Linford School Drainage Improvements 21 March 2016 City of Laramie.

Slides:



Advertisements
Similar presentations
Pedestrian Considerations in Work Zones… St. Peter Main Street Reconstruct.
Advertisements

Town of Mount Airy Main Street Construction Update Community Forum #5 and #6.
Highway 61/147th Street Intersection Business Meeting April 20, 2010.
Maryland Avenue and Arkwright Street Jerry Auge, PE Project Manager Ramsey County April 2, 2013.
Stormwater Illicit Discharge Inspector Training Workshop April 24, 2013 Tabletop Group Exercise.
Washington Avenue Reconstruction Project City of Chelsea Public Informational Meeting May 31, 2011.
Evaluation of Private Property I/I Sources for Sanitary Sewer Evaluation Study City of Grand Rapids – E. Leonard Heights Area Presenter: Jay Zawacki, CDM.
UPPER SLIDE RAVINE WORKSHOP City of Grass Valley September 29, 2009.
EA204 Environmental Technology Pavement Drainage Stormwater Sewer Design.
Welcome Learn more about upcoming construction activities on Cedarvale Avenue and Oak Park Avenue View display boards and speak one-on-one with staff Building.
2014 STREET & UTILITY IMPROVEMENT PROJECT CITY COUNCIL MEETING November 18, 2013.
Lander Streets and Utilities 2015 Public Meeting No. 2 McDougall & Cliff Project Area.
Arterial Street Rehabilitation for Riverside Drive 24 th Street to 35 th Street Public Informational Meeting July 22, 2014.
Dillon and Christina Project Area Lander Streets and Utilities 2015 Public Meeting No. 2.
6 th Street Water Main And Street Reconstruction 2013.
Potomac Ridge Stormwater Management Project
City of Bloomfield Hills 2015 Road Improvement Program.
Capilano Road Improvement Project WELCOME TO THE OPEN HOUSE.
Southern Corridor Study Recommendations March 16, 2011.
2014 Roadway Rehabilitation Project Neighborhood Pre-construction Meeting Monday, June 9, :00 p.m. Currell Boulevard Tamarack Road.
Volusia County Public Works
US Highway 17 (Center Street) Sidewalk Feasibility Study Town of Pierson, Florida.
Holden Heights Community Improvement Project Update Orange County Board of County Commissioners December 17, 2013.
MUNICIPAL STORMWATER PERMITS Water Quality Partnership May 19, 2005.
August 7, 2013 Luke Lortie, EIT Jerry Auge, PE
1 Urban Drainage and Intersection Design Image:
Montwood Street & Drainage Improvement Project Solicitation No November 26, 2012.
Engineering and Technical Plans Description, process and standards Dh 2005.
 Prepared for  City of Palm Coast, Florida  June 24, 2014 Drummond Property Acquisition in Connection With The Land Donation of 70 Laramie Drive From.
In this Presentation…. Project Overview Key Issues Elements of Design Funding and Schedule.
Adams-14 School District Facilities Master Plan Kearney Middle School Focused Site Evaluation SITE DRAINAGE OBSERVATIONS General – Site drainage was primarily.
Greenwood Transit and Sidewalk Project N 90th St to N 105th St Community Open House Sarah Butler, Project Manager September 14, 2015 Presentation begins.
Drainage Task Team Volusia County Public Works Judy Grim, P.E. Road and Bridge Director.
11 District of Columbia Water and Sewer Authority George S. Hawkins, General Manager September 16, 2013 Bloomingdale Civic Association Briefing for: Northeast.
38th ½ Street Improvements (between Grayson and Airport) Group 10: Jordan Alvarez Emily Tat Charles Yamashiro.
Quality Avenue “Safe Streets” Improvements City of Lakeland, Minnesota Paul Pinkston Hamline University August 18, 2015.
Term Project Presentation CE 394K.2 Hydrology Presented by Chelsea Cohen Thursday, April 24, 2008.
Presentation Outline  Recommendation  Project Background  Public Involvement  Proposed Design  Citizen Comments/Questions  Summary and Recommendation.
JULY 16, 2013 BCC APPEAL HEARING ON BZA SE , JUNE 06, 2013 APPLICANT: KEVIN DONAGHY AGENT FOR CHANTEL PRESTON.
City of Madison Engineering Division Joylynne Drive and Douglas Trail Assessment District-2010 Pflaum Road to Tompkins Drive Joylynne Drive to Herro Lane.
PUBLIC INPUT SESSION OCTOBER 27, 2015 City of Asbury Sun Valley Dr. and Sun Ridge Ct. Reconstruction Project.
Planning Commission Public Hearing: SUB Proposed 6-lot Subdivision at Bland Circle December 2, 2015.
PUBLIC INPUT SESSION NOVEMBER 10, 2015 City of Asbury Birchwood Drive Reconstruction Project.
RECONSTRUCTION OF MONTGOMERY STREET Capital Improvements Budget Committee March 24, 2015 Hilary Holmes, Planning & Economic Development (PED)
Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) Water Street Hydrologic and Hydraulic (H&H) Analysis (Drainage Study) City of Platteville.
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
4/26/061 presents Project Crimson April 26, 2006 Sarah Grace Cade Harrelson Cochrane Jamison Libby Probst Justin Williams.
City of Belmont Pavement Reconstruction Project October 15, 2014.
To The For The. CITY OF GLENDALE, CA Community Meeting, January 9, 2016 Ocean View Blvd. Looking South Intersection Verdugo Road and Ocean View Blvd.
Comprehensive Thinking and Planning
PRESENTED AND PREPARED BY CITY OF MISSOULA PUBLIC WORKS DEPARTMENT.
PUBLIC IMPROVEMENT HEARING 2015 Street, Utility and Retaining Wall Improvements - Grandview Boulevard November 12, 2014 (continued to December 9, 2014)
2nd Street Drainage and Paving Improvements
Village of east aurora sycamore street water improvements
Agenda Updates to Driveway and Sidewalk specifications and permits
Week 7, April 10, 2017.
June 5, 2017.
Manchester’s CSO Program: A Look Behind and a Look Ahead
Santa Cruz avenue sidewalks Project
DICKINSON AVENUE RECONSTRUCTION
IA 122 RECONSTRUCTION PRE-BID MEETING
PROJECT NO. T SE Adams Street - SE 29th Street to SE 33rd Terrace
SW Gage Blvd - Street Repair Project
Project Scope of Work Project Contacts
City of McDonough Annexation Proposal
Regulation Amendment AM April 3, 2018.
SE 12th Street Roadway Improvements February 8, 2005.
Galt Court Water Main Replacement
Meadow Lake Boulevard Street Extension Project
MS4 OVERVIEW 2015.
Presentation transcript:

