The ACCOR Project Status Report and Outlook for 2010 and beyond M.Vanden Eynden on behalf of the ACCOR Project Team 1M.Vanden Eynden (BE/CO) - IEFC Workshop,

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Controls Configuration Service Overview GSI Antonio on behalf of the Controls Configuration team Beams Department Controls Group Data & Applications.
ITIL: Service Transition
FESA 3 Implementation Status Stephane Deghaye BE/CO On behalf of the FESA team and many users.
WG on possible controls restructuring 1 Controls activities of the AB equipment groups A. Butterworth E. Carlier, R. Losito, A. Masi, JJ. Gras, Q. King.
Dr. José Miguel JIMENEZ LS2 Coordinator LHC Performance Workshop (Chamonix 2014) Session 8 - Long Shutdown 2 Strategy and Preparation Chair: José Miguel.
Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
Accelerator Complex Controls Renovation, LHC Excluded Purpose and Scope M.Vanden Eynden on behalf of the AB/CO Group.
Overview of Data Management solutions for the Control and Operation of the CERN Accelerators Database Futures Workshop, CERN June 2011 Zory Zaharieva,
BI SW for LINAC4 On behalf of BE/BI/SW BI software development process Specifications List of BI Systems – Not covered: PSB ring systems Conclusions Lars.
Christophe Delamare EDMS Accelerator Consolidation Workshop GS/ASE activities.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
Controls renovation WorkshopFE Software 1 Front-end software C.H.Sicard.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
14 December 2006 CO3 Data Management section Controls group Accelerator & Beams department Limits of Responsibilities in our Domains of Activities Ronny.
Barriere O, Le Roux P
CERN Accelerators Topology Configuration and Change Management Engineering Department Thomas Birtwistle, Samy Chemli – EN/MEF/DC.
Injector De-cabling Project Project Team Meeting #
Timing upgrades after LS1 Jean-Claude BAU BE-CO-HT1.
Accelerator Consolidation Workshop TE/EPC consolidation plan 2 Jean-Paul Burnet ACC consolidation day, 12/09/2013.
Roles Committees Meetings
Stephane Deghaye (AB/CO) ATC/ABOC days.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Eugenia Hatziangeli Beams Department Controls Group CERN, Accelerators and Technology Sector E.Hatziangeli - CERN-Greece Industry day, Athens 31st March.
1 1. Some recent views ( ) 2 Linac tunnel
AGM-2011 On behalf of CO/FE F.Locci - December 15 th, 2011.
Nov, F. Di Maio, M.Vanden Eynden1 CO Proposal concerning AB Front-End Software Responsibilities First detailed proposal based on the global Front-end.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
How to keep the Injectors running for another 25 years S Baird (on behalf of EN/MEF/ABA) LHC Performance workshop Chamonix January 2010.
CERN Raul Murillo Garcia BE-CO LS1 review – TE-EPC feedback BE-CO LS1 review TE-EPC feedback Raul Murillo Garcia on behalf of TE-EPC Daniel Calcoen Stephen.
Machine Interlocks Upgrading MPE workshopChristophe MARTIN14 th Dec
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
Session 7: I-LHC Organization: Chamonix Summary Session7; Oliver Brüning 1 -session organized in collaboration with D. Manglunki and all speakers.
East Area BTV upgrade 2015_09_03 S.Burger BE-BI-PM V.Clerc EN-MEF-SI I.Francescut BE-BI-ML V.deJesus EN-MEF-SI M.Lazzaroni EN-MEF-EBE … F61 line.
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
