Presentation is loading. Please wait.

Presentation is loading. Please wait.

Thomas Fornek Project Manager July 15, 2009

Similar presentations


Presentation on theme: "Thomas Fornek Project Manager July 15, 2009"— Presentation transcript:

1 Thomas Fornek Project Manager July 15, 2009
LUSI PROJECT OVERVIEW Thomas Fornek Project Manager July 15, 2009

2 Provided Material Items Location
Items Project Management Documents Risk Registry, Schedule, Detailed Cost Estimate, March-May Monthly Reports Procurement Documents Current APP Status Log Responses to Recommendations from the April, 2009 status review Design Status Final Instrument Design Review (FIDR) Reports for CXI and XCS Links to CXI and XCS FIDR documentation Link to April review documentation

3 OUTLINE Concentrates on Changes Since April Baseline Project Status
Technical Scope Schedule Cost Project Status Resources and Risks Staffing Project Risks Contingencies ES&H

4 LUSI Baseline

5 LUSI WBS Organization Work Breakdown Structure defines project scope
TITLE 1.1 Project Management 1.2 X-ray Pump Probe Instrument (XPP) 1.3 Coherent X-ray Imaging Instrument (CXI) 1.4 X-ray Correlation Spectroscopy Instrument (XCS) 1.5 Diagnostics and Common Optics (DCO) 1.6 Controls and Data Acquisition (CDA) Instrument scope baseline buy-in from Team Leaders Re-affirmed at Final Instrument Design Reviews Baseline scope provides capable instruments Future scope to enhance science capability identified

6 Project Description (1)
CXI WBS 1.3 X-ray transport tunnel (200 m) XCS WBS 1.4 XPP WBS 1.2 LCLS SXR XCS Offset Monochromator WBS 1.5 MEC LCLS AMO

7 Project Description (2)
LUSI is providing instruments for 3 of the 6 LCLS hutches Near Experimental Hall X-ray Transport Far Experimental Hall 1 3 2 4 5 6 XCSMono AMO SXR XPP XCS CXI H6 Part of LCLS Installation Part of LCLS XPP Mono Added CXI Lenses Added FES ARRA Funds Beam Transport LCLS Offset Monochromator Exp. Chamber Detector LUSI H6

8 Schedule Advancement Milestone @ CD-2 Baseline CD-3 April 2010
Oct 2009 XPP CD-4 Instrument Install Complete April 2012 May 2011 CXI CD-4 Instrument Install Complete June 2012 Aug 2011 XCS Early Science (New) NA XCS Final Install Complete Jan 2012 Final Instrument Readiness Review (Ready for CD-4) March 2012 CD-4 Aug 2012 CD-0 - Mission Need - Approved Aug 2005 CD-1 - Alternative Selection and Cost Range – Approved September, 2007 CD-2 - Approve Performance Baseline – Approved October, 2008

9 RA Funding Effects ARRA Funding
Advances the start of XCS science by 9 months Advances the completion of CXI instrument by 10 months Advances the completion of XPP instrument by 13 months

10 LUSI Integrated Project Team
No change since April DOE-HQ H. Kung, Acquisition Executive T. Brown, Program Manager DOE-SSO H. Joma DOE Federal Project Director DOE-SSO Support Instrument Team Leaders Lab-wide Support ES&H, QA, Finance, EVMS, Procurement, HR SLAC T. Fornek LUSI Project Manager Deputy – R.M. Boyce Technical Configuration Control Committee (Scope Decisions) Installation Manager B. Poling WBS 1.2 XPP IIT D. Fritz (Instr. Scientist) J. Langton ( Lead Eng) N. van Bakel (Detectors) WBS 1.3 CXI IIT S. Boutet (Instr. Scientist) P. Montanez ( Lead Eng) N. van Bakel (Detectors) WBS 1.4 XCS IIT A. Robert (Instr. Scientist) E. Bong (Lead Eng) N. van Bakel (Detectors) WBS 1.5 Diagnostics & Common Optics Y. Feng (Lead Scientist) E. Ortiz (Lead Eng ) WBS 1.6 Data Acquisition & Controls G. Haller (Lead) P. Anthony (Alternate)

11 LUSI Cost Baseline Baseline Oct 2008 May 2009 (Incl RA)
Base Cost (BAC) $42.10 M $43.50 M Contingency $13.00 M $11.60 M TEC $55.10 M OPC $4.90 M TPC $60.00 M Reflects adding XPP LOM and CXI lenses

