VLCW06 - 20 July Global Design Effort1 Installation Global System Review F. Asiri W. Bialowons, T. Shidara Acknowledgment: C. Hauviller, R. Sugahara C.

Slides:



Advertisements
Similar presentations
Wednesday July 19 GDE Plenary Global Design Effort 1 Instrumentation Technical System Review Marc Ross.
Advertisements

Discussion on EUROTeV and ILC Nick Walker (DESY) EUROTeV Kick-off Meeting DESY 1 November 2004.
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
1 DOE Annual Review -June 15,2005 An Overview of Conventional Facilities (Civil Construction) U. S. ILC Civil studies and cost issues for Snowmass Fred.
GDE Meeting B Barish 16-Aug-05 The GDE – who, what and how? The BCD – what is it? Internal Organization toward BCD What do we want out of Snowmass? How.
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
Status of ILC Barry Barish Caltech / GDE 17-Aug-07.
Global Design Effort - CFS CLIC 09 Workshop - WG 5 Technical Systems 1 CLIC 09 WORKSHOP Working Group 5 - Technical Systems ILC REBASELINE ILC.
Global Design Effort - CFS ILC Global Systems Meeting 1 ILC GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP Status and Overview.
High Level RF Technical System Review GDE Cost Review July Vancouver Canada Shigeki Fukuda & Ray Larsen For the HLRF Cost Team C. Adolphsen,
Global Design Effort U.S. ILC Cost Translation R. Stanek, et al. Vic Kuchler 1/26/07.
Report from GG5, Dec. 20, 2005 Report from ILC GG 5: Cost and Engineering (Updates since Snowmass) Wilhelm Bialowons, Peter Garbincius and Tetsuo Shidara.
SLA – Oct. 07 BDS-KOM1 Installation Overview Acknowledgment: F. Peters, M. Munro, J. Kim G. Aarons, C. Corvin, P. Rodriguez Fred Asiri/SLAC.
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update November.
Sendai, March 3, 2008 TILC08 · GDE Meeting Global Design Effort 1 TILC08 · GDE Meeting on International Linear Collider · Tohoku University Sendai · Japan.
US ILC Review by DOE/NSF Apr. 4-6 at Fermilab Consultant reviewers: Ilan Ben-Zvi (BNL/ATF &RHIC) Dixon Bogert (FNAL/NUMI) Isidoro Campisi (ORNL/SNS) Tom.
Nick Walker, Brian Foster LAL, Orsay WP2: Coordination with the GDE.
RDR Report Writing Nan Phinney SLAC for RDR team of editors.
Global Group 4 – Conventional Facilities and Siting V. Kuchler1 of 17 Fermilab R&D Meeting Fermilab R&D Meeting Vic Kuchler Conventional Facilities.
LCFOA Meeting at SLAC Linear Collider Forum of the Americas 1 LINEAR COLLIDER FORUM OF THE AMERICAS CONVENTIONAL FACILITIES OVERVIEW Victor R. Kuchler.
International Linear Collider The ILC is the worldwide consensus for the next major new facility. One year ago, the choice was made between the two alternate.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
November 17, st XFEL / ILC Meeting 1 ILC GLOBAL Design Effort The Current ILC Twin Tunnel Design Wilhelm Bialowons and Nicholas Walker · MPY.
RDR Report Writing Nan Phinney SLAC. 7/20/06 VLCW06 Global Design Effort 2 GLC Report Working model is the 2003 GLC Report ch 4-7
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
19 July 2006 Vancouver Global Design Effort 1 Cryogenic Systems Review Tom Peterson for the cryogenics global group.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Operations, Test facilities, CF&S Tom Himel SLAC.
Global Design Effort 1 Possible Minimum Machine Studies of Central Region for 2009 Reference, ILC Minimum Machine Study Proposal V1, January 2009 ILC-EDMS.
CLIC cost estimate Hans-H. Braun, CLIC-GDE meeting, February 8, 2008  Cost model goals  Methodology  Cost distribution  Future improvements.
6-10 Nov. 06 ILCWS Valencia Global Design Effort 1 RDR Management Board Overview K. Yokoya KEK.
Global Design Effort - CFS ILC Accelerator Design and Integration Meeting 1 ILC AD&I MEETING CONVENTIONAL FACILITIES AND SITING GROUP UPDATE V.
Cost Model including Civil Engineering and Conventional Facilities Hans-H. Braun, CLIC ACE, June 20, 2007  Cost model goals  Methodology  Scaling assumptions.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Global Design Effort - CFS GDE Plenary Session 1 LCWS10 GDE Plenary Session SB 2009 ILC CONVENTIONAL FACILITIES AND SITING GROUP A. Enomoto, V.
Nick Walker – SA meeting KEK Treaty Points and Costing Guidance Nick Walker 1 st System Area Managers Meeting KEK –
Status of the International Linear Collider and Importance of Industrialization B Barish Fermilab 21-Sept-05.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
CLIC Workshop, CERN 1 CLIC/ILC Collaboration Report: Marc Ross (Fermilab); for Nick Walker, Akira Yamamoto Project Managers International Linear.
1 Global Design Effort: Control System Vancouver GDE Meeting, July 2006 Controls Global System Review John Carwardine, ANL (For Controls Global Group Team)
Global Design Effort - CFS Damping Ring Baseline Technical Review 1 DAMPING RING BASELINE TECHNICAL REVIEW CONVENTIONAL FACILITIES AND SITING.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
20 July 2006 Vancouver GDE Meeting Global Design Effort 1 Ring to Main Linac Peter Tenenbaum SLAC.
Global Design Effort - CFS DESY Accelerator Design and Integration Meeting 1 ACCELERATOR INTEGRATION AND DESIGN MEETING CONVENTIONAL FACILITIES.
Global Design Effort: Controls & LLRF Americas Region Team WBS x.2 Global Systems Program Overview for FY08/09.
Tor Raubenheimer KEK Mtg Goals KEK January 19 th, 2006.
Goals of the ILC-Asia Meeting at Pohang Fumihiko Takasaki PAL, Feb. 17, 2006.
M. Ross, N. Walker, A. Yamamoto th ATF2 Project Meeting Accelerator Design and Integration – New Baseline Proposal for ILC – ‘Strawman Baseline.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
PM Report AS ILC PAC (19-20 May) Agenda: –Akira, Rongli, Hitoshi H, Marc, Nick, Toshiaki, Mark P., Peter G. –Nick will report on Design –Marc.
Fred Asiri1 Conventional Facilities and Siting Global Group (CFS) SLAC Update Conventional Facilities and Siting Global Group (CFS) SLAC Update December.
CFS / Global – 09 June, 2010 PM Report: SB2009: –4 two-day workshops form the core of ‘TOP LEVEL CHANGE CONTROL’ –  as advised by AAP, PAC and etc –Written.
1 R&D Plans for Impedance Driven Single-Bunch Instabilities (WBS 2.2.1) M. Venturini ( presented by M. Zisman) LBNL LCWS07 DESY, Hamburg May 30 - June.
Global Design Effort - CFS ILC CFS & Global Systems Meeting 1 ILC CFS & GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP CFS Status.
Main Linac Technology (MLT) Meeting To be held through WebEx July 13, 2007.
November 12-13, 2007 Super-B Factory: Accelerator Costing, PEP-II Hardware and Schedule J. Seeman SLAC International Review Committee meeting November.
Global Design Effort - CFS ILC CFS and Global Systems Meeting 1 ILC CFS AND GLOBAL SYSTEMS MEETING CONVENTIONAL FACILITIES AND SITING GROUP CFS.
ILC CONVENTIONAL FACILITIES A. Enomoto, V. Kuchler, J. Osborne
ILC CONVENTIONAL FACILITIES A. Enomoto, V. Kuchler, J. Osborne
Conventional Facilities and Siting Global Group (ARCFS)
Installation Global System
LCWS11 AWG9 PARALLEL SESSION SUMMARY
Americas KlyCluster Cost Analysis Overview
EDR HLRF Work Packages Draft Summary
Yamamoto WG3: ML-SCRF Parallel Session,
Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007 Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri.
Yasuhiro Okada, Executive Director, KEK
Update on the JLEIC pCDR
Presentation transcript:

VLCW July Global Design Effort1 Installation Global System Review F. Asiri W. Bialowons, T. Shidara Acknowledgment: C. Hauviller, R. Sugahara C. Corvin, G. Aarons, M. Munro, F. Peters, B. McKee, P. Rodriguez,

VLCW July Global Design Effort 2 Status Prepared WBS to level 5 Obtained all pertinent material on similar installation –PEPII, SSC, SLC, Spear II, APS, Fermi Main Inj, KEKB, LHC –None offer a one-for-one scalable comparison, but collectively they provided a range “ 2% to 12%” an average of 7% Identified “Point of Contact” for each T.S. and A.S. Attempted to obtained components list from T.S. and A. S. managers –The list is lately received and is partially complete –The equipment installation details are not yet confirmed Established subsystem interfaces/Boundaries –Qualitatively and softly defined Established an Installation and costing plan

VLCW July Global Design Effort 3 Compiled, studied and discussed the data obtained for installation cost estimate of other projects –LHC, KEKB, TESLA, NLC, etc Visited CERN and DESY –Discussed and obtained parametric data for LHC installation –Observed installation of Cryomagnets and CMS detector –Participated in the ILC Main Linac cost model meeting in DESY Discussed and obtain data for installation from XFEL presentations Discussed installation issues related to ILC Main Linac Applied RSMeans approach for the equipment installation cost as percentage of total project cost –RSMeans is N. America’s leading supplier of construction cost information and provides accurate and up-to-date cost data –Established a range (5% to 8% ) Installation Cost Estimate Approach