26 Jan 06Marine Pace - AB/CO1 LEIR Controls : Gain of Experience for the Running-in of LHC Marine Pace on behalf of AB/CO and LSA.
2. Linac Systems 3. Booster Systems 4. Installation commiss. 5. Building, Infrastruct. 2.1 Ion Source and LEBT, R. Scrivens, BE/ABP 2.2 Radio Frequency.
AT Control Forum First Meeting. Introduction  The AT Controls FORUM :  Is responsible for coordination of the overall strategy for controls activities.
LS1 Review P.Charrue. Audio/Video infrastructure LS1 saw the replacement of BI and RF analog to digital video transport Was organised in close collaboration.
Jan 23rd, 2008M.Vanden Eynden on behalf of the AB-CO Group1 AB-CO MTTR & Spare Part Policy for the LHC Injectors, Experimental Areas & other Facilities.
BE-CO Presentation FESA and O/S Support Post-ACCOR renovations until LS2 Front-End Platforms BE-BI TB, May 21 st, 2015 M.Vanden Eynden on behalf of BE-CO.
Feedbacks from EN/STI A. Masi On behalf of EN-STI Mathieu Donze` Odd Oyvind Andreassen Adriaan Rijllart Paul Peronnard Salvatore Danzeca Mario Di Castro.
POST-ACCOR renovations until LS2 – DEBRIEFING – Marine Pace, CO3 – 17 September 2015 Input from Chris, Marc, Stephen, Stephane, Wojtek.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.
CLIC Interlock System study: from Principle to Prototyping Patrice Nouvel TE-MPE-EP TE-MPE Technical Meeting : 22/03/2012.
Stephane Deghaye (AB/CO) The InCA project - S. Deghaye Accelerator Complex Controls Renovation Workshop Motivations & Objectives.
– Machine Controls Coordinators (MCC): team and role – Overview of renovations during LS1 – Proposal for after-LS1 Commissioning organization ACCOR PROJECT.
Agenda 1 BOSS Meeting - 27/5/ : :10 Introduction and aims of the workshop 10‘ 09: :25 Priorities from OP for PSB and transfer lines 15'
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
Proposal: Use of ECRs for “Controls” Changes and Renovations Rende Steerenberg, Samy Chemli, Marine Gourber-Pace, Klaus Hanke, Verena Kain, Bettina Mikulec,
The OP Viewpoint on the Accelerator Complex Controls Renovation R. Steerenberg on behalf of the OP group Accelerator Complex Controls Renovation Workshop.
Dr. José Miguel JIMENEZ LS2 Project Leader, CERN 1 LS2 Days 30 th September2015.
1 st of April st LS2C LS2 Committee Mandate and Organization 2 Chairman:Jose Miguel JIMENEZ Deputy:Jean-Philippe.
Radio Frequency Andy Butterworth AB/RF Accelerator Controls Renovation WS 3 Dec 2008.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
LSA Core overview 6 / 11 / 2007 Wojciech Śliwiński (AB-CO-AP) on behalf of LSA team.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
AB-CO Exploitation 2006 & Beyond Presented at AB/CO Review 20Sept05 C.H.Sicard (based on the work of Exploitation WG)
LS1 Review BE-CO-SRC Section Contributions from: A.Radeva, J.C Bau, J.Betz, S.Deghaye, A.Dworak, F.Hoguin, S.Jensen, I.Koszar, J.Lauener, F.Locci, W.Sliwinski,
PS Complex Controls Renovation S Baird AB/ABP ATC/ABOC Days: Session Jan 2008.
V4.
ITIL: Service Transition
Accelerator Controls Renovation Project “ACCOR”
Status and Plans for InCA
EC Activities Status for the LIU
Renovation of the Accelerators Controls Infrastructure and its Assets Management Asset and Maintenance Management Workshop November 14th, 2013 Cl.Dehavay.
GIS PORTAL RACKS Integration of Equipment Racks in the Geographic Information Service (SMB/SE) Olivier Barrière.
Interlocking of CNGS (and other high intensity beams) at the SPS
Experimental Areas – LS2 planning
Presentation transcript:

