1 SW Gage Blvd - Street Repair Project
SW 21st Street to SW 25th Street PROJECT CONTACT INFORMATION City of Topeka Engineering Robert Bidwell, PE 620 SE Madison Topeka, KS 66607 (785) PROJECT SCOPE: Edge mill, concrete patching, & asphalt overlay Limited curb & gutter replacement Limited sidewalk replacement & sidewalk ramp replacement Storm sewer inlet replacement Consultant: SBB Engineering, LLC Brian Austin, PE 1415 SW Topeka Blvd. Topeka, KS 66612 Ph: Contractor: Sunflower Paving, Inc. Jeff Engroff, President 1457 N 1823 Road Lawrence, KS 66044 (785) Project Funded by City of Topeka City Wide Half-Cent Sales Tax

2 Gage Blvd is currently concrete pavement with joints
PROJECT OVERVIEW – SW Gage Blvd Street Repair General Overview Gage Blvd is currently concrete pavement with joints Repair Joints, Limited Full Depth Replacement Overlay concrete with Asphalt for much smoother ride Limited sidewalk replacement Replace majority of sidewalk ramps Limited curb and gutter replacement

3 Right: Curb and Gutter that will be replaced
Left: Full depth repair of concrete pavement

4 Above: A portion of the existing sidewalk will be replaced to avoid trip hazards.
Above: Sidewalk ramps to be replaced to meet ADA requirements.

5 Above: Example of finished product.
Asphalt pavement, new pavement marking, sidewalk ramps replacement.

6 Above: Unmarked mid-block cross-walks will be removed
Above: Unmarked mid-block cross-walks will be removed. A new Rectangular Rapid Flashing Beacon (RRFB) will be installed on the south side of 23rd Street.

7 Schedule: Start Date – June 18, 2018 Substantial Completion Date – September 28, 2018 Final Completion Date – October 12, 2018 Phase 1 – Temporary Traffic Control June 18 – July 27 (approximate) One lane each direction in existing southbound lanes Left turns prohibited

8 Schedule: Start Date – June 18, 2018 Substantial Completion Date – September 28, 2018 Final Completion Date – October 12, 2018 Phase 2 – Temporary Traffic Control July 28 – September 28 (approximate) One lane each direction in existing northbound lanes Left turns prohibited

9 Questions?