1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beneficial Occupancy Readiness Evaluation Plan Update Brian Heneveld, P.E., CIH NSLS-II BORE Coordinator Conventional.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Electrical Utility Service Dennis Danseglio, P.E. Project Engineer.
1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction Engineer Convention Facilities Advisory Committee Review.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Authorization Basis Steve Hoey, NSLS-II ESH Manager Project Advisory Committee February 8-9, 2011.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Time Management Ahmed Awad, Ph.D., PMP. Time Management It includes the processes required to ensure timely completion of the project. b Activity Definition.
1 BROOKHAVEN SCIENCE ASSOCIATES Nick Simos NSLS2 Ground Motion and Vibration Studies.
1 ®  Overview Benefits of a Good Construction Schedule Baseline Schedule Development Schedule Updating and Maintenance Managing Project Changes USACE.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Accelerator Installation Plan Gregory Fries Project Engineer, Accelerator Systems Division CFAC Review of NSLS-II.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Thomas C. Nehring, P.E. Lead Electrical Engineer CFAC Review November 9-10, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Readiness Stephen Sawch, Assistant Director for Construction Management Conventional Facilities.
CFS near term & Required ADI input CFS near term & Required ADI input 6-12 month activities, required ADI information 10. AUG 2014CFS-ADI Joint Meeting1.
1 BROOKHAVEN SCIENCE ASSOCIATES Nick Simos NSLS2 Ground Motion and Vibration Studies.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities LEED-ESH-Facility Utilization May 8, 2007.
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
1 BROOKHAVEN SCIENCE ASSOCIATES As-Built Drawings and Commissioning Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities NSLS-II PAC Review.
Amin Salari, CCM, PMP, LEED AP – Lundgren Management
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Update Marty Fallier Director for Conventional Facilities NSLS-II PAC Meeting May 24, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Update Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director Experimental.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II EFAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities & Beam Stability Marty Fallier Director for Conventional Facilities NSLS-II Beam Stability Workshop.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Plans for LOBs and Site Master Plan Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES CF Role in NSLS-II Operations Marty Fallier Conventional Facilities Advisory Committee Review October 5-6, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting February 8-9, 2011.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II ASAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Status Update Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11,
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities CFAC Cost Review May 9, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Support Update Diane Hatton, Project Support Division Director NSLS-II Project Advisory Committee Meeting May 24-25,
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
1 BROOKHAVEN SCIENCE ASSOCIATES CHILLED WATER & COMPR. AIR PIPING Thomas F. Joos, P.E. Lead Civil/Structural Engineer CFAC Review November 9-10, 2009.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities NSLS-II Conventional Facilities Update May 8, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES CCW Plant Expansion & CCW Piping Thomas F. Joos, PE Lead Civil/Structural Engineer CFAC Review March 10-11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Presentation to PAC R. Casey NSLS-II ESH Program Status May 25, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Overview Marty Fallier, Conventional Facilities Director ASAC Meeting July 18, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Steve Dierker Director, NSLS-II Conventional Facilities Division NSLS-II User Workshop July 17,
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Procurement David Dale Procurement Manager NSLS-II Project Project Advisory Committee November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Steve Sawch Asst. Director, Construction Management NSLS-II CF Construction Preparations May 8, 2008.
1 BROOKHAVEN SCIENCE ASSOCIATES CF FY09 Work Plan & Schedule Martin Fallier, Conventional Facilities Division Director CFAC Review March 10-11, 2009.
1 BROOKHAVEN SCIENCE ASSOCIATES EFAC Review Conventional Facilities Update Marty Fallier Director for Conventional Facilities May 10, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Procurements Thomas C. Nehring, PE Lead Electrical Engineer Conventional Facilities Advisory Committee - Review.
Project Scoping. Project Scoping – learning objective Who should complete the Project Initiation Package (PIP)? How is PDP Path used in scoping? Task.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting March 29-30, 2012.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Status Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Accelerator.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Overview Scope & Schedule Marty Fallier Director for Conventional Facilities.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Management Breakout: MREFC Budget Summary Victor L
Details supporting the increase
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Presentation transcript:

1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the NSLS-II Project May 8, 2008