Linford School Drainage Improvements 21 March 2016 City of Laramie

Introductions City of Laramie ► Eric Jaap, PE – City Engineer ► Tony Shifflett – City Inspector ► William Winkler - EIT Albany County School District ► Ed Goetz – Business Manager Amec Foster Wheeler ► Aaron Murray, PE – Design Engineer ► Ross Davenport, EIT – Civil Design 2

► Frequent drainage problems due to unpaved streets with little or no slope. 3 Project Background ► City of Laramie, working closely with the Albany County School District, initiated a project to study, design, and construct drainage improvements.

Stormwater Drainage ► Safely convey runoff from minor and major storm events to downstream storm sewers in Monroe Street ► Detention required to meet available downstream capacity 4 Project Goals Roadway ► Pave streets in project area to move water to low points where inlets can pick up flow ► Improve pedestrian, ADA access Water Lines ► While streets are opened up, upgrade existing waterlines (upsize, PVC)

5 Benefits to Linford School and Neighborhood ► Improved drainage – minimize or eliminate ponding ► Not passing the problem to adjacent blocks ► Upgraded water lines ► Replacing aging pipes to improve reliability ► Improve fire protection in the area – new hydrants ► Replacing service lines (to the property line) ► Paved roads ► sidewalks, curb and gutter ► ADA access ramps ► Paved driveway approaches or rollover curb

6 Project Improvements Map – Drainage and Water

7 North Side Improvements – Drainage and Water

8 South Side Improvements – Drainage and Water

9 Street Improvements

10 Street Construction – Cross Sections

11 Schedule Estimated Construction Start (Subject to Permit Approvals) ► May 2016 Sequence of Construction ► Likely start at Monroe & Johnson -- water & storm sewer installation ► work to the north ► Must install underground detention at Linford School parking lot between June 10, 2016 and July 8, 2016 ► Project substantially complete by October 1, 2016

Access to Residences/School ► Contractor to maintain access to driveways ► Contractor to keep at least one access to school parking lot open Temporary Water ► Contractor to provide and maintain temporary water service Work Hours ► 7 AM to 7 PM, Monday – Friday, Saturdays by City Approval only Garbage Collection 12 Resident Concerns

13 Questions?