February 26 th 2013Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.

Slides:



Advertisements
Similar presentations
CSC upgrade for LS1 USA-15 rack: layout, construction and installation 11 th February 2013.
Advertisements

Winter shutdown 08/09 Summary of HV interventions Barrel Muon Workshop, 02/09 Jesús Puerta-Pelayo, CIEMAT 17-February-2009.
02-Mar-09A. Cardini / CERN & INFN1 Muon Detector Status (week 9: Feb 23 rd  Feb 27 th ) Present: Ale, Thomas, Nikolai, Oleg, Sasha, Maria Luisa, Perluigi,
Xe leak status C. Garabatos. Leak story The maximum allowable leak rate corresponds to a loss of 10% of the total volume in one year – 0.3 l/h for the.
David Emschermann DCS Workshop – PI Heidelberg – 22/01/2007 How to power up the TRD David Emschermann Physikalisches Institut Universität Heidelberg updated.
Problems with UPS racks last week... During the DSS tests on the weekend Jun 1-2 all racks connected to „interruptable“ UPS were cut by DSS at some point.
19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
Barrel Maintenance Scenario for LS1 MUON-IB CMS week 11 December 2012 A. Benvenuti (INFN Bologna)
ZDC Crane Status 9 Feb 2012, Michael Murray. Test at SX5 Last week the ZDC was taken out via a forklift. Tunnel access closes at 5pm on the 21 st Before.
NSW SG 19 Nov Nov 2014 S. Zimmermann, NSW SG 1.
MDT PS DCS for ATLAS Eleni Mountricha
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
TC meeting P2 planning wks 7&8 A.Tauro
ATLAS MDT Power Supply DCS Anastasios Iliopoulos 15/08/2006.
DCS Plans and Pending Activities for 2013/14 Shutdown Muons in general Replacement/upgrade of DCS computers OS migration to Win-7, Win-2008 or SL6 PVSS.
Gas Coordination Panel 24/08/2004 Flammable Gas Installation Requirements, Interlocks, etc. F.H.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester June 17, 2013.
Muon System Safety Issues Burkhard Schmidt.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
CERN, O.Pinazza: ALICE TOF DCS1 ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and.
G. Pugliese RPC requests for GIF++ G.Pugliese, N. Zaganidis and I. Pedraza on behalf of the RPC group 1.
Main priorities for the next years. Where do we stand Muon system in good shape (in my opinion) – Sub-systems hardware quite robust (see later for main.
+2.5 V 30 A +5.8 V 3 A -3.6 V 25 A +4 V 100 A +4 V 100 A Controller TGC1 subrack organization +4 V 65 A Controller First 84 HP (19”) subrack Controller:
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
All CMS 30 May07 TSV1 All CMS 3 30 May 2007 LHC machine CMS Progress Overall Schedule.
PS VFE & PS/SPD FE Electronics Status and Plans 20 February 2008 LPC Clermont.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester June 24, 2013.
TGC-electronics commissioning before beam collision Y. Sugaya Osaka-U アトラス総会2004 12/23 河口湖.
1 OperationsOperations CSC is stable running since HI run has started. The low CSC occupancy in HI running allows us to operate all HV channels at nominal.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.
P. Paolucci - I.N.F.N. of Napoli 1 RPC workshop, 2 march 07 RPC Power system P. Paolucci, G. Polese and D. Lomidze I.N.F.N. di Napoli.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
ATLAS closing scenario  Where we are  What is still be done before closing (ADO-PO support)  Closing scenario / Procedure / Schedule Prepared by Michel.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Zhen YAN, Muon Offline DQ meeting, 05/10/2015 Signed off runs(express stream) since last Friday meeting Default defects:  MS_RPC_BA_ROD_PROBLEM_1  MS_RPC_BC_ROD_PROBLEM_1.
MUON DAQ WORKSHOP Muon Week, CERN February 2014 Nicoletta Garelli (SLAC)
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
STUDENT LED CONFERENCES FEBRUARY UPDATED SLC SCHEDULE Tuesday, Feb. 9 1st period8:00-9:15 (75) 2nd period9:20-10:35 (75) Lunch10:35-11:15 (40)
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Chambers to be installed in ATLAS MSW on Small Wheel MBT0 on front-face of end-cap electromagnetic calorimeter.
Status of HO Installation Shashi Dugad Tata Institute of Fundamental Research India-CMS Collaboration Meeting, Chandigar April 2007.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
W.Van Doninck February 2010 The CMS muon upscope Restore the TDR version of CMS  ME4 CSC’s and RE4 RPC’s on Yoke YE3  When ? During first long shutdown.
Claudio Bortolin. pump: replaced outlet filter: replaced demineralized cartridge: replaced mechanic filter on air control: replaced SSD chilled water.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
TGC On-Line Monitoring Status for 1 beam Before LHC Startup on TomBox: A single machine (pc-tgc-mon-rod-01) receives all TGC events.
1 Top Level of CSC DCS UI 2nd PRIORITY ERRORS 3rd PRIORITY ERRORS LV Primary - MaratonsHV Primary 1 st PRIORITY ERRORS CSC_COOLING CSC_GAS CSC – Any Single.
Preparation for Running Outline Present Schedule Detector Preparation Requests for dedicated runs –Cosmics, Splashes, Alignment Muon Shifts Experts A.
Atlas status report. LHC Cooldown Status LHC is proceeding with the cooldown and the hardware commissioning L.Evans is asking the experiments to close.
TC meeting P2 planning wks 3&4 A.Tauro
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester Feb 24, 2014.
ATLAS Plenary, Feb. 18th, 05Commissioning1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators.
Muon works in the next months. MDT Up to May 15 Commissioning of EE From May 15 for (at least) 2 moths DCS works – Installation of new hardware – New.
TRT HV System status and plans for LS1 LPI Moscow, K. Zhukov.
LHC during week 45 LHC delivered ~0.837 fb-1 in week 45
Technical Support Activities in EP-ADO-PO
Technical Support Activities in PH-ADO-PO
RPC HV&LV status Introduction HV power supply tender
BLM planning 03/03/2014.
Pierluigi Paolucci & Giovanni Polese
Pierluigi Paolucci & Giovanni Polese
Rack and Interconnect Design in E-plan
Presentation transcript:

February 26 th 2013Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions Zhen Yan February 26 th 2012

February 26 th 2013Muon LS1 operation meeting2 Recap of last week Feb 19 –MDT SmallWheelA/C (LV and grounding) + BEEA/C (all services) had been disconnected by Tiesheng, Jiaming and Haolu. Feb 20 –Big wheel C moved to opening position. –Services of MDT BIL[456][AC]01 and BIL6[AC]13 had been disconnected by Joerg to provide access to inner detector parts –One hook of the 140T crane damaged, the opening process on A side delay about 4 days Feb 21 –MDT gas leak test done ( see detail in Joerg’s input ) –One BCAM damaged ( barrel side A sector 9-11 ) Feb 22 –Anatoli started to work on EO gas leak repairing. Both HV and LV on A and C side had been turned off and physically disabled. Feb 25 –ECT moved to opening position –Removed pc-csc-det-02 from rack Y2816A1 by Kalliopi

February 26 th 2013Muon LS1 operation meeting3

February 26 th 2013Muon LS1 operation meeting4 Muon related activities this week Tuesday 26/02 at 8:00 –Big Wheel A side movement ( TGC + MDT supporting team, impact had been approved ) Thursday Feb. 28th at 6:00 am –Lowering of MDT for sector 13 C side (BOE) : (early morning time) 01/03 or 04/03 –SWC movement ( TGC + MDT supporting team ) –EEL sector 15A installation ( MDT service ) 05/03 and 06/03 –SW-C services disconnection ( TGC + MDT + CSC experts for services disconnecting ) Close the gas valve on chamber side Disconnect HV+Fiber+Alignment at patch panel

February 26 th 2013Muon LS1 operation meeting5 Other issues and discussions Keep 2 desktop machines running in ACR for next few weeks –MDT DCS + TGC HV recovery work Impact for accessing to the USA15 area –Received all the feedbacks. Thanks a lot. –Will submit today Re-submit all PPSPS documents –Any progress? New meeting time had been decided –Every Tuesday 9:00-10:00 Keep to run this meeting weekly until the opening process finish –Move to bi-weekly afterward