The ACCOR Project Status Report and Outlook for 2010 and beyond M.Vanden Eynden on behalf of the ACCOR Project Team 1M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, 2010

Preamble Project snapshot 2009 : achievements and open Issues Context changes and impact Proposals for 2010 A quick summary of the technical progress A list of strategic options to be discussed at both technical and managerial levels M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What is this presentation about? What can Audience expect?

Preamble Project snapshot 2009 : achievements and open issues Context changes and impact Proposals for 2010 M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What is this presentation about?

Project Snapshot Control system renovation of all machines, LHC excluded Budget : –4.6 MCHF P+M (agreed mid-2009) –Period Hardware Obsolescence Need for Application software rationalization Need for having one (and only one) model of responsibilities for the development and operation of the control system of the entire Accelerator complex M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Scope Motivations

Project Snapshot High dependence on LHC Operational Schedule High dependence on the global Injectors consolidation project (S.Baird) High dependence on strategic choices such as SPL and PS2 Complex planning involving several Equipment Groups from BE, EN, TE and GS departments But at the same time, we are hitting now the end-of-life of several components (more on this later) M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, An evolving Context

Controls Core InCa Software, S.Deghaye Front-End Software, A.Radeva Hardware Modules & Device Drivers Hardware Platforms & Layout, N.de Metz-Noblat Data Management, R.Billen Systems Beam Instrumentation, L.Jensen (BE/BI) Beam Transfer, E.Carlier (TE/ABT) Power Converters, Q.King (TE/EPC) Radio Frequency, A.Butterworth (BE/RF) Interlocks, B.Puccio (TE/MPE) Controlled Access, P.Ninin (GS/ASE) Dumps and Targets, A.Masi (EN/STI) CONTROLSRENOVATIONWBSCONTROLSRENOVATIONWBS CONTROLSRENOVATIONWBSCONTROLSRENOVATIONWBS Generic FESA Classes, FESA 3.0 Specs Vacuum, P.Gomez (TE/VSC) Controls Config DB, Layout DB, … LSA, CBCM, ACQ Core, … VME, PICMG1.3, cPCI, Linux,… HW design & production E.Van der Bij HW design & production E.Van der Bij Management Project Leader, M.Vanden Eynden (BE/CO) Budget BE-CO Budget, M.Draper (BE/CO) Procurement & Installation Procurement & Installation Hardware Purchase & Spares, Ch.Gayraud (BE/CO) Field Installation & Coordination, C.Dehavay (BE/CO) 627/5/09M.Vanden Eynden - BE/CO Magnets, L.Walkiers (TE/MSC) Device Drivers D.Gonzalez Cobas Device Drivers D.Gonzalez Cobas

Project Snapshot M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Roadmap PROJECT ACCEPTANCE TECH CHOICES & PROCURMENT DESIGN AND INTEGRATION APPL PROTOTYPING OPERATIONAL DEPLOYMENT … 13

Preamble Project snapshot 2009 : achievements and open issues Context changes and impact Proposals for 2010 M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What is this presentation about?

2009 : Achievements and Open Issues Organization and sharing of responsibilities CO3 –Based on the LHC approach (major culture change for the injectors complex) Solid Technical choices CO3 –New Hardware platforms (VMEbus, cPCI, PCI, PCIe) Processors, Linux O/S, HW development strategy –FESA as embedded RT software framework Re-use of some LHC Q&A principles CO3 –Layout DB –Asset Management –Naming Convention M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Achievements - Strategy

2009 : Achievements and Open Issues Global ACCOR Budget established and approved mid-2009 –4.6 MCHF covering Front-End processors and crates Hardware modules (design and mass production) Human resources (PJAS, UPAS, etc) Large Tendering processes through CERN Finance Committee for: VMEBus Processors (done) PCI/PCIe PICMG1.3 Platform (done) VMEBus crates (Starting Nov > June 2010) M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Achievements – Financial

2009 : Achievements and Open Issues Hardware Platforms –Integration of new Intel Core2Duo VMEbus processors + Linux O/S quite well advanced. –Standardization of PICMG1.3 as the new cost-effective PCI/PCIe solution with several candidate applications –Development systems and prototyping activities running in several Eq.Groups Integration Roadmap –Collection of “Standard” HW modules + Linux Device Drivers + FESA Classes has been proposed by CO3 committee (priority list + timetable) Front-end Software –Sharing of the existing GM software classes (> 125) between all parties is agreed. Migration of “generic classes” remains under BE-CO responsibility and has started (in sync with the HW modules design) M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Achievements – Technical

2009 : Achievements and Open Issues InCA - Application & Business Software Layers –Objectives Rationalise and homogenise the high-level controls Use LHC components e.g. LSA for the settings management –Introduce extensions whenever required by the PS complex accelerators Introduce an “acquisition service” to relieve the Front-end computers from high client load Review and integrate central timing in the overall control system –Use BE/CO standard approach and components Produce specifications for FESA 3.0 and specify an Application Programming Interface (API) to ensure smooth integration of new Front- end software developments –Validation through several iterations and MDs in 2009 (LEIR) M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Achievements – Technical

2009 : Achievements and Open Issues Dedicated P2P discussions with Equipment Groups –BE/BI, TE/ABT, BE/RF, TE/EPC, TE/MPE, TE/MSC –Several key technical options agreed Use industrial PC platform for –Power Converters (MIL-1553 and serial) –Kicker systems (PS complex) –SPS RF system (MIL-1553) –First batch of operational objectives Objective to renovate the SPS MUGEFs with the new VMEBus processors and Linux Installation of 120 FGCs on Booster (shutdown ) Installation of 350 FGCs on SPS North Area (shutdown ) Objective to renovate all BI BTV front-ends on all machines (>27 systems) with the new VMEBus processors and Linux Objective to renovate the BI SPS North Area installation with the new VMEBus processors and Linux First deployment proposals for Beam Interlock Controllers (Booster in 2014) M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Achievements – Operations

