Presentation is loading. Please wait.

Presentation is loading. Please wait.

Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007 Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri.

Similar presentations


Presentation on theme: "Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007 Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri."— Presentation transcript:

1 Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007
Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri

2 A Tentative CF&S Work Plan Approach for EDR
Fred Asiri

3 A Tentative CF&S Work Plan Approach for EDR
Goal: To apply the first iteration cycle of the Work-Plan, focusing on e- Sources, Beam Delivery and Interaction Region Approach: Will be based on Systems Engineering Management Define physics functional requirements Identify the range; Acceptable, Preferable, Desirable Define boundaries, interfaces, utility needs and functional environment Define physics requirement to an engineering requirements Initiate a CFS Design Configuration Control Document Put under Interface Control Identify Optimization Studies Design Alternatives Trade-Offs Trade Studies Constructability Studies Value Analysis Studies Fred Asiri

4 Activities Update Since November 5, 07
All three regions contributed to the following CFS accomplishments: An overall Work Breakdown Structure (WBS) for the CE/CF effort was developed that reflected work required for the development of the EDR . The WBS were prioritized and the highest priority items were then developed into CE/CF work packages with suggested milestones and completion dates. Project Management Plan (PMP) with milestones for the highest priority work packages was developed and submitted to the Project Management Group. An initial comprehensive Area System criteria list was developed. This criteria list will be used, with necessary adjustments, to collect data from all of the Area Systems in the coming months and will serve as the basis for the EDR CFS design Fred Asiri

5 Activities Update Since November 5, 07
The points of contact will be the primary focus for the gathering of criteria. Those primary responsibilities are: T. Lackowski Main Linac - T. Lackowski with A. Enomoto J. Osborne e- Source - G. Aarons e+ Source - J. Osborne Damping Ring - T. Lackowski with A. Jackson RTML - FNAL person to be determined F. Asiri BDS - F. Asiri Interaction Region - J. Osborne Fred Asiri

6 Activities Update Since November 5, 07
Following is an excerpts from BDS –CFS criteria spreadsheet: Fred Asiri

7 Activities Update Since November 5, 07
All three regions contributed to the following CFS accomplishments, continued: A review of the CFS cost estimate was initiated at the GDE Meeting held at Fermilab in October, 2007. Additional work was conducted in the weeks that followed. The result is: A CFS cost estimate that has been reconciled between the three regions, Is consistent with the information contained in the Reference Design Report and adjusted to correct minor discrepancies that had been identified by the Cost and Scheduling Group The first in a series of value management reviews was organized, in conjunction with consultants from the U. S. Army Corps of Engineers Goal; to identify options for value improvement and cost reduction with respect to the ILC Main Linac process cooling water system. The review was held at Fermilab, Nov 27-29, with international participation both in-person and by Video. Fred Asiri

8 Activities Update Since November 5, 07
Main Linac Value Management Workshop-11/07 Workshop to comprehensively examine the power and cooling system requirements and design solutions leading to ideas that will reduce the connected power, power usage and operating costs for the project Followed U.S. Army Corps of Engineers Format Agenda and presentations at: Concentrated on largest power user, the Main Linac examined all aspects of the technical equipment and conventional equipment as it relates to power and cooling Speculation Phase -> Functional Analysis Phase (FAST Diagrams) -> Development Phase Planning Fred Asiri

9 Activities Update Since November 5, 07
Fred Asiri

10 Activities Update Since November 5, 07
Functional analysis methodology How ; Why ; when Fred Asiri

11 Activities Update Since November 5, 07
Close-out Over 50 items prioritized Top 13 listed were developed into Work Packages 13 WP Proposals to be bid on by Labs or others Fred Asiri

12 Activities Update Since November 5, 07
Anticipated work in the coming months: Generate and distribute criteria lists to all Area Systems (tailored as needed for general as well as area specific criteria). Establish EDR points-of–contact with all Area Systems and Technical Systems as needed. Continue to develop CE/CF plan for EDR definition and completion for presentation at the GDE Meeting in March, 2007 with consideration for available resources and work package assignments. The CFS Group will explore with CERN issues common to the ILC and CLIC projects that have strong mutual interest and overlap in the Conventional Facilities area. Fred Asiri

13 A Tentative CF&S Timeline for EDR
Fred Asiri


Download ppt "Conventional Facilities and Siting Global Group (CFS) SLAC Update December 10, 2007 Acknowledgment: Jerry Aarons, Clay Corvin, and Esther Kweon Fred Asiri."

Similar presentations


Ads by Google