W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.

Slides:



Advertisements
Similar presentations
Chapter 7 Managing Risk.
Advertisements

PROJECT RISK MANAGEMENT
Note: See the text itself for full citations. Information Technology Project Management, Seventh Edition.
Chapter 7: Managing Risk
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Project Change Management
M. Reichanadter, SLACLCLS FAC Meeting - April 29, 2004 LCLS Organization & Execution M. Reichanadter LCLS FAC Meeting April 29, 2004 LCLS.
Project Risk Management
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
J. B. Hastings LUSI Overview LCLS FAC March 20, 2007 LUSI Overview J. B. Hastings January 2007 Lehman Review Response to Lehman Review.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
M. Reichanadter LCLS Project June 2008 FAC Meeting Report to the LCLS Facilities Advisory Committee Project Management.
1 April 2010 TX SET Timeline Project Conceptualization 11 weeks Market Requirements 12 weeks ERCOT Requirements 12 weeks Conceptual Design 6 weeks Detail.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
1 T. Fornek 1 LUSI CXI FIDR June 3, 2009 Thomas Fornek Project Manager June 3, 2009 LUSI Coherent X-Ray Imaging Instrument Final.
1 T. Fornek 1 LUSI XCS FIDR June 17, 2009 Thomas Fornek Project Manager June 17, 2009 LUSI X-Ray Correlation Spectroscopy Instrument.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
David Pindroh Procurement Overview LUSI DOE Review 8/19/08 – 8/21/08 p.1 LCLS Ultrafast Science Instruments (LUSI) David Pindroh – LCLS Procurement Manager.
Management of a Training Program January 12 – 14, 2009.
Project Risk Management. The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding.
Server Virtualization: Navy Network Operations Centers
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 BROOKHAVEN SCIENCE ASSOCIATES Project Performance & Risk Management Aesook Byon, Deputy Project Director NSLS-II PAC Meeting February 8-9, 2011.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
Project management Lecture 10. Topics covered Management activities Project planning Project scheduling Risk management.
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
Project Life Cycle.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
@2002 Copyright, Itreya Technologies CMMI kick off July 2005.
TOF Project Construction Project Plan
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Felix B. Fernandez LUSI DOE Review August 20, 2008 PMCS Overview p. 1 LCLS Ultrafast Science Instruments (LUSI) Felix B. Fernandez.
Project Risk Management Planning Stage
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
The Project Plan Plan Your Work, then Work Your Plan
Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.1 LCLS Ultrafast Science Instruments (LUSI) T. Fornek – Project.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
Project Management Processes for a Project Chapter 3 PMBOK® Fourth Edition.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
Week 2 – Risk Planning & Identification. Risk & Risk Management.
6/6/ SOFTWARE LIFE CYCLE OVERVIEW Professor Ron Kenett Tel Aviv University School of Engineering.
- 1 - Case Elaboration. Design Closing XPMR PMR Definition of Results RS Risk Analysis RA PMR n every 6 months Execution Multiannual Planning PEP.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Project Management PTM721S
Camera PDR/CD1 Planning 19 September 2008
Project Management W. J. Foyt
Project Integration Management
Enterprise Content Management Owners Representative Contract Approval
CIS12-3 IT Project Management
Risk Management Process (Revised)
Linac Coherent Light Source (LCLS)
Thomas Fornek Project Manager July 15, 2009
Details supporting the increase
DOE Review of the LCLS Project
Linac Coherent Light Source (LCLS)
Conventional Facilities
XRN 4954 – MiR Drop 5 - Status Update
XRN 4927 – MiR Drop 4 - Status Update
LCLS Instrument MIE Project: Staffing, Schedule
Presentation transcript:

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate Risk/Contingency Staffing Project Controls Procurement CD-1 Documentation Issues Summary Project Scope Timeline Cost Estimate Risk/Contingency Staffing Project Controls Procurement CD-1 Documentation Issues Summary