2 BROOKHAVEN SCIENCE ASSOCIATES CF Schedule Outline Schedule Parameters Schedule Risk Reduction Summary Schedule Schedule Durations Intermediate Milestone Challenge Verification with Independent CPM Schedule Schedule Analysis WBS Update Schedule Summary

3 BROOKHAVEN SCIENCE ASSOCIATES Schedule Parameters Schedule for conventional facilities developed at detailed level Needed to meet critical milestones Needed to meet project funding Needed to develop confidence in schedule phasing and sequencing Needed to identify key interface points with accelerator & beamline installation Needed to develop baseline schedule Prepared based on input and discussions with: LIRO/Gilbane CM scheduling group Large local contractors Consensus that logic, sequencing, phasing and durations are reasonable

4 BROOKHAVEN SCIENCE ASSOCIATES Schedule Risk Reduction Early procurement Site-prep reduces schedule and cost risk and overall duration Takes risky earthwork (unforeseen existing conditions) off the critical path Delays due to “ getting out of the ground ” are frequent source of claims Perform environmental testing and remediation (if required) Decommission/relocate existing utilities Early procurement of chilled water equipment Chillers Cooling Towers Early procurement of electrical equipment Main substation Switchgear

5 BROOKHAVEN SCIENCE ASSOCIATES Summary Schedule

6 BROOKHAVEN SCIENCE ASSOCIATES Schedule - Durations Construction Activities Site preparation contract duration – 4 months Main bldg contract bid & award – 5 months Ring bldg contract duration – 36 months (excluding LOBs) Entire bldg contract duration - 48 months Chilled Water Plant Expansion – 28 months Electrical Utilities – 18 months Mechanical Utilities – 22 months LN2 system – 9 months

7 BROOKHAVEN SCIENCE ASSOCIATES Critical Intermediate Milestones Key schedule objective – Enable start of accelerator installation March 2011 CF is on or near critical path until the main bldg spaces are turned over for accelerator installation Schedule was interfaced with Accelerator and EXP. Facilities groups to identify necessary and workable dependencies Key dependencies: 1 st pentant ready for accelerator installation BO of Ring Bldg for beamline installation

8 BROOKHAVEN SCIENCE ASSOCIATES Pentant 1 Detailed Schedule

9 BROOKHAVEN SCIENCE ASSOCIATES Verification with Independent Schedule BNL Schedule Duration Pentant 1 – 20 months Pentant 5 – 20 months Pentant 2 – 21 months Pentant 3 – 24 months Pentant 4 – 24 months Injection Bldg. – 26 months RF Bldg. – 21 months Overall – 48 months Liro/Gilbane Schedule Duration Pentant 1 – 21 months Pentant 5 – 21 months Pentant 2 – 20 months Pentant 3 – 20 months Pentant 4 – 19 months Injection Bldg. – 18 months RF Bldg. – 16 months Overall – 41 months

10 BROOKHAVEN SCIENCE ASSOCIATES Schedule Analysis Analysis At NSLS II site ~$180M in work over ~48 mos = $3.75M/mo At CFN $2.4M/mo but in 50ksf building footprint Footprint for NSLS II is ~400ksf – 8 times the space! As long as sequencing is correct, there is ample time to get this work done The space available and layout enables great flexibility in sequencing work so all trades are continuously productive APS Comparison (escalated to today's $) APS cost $275M over 63 mo = $4.4M/mo vs $3.75M/mo for NSLS II APS- 960ksf/63mo = 15ksf/mo vs 400ksf/48mo = 8.3ksf/mo NSLS II

11 BROOKHAVEN SCIENCE ASSOCIATES WBS Update Currently Updating WBS Construction Phase CM Deleted LOBs Design Deferred LOBs Separate Contract Chilled Water Plant and Piping Separate Contracts Simplify and Standardize Use CSI Codes – Divisions 1-16 – map to estimates GC to Develop Their Own Schedule Establish GC Interface Evaluate Performance- EVMS

12 BROOKHAVEN SCIENCE ASSOCIATES Schedule Summary Schedule provides confidence that scope can be done in scheduled time Critical path is identified Critical dependencies are identified Schedule risk areas identified and mitigation underway (early procurement) Path Forward – Additional schedule development underway: Ongoing Scheduling Updates Input from CM during Pre-Construction Contractor Outreach More detailed resource loading of activities in CSI format