2009 : Achievements and Open Issues –New sharing of responsibilities, mainly at the Front-end software level will require dedicated efforts in 2010 BE-CO can only ensure “corrective maintenance” of existing GM classes Inventory of systems, understanding of software behaviors and interfaces are, in many cases not transferred yet to Eq.Groups BE-CO will stimulate the process but ownership transfer must be effective if we want: –a more solid renovation plan coherent with the other activities of the Eq.Groups –More inputs for the “design an integration” work done by BE-CO –Operational deployment objectives We have some objectives but we lack a global vision compared to the complexity of the problem up-front Who owns the overall renovation planning for each Accelerator, as controls is just one element of the problem? –In some cases, Eq.Groups lack resources and the front-end software level BE-CO is ready to accept this work, provided that these systems are clearly identified and that BE-CO received the ad-hoc resources for the development and maintenance effort Typical examples : B-train systems, machine protection systems An exhaustive list of systems + resource estimates must be agreed in 2010 M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Open Issues

Preamble Project snapshot 2009 : achievements and open issues Context changes and impact Proposals for 2010 M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What is this presentation about?

Context Changes and Impact M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Long LHC Operational Run Impact on Planning Impact on Reliability Major hardware renovation campaigns on the LHC injectors will be postponed until end Example : Booster Power Converters Upgrade with LHC type FGC3 (x120) Focus on AD, CTF, REX-ISOLDE Months BE-CO not in a position anymore to guarantee support for obsolete hardware solutions supposed to be eradicated since 1993 … No test bed, almost no spares in unknown state, impossible to repair (> 30 years old) PO and CO have to work on this! BE-CO not in a position anymore to guarantee support for obsolete hardware solutions supposed to be eradicated since 1993 … No test bed, almost no spares in unknown state, impossible to repair (> 30 years old) PO and CO have to work on this!

Context Changes and Impact M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Upgrade of Accelerator Complex This should provide A high-level upgrade plan, along with priorities for controls This should provide A high-level upgrade plan, along with priorities for controls

Preamble Project snapshot 2009 : achievements and open issues Context changes and impact Proposals for 2010 M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What is this presentation about?

Proposals for 2010 BE-CO –continue the design, integration and production of core control system components (HW and SW) – roadmap exists HW modules, FESA 3.0 framework and generic FESA classes –Run tendering process for electronics subracks VMEBus, cPCI, general purpose crates –Continue the Inca development, validation and deployment – solid plan exists EQ-Groups –Validate BE-CO deliverables – important technology shift –Identify performance problems and fix them with the support of BE-CO –Develop and validate prototype applications M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Technical perspective

Proposals for 2010 For each Accelerator –Review current controls situation –Identify areas requiring most urgent controls renovation (obsolescence, performance problems) –Develop action plan between CO, OP and Eq.Groups –Link this to the general renovation planning (see later) To achieve this: –Machine Controls Coordinators (MCC) are mandated in BE-CO in order to propose concrete action plans for each Accelerator M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Operational objectives

Proposals for 2010 ACCOR will provide (through the MCC) a prioritized list of controls renovation actions (scope, resources, time estimates) These proposals need to be combined with: –Other urgent consolidation initiatives –Modifications and or extensions required in the context of the forthcoming Booster and SPS upgrade studies (cf. Chamonix workshop session 7 summary) A high-level planning effort seems now mandatory as it is agreed that the current complex must run with high performance and high reliability until 2025 M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, Overall Renovation Plan

Conclusions The ACCOR project has solid asset in terms of budget, technical strategies and sharing of responsibilities between all parties Many resources in BE-CO are actively working on this project A first roadmap exists for the procurement of core controls components Eq.Groups are actively validating the new technological choices The need to run the existing complex until 2025 is clear to everybody M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What is OK

Conclusions We lack operational objectives -> Machine controls coordinators will enter in action in 2010 We are hitting the LIMITS in terms of hardware obsolescence and the long LHC run requires immediate decisions in some areas (PO, CO) Ownership of front-end software must become a reality in BE-CO has the know-how and is ready to help Eq.Groups Some Eq.Groups lack competences and resources at the front-end software level. BE-CO can only take this responsibility if an exhaustive list of such systems exists, along with resource estimates and provision Important decisions are being taken after the Chamonix WS, we need now a high-level upgrade plan to which, of course, ACCOR will provide inputs. M.Vanden Eynden (BE/CO) - IEFC Workshop, Feb 10th, What has to be improved in 2010