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 2 Project Scope Work breakdown structure – WBS 1.1Project Management WBS 1.2X-ray Pump/Probe (XPP) WBS 1.3Coherent X-ray Imaging (CXI) WBS 1.4X-ray Correlation Spectroscopy (XCS) WBS 1.5Diagnostics WBS 1.6Controls & Data Systems WBS 2.0Other Project Costs Work breakdown structure – WBS 1.1Project Management WBS 1.2X-ray Pump/Probe (XPP) WBS 1.3Coherent X-ray Imaging (CXI) WBS 1.4X-ray Correlation Spectroscopy (XCS) WBS 1.5Diagnostics WBS 1.6Controls & Data Systems WBS 2.0Other Project Costs

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 3 Project Scope Scope definition – LUSI project consists of three x-ray instruments (XPP, CXI and XCS), associated diagnostics, controls & data systems and project management. Priority – CXI and XPP to be baselined (CD-2a) in Dec These instruments to be capable of producing science when LCLS operational. This will be LUSI’s CD-4a. 3 rd instrument (XCS) to be baselined at CD-2b. 3 instruments to be complete at CD-4b. Scope definition – LUSI project consists of three x-ray instruments (XPP, CXI and XCS), associated diagnostics, controls & data systems and project management. Priority – CXI and XPP to be baselined (CD-2a) in Dec These instruments to be capable of producing science when LCLS operational. This will be LUSI’s CD-4a. 3 rd instrument (XCS) to be baselined at CD-2b. 3 instruments to be complete at CD-4b.

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 4 Project Scope Key performance parameters – CD-4 will be staged: two partial instruments at CD-4a (Feb.’10), three complete instruments at CD-4b (Mar.’12) CD–4a: CXI operational with detector, diagnostics, and controls & data systems XPP operational with shared laser system, detector (1 st article), diagnostics and controls & data systems CD-4b: CXI operational with compressor, detector, particle injector and full diagnostics, and controls & data systems XPP operational with dedicated laser, detector, off-set monochromator and full diagnostics and controls & data systems XCS operational with detector, optics, sample environment and full diagnostics and controls & data systems Complete instrument parameter list in PPEP (5.1) Key performance parameters – CD-4 will be staged: two partial instruments at CD-4a (Feb.’10), three complete instruments at CD-4b (Mar.’12) CD–4a: CXI operational with detector, diagnostics, and controls & data systems XPP operational with shared laser system, detector (1 st article), diagnostics and controls & data systems CD-4b: CXI operational with compressor, detector, particle injector and full diagnostics, and controls & data systems XPP operational with dedicated laser, detector, off-set monochromator and full diagnostics and controls & data systems XCS operational with detector, optics, sample environment and full diagnostics and controls & data systems Complete instrument parameter list in PPEP (5.1)

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 5 Timeline Major events - Aug. 2005CD-0 Feb. 2006Detector MOU - BNL July 2007CD-1 Nov. 2007Split & Delay MOU - DESY Dec. 2007CD-2a Jan. 2008Particle Inj. MOU - LLNL July 2008CD-3a Nov. 2008Split & Delay Rec’d May 2009XPP Detector Rec’d Oct. 2009CD- 2b Nov. 2009Particle Inj. Rec’d Feb. 2010CD-4a Mar. 2010CD-3b Sept. 2011XCS Detector Rec’d Mar. 2012CD-4b

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 6 Cost Estimate

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 7 Cost Estimate Funding profile – Obligation profile –

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 8 Details - Cost Estimate LUSI COST ESTIMATE $60,000.0 DIRECT $30,586.0 PROJ MGT $3,264.7 XPP 7,914.6 CXI 6,714.6 XCS 5,826.6 DIAGNOSTICS 2,329.7 CTRLS & DATA SYS 4,535.8 INDIRECT 8,120.0 ESCALATION 3,218.8 CONTINGENCY 13,175.2 OPC 4,900.0 LUSI COST ESTIMATE $60,000.0 DIRECT $30,586.0 PROJ MGT $3,264.7 XPP 7,914.6 CXI 6,714.6 XCS 5,826.6 DIAGNOSTICS 2,329.7 CTRLS & DATA SYS 4,535.8 INDIRECT 8,120.0 ESCALATION 3,218.8 CONTINGENCY 13,175.2 OPC 4,900.0

