Presentation is loading. Please wait.

Presentation is loading. Please wait.

ILC CONVENTIONAL FACILITIES A. Enomoto, V. Kuchler, J. Osborne

Similar presentations


Presentation on theme: "ILC CONVENTIONAL FACILITIES A. Enomoto, V. Kuchler, J. Osborne"— Presentation transcript:

1 ILC CONVENTIONAL FACILITIES A. Enomoto, V. Kuchler, J. Osborne
LCWS10 Final Plenary ILC CONVENTIONAL FACILITIES AND SITING GROUP A. Enomoto, V. Kuchler, J. Osborne

2 Parallel Sessions March 27
Morning Session 1 GDE Plenary for Beyond SB 2009 Morning Session 2 and Afternoon Session 1 Joint Session with Main Linac and HLRF Discussion of KCS and DRFS Alternatives More Detailed Cooling and Electrical Requirements were Established Update on R&D Status of Both Systems Was Presented Presentation was Provided for Experience with Cryomodule Installation at DESY XFEL Tunnel Model CFS Also Participated in a Joint Session with MDI/BDS Afternoon Session 2 Review of Civil Engineering Design for the Asian Region and General Discussion

3 Current ML KCS Tunnel Cross Sections
Americas Region 4.5 m Dia. European Region 5.2 m Dia.

4 Current ML DRFS Tunnel Cross Sections
Americas Region 5.2 m Dia. Asian Region 5.2 m Dia.

5 Current ML KCS Equipment Design Progress

6 Current ML DRFS Equipment Design Progress

7 Single Tunnel Installation Review

8

9 Asian Regional Tunnel Configuration
Single-tunnel “Accelerator” Configuration Reduce tunnel numbers from “BmT+SvT+AcT” to “SgT+AcT” (1) Less surface facilities (2) Life Safety (3) Spontaneous Drainage (4) Avoid tunnel excavation risk (5) Radioactivation free TDP2 Cavern Cavern RDR Access Tunnel Sub-tunnel Double-Tunnel Accelerator Single-Tunnel Accelerator

10 Overall Civil Layout (Final)
Legends Detector Hall Only 3 Cooling Tower Farm Cryoplants Access / Evacuation Passages Local Substations Cooling Towers Main and Sub Tunnels Access shafts / sloped tunnels Cooling Tower Cooling Tower Cooling Tower Cryoplants Detector Hall Cryoplants Cryoplants Cryoplants Cryoplants Cryoplants Cryoplants Cryoplants Cryoplants Local Substation Drainage Passage Local Substation Access/Evacuation Passage Cryoplants

11 Parallel Sessions March 28
Morning Session 1 & 2 Joint Session with Area Systems to Discuss SB2009 Central Region Configuration Review of Americas Region Tunnel Cross Sections Webex Presentation for European Updated Central Region Beam Component Layout and Integrated with CERN 3D Tunnel Configuration Afternoon Session 1 General Discussion of CFS Support Utilities Specific Presentations Provided Describing Progress in Asian and Americas Region Additional Discussion with Representatives of HLRF Working Group Afternoon Session 2 Discussion to Finalize the Dubna Soil Investigation Report Regional Presentations Describing the 3D Modeling Progress

12

13

14 Parallel Sessions March 29
Morning Session 1 Regional Review of CFS Budgets FY 2010 through FY 2012 General Planning Discussion on Resource Allocation and Near Term Priorities for TDP II Morning Session 2 Review of Tunnel Life Safety and Egress Plans with Emphasis on Approaches Used in Asian and Americas Region Afternoon Session 1 CFS TDP II Planning and Preparation of CFS Final Plenary Presentation Afternoon Session 2 GDE Plenary Session


Download ppt "ILC CONVENTIONAL FACILITIES A. Enomoto, V. Kuchler, J. Osborne"

Similar presentations


Ads by Google