of irradiated cables t.b.c…) LS1 Day: The Injectors20

EAST Area DIRAC will be removed to make way for a new irradiation facility This is the first step in the EAST Area renovation as presented at the EAST Area Day LS1 Day: The Injectors21

Conclusions Now we can get started – Business as usual = Coordination meetings… – PS Complex access system is the time critical item – SPS: Two major activities have been removed – Please inform us of changes to your needs (MEF Coordinators and PLAN) Some questions – BA5 and PSB: Will we install equipment without new cables? – TDC2/TCC2 Can we make a limited cable replacement campaign? – TT2 magnet renovation? – Is non-stop operation from early 2014 to the end of 2015 a concern? – ….. LS1 Day: The Injectors22

LS1 Day: The Injectors23 Conclusions