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 9 Cost Estimate WBS 2.0 Other Project Costs = $4,900k Salary/Wage & Fringe 1,224k MS&T 670k Detector R&D 1,812k Indirect Costs 1,194k WBS 2.0 Other Project Costs = $4,900k Salary/Wage & Fringe 1,224k MS&T 670k Detector R&D 1,812k Indirect Costs 1,194k

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 10 Cost Estimate Methodology - Costs collected at levels 3, 4 or 5 of the WBS Labor by type in person weeks (44/yr) Calculated to FY’07$ using modified LCLS rates BNL detector estimates provided via MOU LLNL provided particle injector estimate; MOU in process Purchased materials & services entered by quantity & unit value Excluding MOUs, quotes/catalog items represent >50% of estimate Material burden factor (4.8%) Indirect (G&A) 20% calculated on labor & travel Contingency based on risk assessment at line item level Escalation (FY ’07 base year): Labor 4.0% / year Material 2.3% / year Methodology - Costs collected at levels 3, 4 or 5 of the WBS Labor by type in person weeks (44/yr) Calculated to FY’07$ using modified LCLS rates BNL detector estimates provided via MOU LLNL provided particle injector estimate; MOU in process Purchased materials & services entered by quantity & unit value Excluding MOUs, quotes/catalog items represent >50% of estimate Material burden factor (4.8%) Indirect (G&A) 20% calculated on labor & travel Contingency based on risk assessment at line item level Escalation (FY ’07 base year): Labor 4.0% / year Material 2.3% / year

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 11 Cost Estimate Cost estimate worksheet –

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 12 Risk / Contingency LUSI risk analysis identifies potential risks by: type - cost, schedule, technical consequence - marginal, significant, or critical likelihood - unlikely, likely, or very likely Intersection of these elements categorizes the potential risk to the project as either low, medium, or high Of 19 potential risks identified and documented in Risk Registry, 2 are categorized as High: Delay in FY funding (CR) Staffing difficulties Risk Registry will be evaluated monthly or when an event requires re-assessment As project becomes mature risk assessment will be more quantitative including estimates of potential costs, schedule impacts, cost of implementing mitigation strategy, and the residual risk. LUSI risk analysis identifies potential risks by: type - cost, schedule, technical consequence - marginal, significant, or critical likelihood - unlikely, likely, or very likely Intersection of these elements categorizes the potential risk to the project as either low, medium, or high Of 19 potential risks identified and documented in Risk Registry, 2 are categorized as High: Delay in FY funding (CR) Staffing difficulties Risk Registry will be evaluated monthly or when an event requires re-assessment As project becomes mature risk assessment will be more quantitative including estimates of potential costs, schedule impacts, cost of implementing mitigation strategy, and the residual risk.

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 13 Risk / Contingency Risk Matrix utilized in estimate preparation–

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 14 Risk / Contingency Application of Risk Matrix & contingency development –

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 15 Risk / Contingency Contingency – is developed utilizing a risk analysis at the lowest level of the WBS. An algorithm sums the technical, cost and schedule risk multiplied by the weight of the occurrence.

