Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.

Similar presentations


Presentation on theme: "Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013."— Presentation transcript:

1

2 Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013

3  Status of EPC equipment & control  Present consolidation plan (Simon’s file)  Update of the consolidation plan with present MPP  Remaining issues & proposals 3 ACC consolidation day, 12/09/2013

4 Status of EPC equipment TE-EPC is managing all the power converters for magnets and some for RF systems. 40% of the equipment are less than 10 years old 50% of the equipment are more than 30 years old Older ones are close to 50. EPC has already 43MCHF in the Simon’s file (until 2020) which represents 50% of the EPC project budget. The EPC consolidation items are only for replacement of old equipment. No item can be considered as maintenance (recurrent process) or infrastructure upgrade or tools. 4 ACC consolidation day, 12/09/2013

5 Why is it so difficult to consolidate ? the 5300 power converters in operation are from 460 different types ! LHC is done with 10 types, so the difficulty is in the injector and experimental areas. All power converters are custom equipment designed mainly by CERN. No industrial product in our domain. 5 ACC consolidation day, 12/09/2013

6 After more than 40 years there is a zoo of 8 different types of controls electronics in use with power converters: 1. CAMAC 2. MIL1553/G64 3. PLC 4. RS422 5. Junction Crate 6. MUGEF 7. FGC2 8. FGC3 An important goal for the future is to the reduce the number of different types of controls to make support easier. Huge effort to maintain all these obsolete hardware and Software, costly in manpower! 6 ACC consolidation day, 12/09/2013 Status of EPC control

7 PSB main power converter will be replaced in the framework of LIU. New SVC is needed with the new sub-station ME59, requested for LS2. PS main power converter was replaced by POPS. SPS main power converters are fully consolidated during LS1. Spare SVC (new BEQ1) is requested for LS2. 7 ACC consolidation day, 12/09/2013 Status of big power system

8 Present consolidation plan Up to 2013, only injector chain equipment were considered for consolidation. Only most critical equipment were upgraded or replaced (example, POPS). No full consolidation were done per machine. For experimental areas, nothing was done. First proposal for the North area consolidation dates from 2001! New facilities (HIE-ISOLDE, ELENA,…) get the priority which always postpones the experimental area consolidation. A status board of the consolidation need per machine is shown afterward with its evolution over the years. 8 ACC consolidation day, 12/09/2013

9 9 EPC Consolidation status board after LS1 ACC consolidation day, 12/09/2013 LHC program

10 Update of the consolidation plan In the present plan, the north area should have start in 2015, but with the present MPP, it will not be possible for EPC. Idem for EAST Withdraw of 23 MCHF over the 43! Here are the main objectives for EPC with our present MPP for the coming years including all projects : 10 ACC consolidation day, 12/09/2013

11 EPC main objectives before LS2 MachineEnd of Projecttotal costStatus LINAC4201410MCHFCommissioning LT-LTB-BI2017ACC800kCHFNew request RD1 replacement (LHC)2016ACC1MCHFApproved SM16-26, PS-RF, QKECT (PS)2016ACC2.4 MCHFApproved CANADA (PSB)2017ACC1.2MCHFApproved SPS extraction2016ACC1MCHFNew proposal HIE-ISOLDE20152.2MCHFApproved TSR (ISOLDE)2018?3.5MCHFNot approved ELENA2016890kCHFApproved AD consolidation2019ACC3MCHFNot approved AWAKE2018240kCHFApproved SESAME20161MCHFApproved S-FRS2016800kCHFApproved 11 ACC consolidation day, 12/09/2013 LHC program

12 EPC main objectives for LS2 MachineEnd of Projecttotal costStatus LIU PSBLS221MCHFApproved LIU PSLS22.6MCHFApproved TT2 consolidationLS2ACC3.8MCHFApproved SVC SPS (new BEQ1)LS2ACC10MCHFApproved SVC Meyrin ME59LS2ACC7MCHFNew request LHCCONS (R2E)LS2ACC20MCHFApproved LHC 11T (Nb3Sn)LS2?Approved? 12 ACC consolidation day, 12/09/2013 All LHC program

13 13 EPC Consolidation status board after LS2 ACC consolidation day, 12/09/2013

14 EPC main objectives for LS3 MachineEnd of Projecttotal costStatus New Inner-tripletLS310MCHF?Approved SPS aux & CODLS3ACC6MCHFEPC tentative EAST LS3ACC5MCHFEPC tentative TT20LS3 or LS4ACC3MCHFEPC tentative NORTHLS3 or LS4ACC30MCHFEPC tentative The consolidation of the experimental areas is postponed to LS3 but depending of new approved projects, it could be postponed to LSXX !!! 14 ACC consolidation day, 12/09/2013 LHC program

15 15 EPC Consolidation status board after LS3 ACC consolidation day, 12/09/2013 Best case, East – North done in LS3 Most likely situation with present MTP. For EPC, the NORTH consolidation is a 5 year project before installation. For LS3, EPC has to start working on it from 2017 ! Seems very difficult with LIU workload for LS2.

16 Coordinate the consolidation of the experimental areas For Experimental Areas, the powering of these facilities should be reviewed to reduce energy consumption. For EAST, reduction of 95%, saving 500kCHF/year, 30 magnets to be replaced. For NORTH, reduction of 30%, saving 800kCHF/year, 120 magnets to be replaced. This requires :  to have laminated magnets  to operate the magnets in pulse mode The consequences are:  Replace of solid yoke of magnets  Change of power converter types and ratings  Change of the electrical distribution (less transformers, different sockets)  Reduce water cooling needs The consolidation shall be planned for the same LS for all groups (EL, CV, MSC, MPE, EPC). 16 ACC consolidation day, 12/09/2013

17 Remaining control issue Even with this plan, the control issue will not be solved. Here you can see the evolution of the converter controls: After LS1 After LS2 After LS3 Still 1000 MIL1553 devices after LS3 ! Still 300 MUGEF devices after LS3 ! FGC based control systems will be in all machines but mixed with older control system 17 ACC consolidation day, 12/09/2013

18 Solving control issue To solve the control issue, a plan could be added with 2 milestones:  LS2: migrate all converter control to FGC from LINAC4 to PS  LS3: migrate all converter control to FGC for SPS and all experimental areas This could be possible with additional resource as requested in our MPP and a dedicated ACC budget for the upgrade of the converter control. Expected situation after LS3 FGC based control systems + Industrial controls 18 ACC consolidation day, 12/09/2013

19 Additional objective for LS2 With the present plan, we replace equipment for LIU and we consolidate critical equipment with the ACC. The result will be a mix of new and old equipment with different control system. EPC would recommend to upgrade all equipment to get an unified machine. from LN4 to PS. Estimation to be done. 19 ACC consolidation day, 12/09/2013

20 20 Summary EPC has many equipment to consolidate With the present MPP, the experimental areas can’t be consolidated before many years An increase of 10% of EPC manpower is needed to launch consolidation of the experimental areas The consolidation of experimental areas has to be coordinated between all the groups and plan for a same LS Availability of NORTH, EAST, AD will decrease up to …? The zoo of converter controls should be addressed, risk analysis is not enough The EPC item on the Simon’s file has to be updated with new objectives defined after this review ACC consolidation day, 12/09/2013