VLCW July Global Design Effort 4 Obtained the detailed WBS for installation cost estimate for USLCSC for cold machine (5% to 7%) –Compared scope, complexity and salient features with the ILC Baseline machine –Used the parametric data available and scaled to match –Discussed the results in numerous meetings and made collective judgment –Results presented in the Installation WBS format and discussed with the other installation co-leader Installation Cost Estimate Approach

VLCW July Global Design Effort 5 Each cryomagnet costs about 1000K MCHF –Procurement and Maintenance: 26 MCHF –Operation: 23 MCHF Due to presence of fragile components, tolerance of the internal parts must maintained with in ±0.1 mm during shipping, handling and installation –Most of the cryomagnets were installed on site, too many handling –Special customized transport system used –Special care in handling, transport an installation became necessary –In tunnel transport maximum speed, 3K/hr It took at least 5 days to complete on site assembly and 5 days for testing prior to installation Installation team consisted of total 70 people (Eng, Tech, Operator) Installation rate: initially 10 cryomagnets per week, now up to 30 working 24 hours a day, 7 days a week Notes from LHC Cryomagnet installation at CERN:

VLCW July Global Design Effort 6 Metric: ~53.50/hour $US, (~79.17/hour $US with Overhead & Profit) ~1676 hours/year Installation Cost Model for Equipment in Tunnels

VLCW July Global Design Effort 7 Installation Cost Model in Tunnels 724 Main Linac HLRF AC-DC Power Units With: Added Tunnel Equipment Handling $104,182,594 Without: Added Tunnel Equipment Handling - $ 95,855,560 $ 8,327,034 Percent added = ~100M $US Level

VLCW July Global Design Effort 8 Overall Project Installation Cost Extension Ranges Installation: Surface & Tunnel Cost Percent added = ~1B $US Level

VLCW July Global Design Effort 9 Installation: Cost Parameters Installation Cost Adders & Scale by Size & Location ~10% ~10M $US Level ~ 11.2 man-years in Tunnels ~ 8% ~100M $US Level ~ 89.2 man-years in Tunnels ~ 6% ~1,000M $US Level ~ 669 man-years in Tunnels & Surface ? 4% ~10,000M $US Level ~ 4461 man-years for ILC Project? Metric: ~1676 ~53.50/hour $US

VLCW July Global Design Effort 10 Level 4 Rollup WBS Installation WBSComponent 173 Installation 1731 General Installation 1 Logistics Management 2 Engineering Support 3 Equipment 4 Vehicles 5 Shipping-Receiving 6 Warehousing 7 Surface Transport 1732 Area System Installation 1 Sources e- Area Installation 2 Sources e+ Area Installation 3 Damping Ring Area Installation 4 RTML Area Installation 5 Main Linac Area Installation 6 Beam Delivery Area Installation

VLCW July Global Design Effort 11 On the surface Installation work WAREHOUSING PICKING SYSTEM RACKS CONVEYORS LIFT TRUCKS DOCKS CUSTOM EQUIPMENT MACHINE TOOLS ELECTRONIC TEST MAGNET MEASUREMENT RF TEST QUALITY CONTROL ASSEMBLY INVENTORY CONTROL MANAGEMENT STAGING MANAGEMENT COST CONTROL VEHICLES TRUCKS PEOPLE MOVERS

VLCW July Global Design Effort 12 In the tunnel Installation work

VLCW July Global Design Effort 13 Plans and Goals Near Term In this workshop meet with each T.S and A.S group –To review scope and content of each T.S. WBS –To understand scope of on site testing –To identify any omission, overlapping, double counting Between this and the Valencia workshop –To define scope of on site deliverable for each subsystem –To define the subsystem installation requirements –To establish subsystem interfaces/Boundaries –To review and continue to refine the parametric installation cost Estimate –To incorporate adjustments and Inputs from Area and Technical Systems as Required and Complete the Installation Portion of the Reference Design Report for Submission at the Valencia GDE Meeting in November, 2006 Franz Peters has joined SLAC Installation group part time (0.5 FTE) M. Munro, B. McKee, P. Rodriquez will provide additional support

VLCW July Global Design Effort 14 Goal: to produce an integrated Installation process for the ILC Baseline in full cooperation with other regions –Set-up and manage an installation data base in FY 07 that can be expanded in a full pledged program through FY 08 and FY 09 toward TDR –Proposed estimated level of effort for the American Region toward TDR FY 07;1.5 FTE and ~ $100K M&S (contract) FY 08; 2 FTE and ~ $200K M&S (contract) FY 09; 2 FTE and ~ $200K M&S (contract) –Needs same level of effort from the other regions to perform a real bottom-up cost estimate Installation G.S Long Term Plan