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 16 Risk / Contingency Project contingency –

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 17 Staffing

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 18 Project Controls LUSI utilizes existing LCLS EVMS, policies, procedures and project controls staff On-site EVMS training for Project staff planned 1 st two instruments to be baselined in Dec.’07 Earned Value (EV) reporting begins in FY 08. BNL (Detectors) and LLNL (Injector) will report EV against approved baseline schedules LUSI utilizes existing LCLS EVMS, policies, procedures and project controls staff On-site EVMS training for Project staff planned 1 st two instruments to be baselined in Dec.’07 Earned Value (EV) reporting begins in FY 08. BNL (Detectors) and LLNL (Injector) will report EV against approved baseline schedules

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 19 Project Controls Managing the Baseline – Prior to presenting a Baseline Change Request (BCR) to the Baseline Change Control Board (BCCB), the request will be reviewed by LUSI management. This review will include: Background leading to the request Extent of the problem Proposed solution Other solutions considered Stakeholders review (System Managers, QA, ES&H, RM Coordinator) Impact of the BCR Will there be a technical impact What resources are affected Will this require a draw on contingency What milestones, if any, are impacted Integrated Schedule Analysis Impact of not approving this BCR Affected drawings, parts or requirements LUSI BCR process detailed in PPEP (6.0) Managing the Baseline – Prior to presenting a Baseline Change Request (BCR) to the Baseline Change Control Board (BCCB), the request will be reviewed by LUSI management. This review will include: Background leading to the request Extent of the problem Proposed solution Other solutions considered Stakeholders review (System Managers, QA, ES&H, RM Coordinator) Impact of the BCR Will there be a technical impact What resources are affected Will this require a draw on contingency What milestones, if any, are impacted Integrated Schedule Analysis Impact of not approving this BCR Affected drawings, parts or requirements LUSI BCR process detailed in PPEP (6.0)

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 20 Procurement LUSI is utilizing LCLS procurement cell Advanced Procurement Plans (APP) being developed for all procurements on the critical path or with an order value >25k$ APP provides rolling 6 month window of planned procurement activity LUSI administration will monitor all phases of procurement LUSI is utilizing LCLS procurement cell Advanced Procurement Plans (APP) being developed for all procurements on the critical path or with an order value >25k$ APP provides rolling 6 month window of planned procurement activity LUSI administration will monitor all phases of procurement

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 21 CD -1 Documentation Documentation required for CD-1 approval – (documentation prepared for Jan. review updated to reflect action item) Documentation required for CD-1 approval – (documentation prepared for Jan. review updated to reflect action item) Conceptual Design Reportpublished July 2007 Design Review Reportissued July 2007 Acquisition Strategydraft released June 2007 Prel. Project Execution Plandraft released June 2007 Risk Management Plan/Assessmentissued June 2007 Prel. Security Vulnerability Assessmentissued Dec Prel. Hazard Analysis Reportissued July 2007 Quality Assurance Program – LUSI Quality Implementing Procedure issued June 2007 Value Management Planissued May 2007

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 22 Issues A Continuing Resolution (CR) in FY ‘08 would impact schedule. With minimal carry forward and a projected burn rate of ~460k$/mo, LUSI could manage the 1 st qtr of FY ’08 by withholding the balance of FY ’07 and delaying FY ’08 detector funding. Maintaining the detector schedule through 1 st qtr would require an additional 650k$ in FY 07. Potential CRs in the out years should be manageable without significant impact to the project schedule due to the funding profile. A Continuing Resolution (CR) in FY ‘08 would impact schedule. With minimal carry forward and a projected burn rate of ~460k$/mo, LUSI could manage the 1 st qtr of FY ’08 by withholding the balance of FY ’07 and delaying FY ’08 detector funding. Maintaining the detector schedule through 1 st qtr would require an additional 650k$ in FY 07. Potential CRs in the out years should be manageable without significant impact to the project schedule due to the funding profile.

W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 23 Summary Input from internal and external reviews have proven invaluable. Action item from Jan review was resolved on schedule and plan is being worked to meet or exceed requirement. All recommendations from Jan review have been responded to. LUSI staff has sharpened its plan and is prepared to deliver world class instruments on time and within budget. Input from internal and external reviews have proven invaluable. Action item from Jan review was resolved on schedule and plan is being worked to meet or exceed requirement. All recommendations from Jan review have been responded to. LUSI staff has sharpened its plan and is prepared to deliver world class instruments on time and within budget.