12 LUSI Funding Profile (AYM$) With RA Funds
RA Modified Profile Moves FY10-FY12 Funds into FY09 LUSI Funding Profile (AYM$) With RA Funds Prior Yrs FY07 FY08 FY09 FY10 FY11 FY12 Total Pre RA 0.50 6.00 15.00 13.50 5.10 55.10 MIE (Non-RA) 21.50 MIE (RA) 33.60 OPC 3.40 1.50 4.90 2.00 48.60 60.00 All remaining LUSI funding has been received

13 BA Plan & Obligation Profile
ARRA BA Profile 08 Q1 Q2 Q3 Q4 09 10 11 12 .5M 6.5M 8.0M 9.5M 55.1M

14 LUSI Project Status

15 Project Completion

16 Project Design Completion
ALL LUSI DESIGN IS CD-3 READY CXI Final Instrument Design Review Complete – CD-3 Ready XCS Final Instrument Design Review Complete – CD-3 Ready Diagnostics and Common Optics (DCO) Harmonic Rejection Mirror Preliminary Design Review Complete – DCO CD-3 Ready Controls and Data Acquisition (CDA) Preliminary Design Reviews for CXI and XCS Controls Complete – CDA CD-3 Ready Prepared responses to April Independent Project Review Included in back-up information Scope inclusions to enhance science: Added XPP Large Offset Monochromator Added focusing lenses to CXI instrument

17 Project Performance TEC - $55.1M (CPI = 1.05, SPI = 0.98)
Work Scheduled (BCWS) $9,129K Work Performed (BCWP) $8,902K Actual Costs (cum) (ACWP) $8,499K Obligations (cum) $3,392K LUSI EAC for TEC $43,197K Remaining Work (ETC) $ 34,992K Remaining Management Reserve $ 11,609K % MR (Cost to Go) 33% % MR (Uncom to Go) 37% Adding scope to optimize science. Reserve adequate contingency to address remaining risks to project. LUSI EAC for OPC $4,900K Remaining Work (ETC) $ K Remaining Mgmt Reserve $ K

18

19 LUSI Project Summary Schedule
Early Milestone Completion Dates Reflect RA Facilitated Schedule Advancement

20 LUSI Resources & Risks

21 Staffing (FTE) LUSI staffing is appropriate for the project needs
No new jobs for RA Effort is moved forward and rolls off earlier

22 Risk Management Fifty-five risks were identified at CD-2
One risk added since Eighteen risks have been retired Thirty-eight risks remain All remaining risks have mitigation plans Major risks remaining Meeting RA requirements Foreign procurements – Dollar fluctuation Component delivery and performance

23 Cost and Schedule Contingency
Available Management Reserve is $11.61M Bottoms-up” contingency estimate is $9.83M on $34.7M ETC Management Reserve is managed at the project level LUSI performs monthly Management Reserve update and annual comprehensive ETC Float 60 working days to Final Instrument Readiness Review Approved – March 30, 2012 160 working days to CD-4 Critical Path (XCS is most critical to CD-4) XPP Diffractometer (Contract issued) CXI 1 micron K-B mirror system (Contract issued) XCS Diffractometer (Critical for “Early Science”) Monochromator (Critical for Final Instrument Readiness Review) XCS Final Detector (Critical for Final Instrument Readiness Review)

24 Management Reserve Assessment
Assessment is a bottoms-up, risk-based estimate of “potential need” by each CAM Total Management Reserve available is $11,610K 24

25 Possible Future Scope Enhancements
Priority list is a living document with input from stakeholders and each item requires approval by the TCCC prior to starting a Baseline Change Request Balance science enhancements With risks and available MR

26 LUSI ES&H

27 Integrated Safety Management Process
SLAC Integrated Safety and Environmental Management SLAC ES&H Manual Safety Oversight Committee Review Process Work Planning and Control Program Scope work, including hazard Id & controls Authorization and Release of work Lessons Learned SLAC process driven by Operating Experience Program (210.2) SNS Lessons Learned from Instrument Beamline Construction (413.3A) LCLS ES&H management practices LCLS Requirement, Specification and Interface Documents Physics Requirements doc’s, Engineering Specification doc’s, Prelim. & Final Design Reviews The above meets or exceeds DOE O / Safety Management System Hazard Analysis Report Required for CD-3 to be updated and approved at field level - Done Construction ES&H Plan Required for CD-3 to be prepared and approved at field level – Done The above meets or exceeds DOE O 413.3A / Program and Project Management

28 ES&H ISM Integrated into process
SLAC and LCLS ES&H Subject Matter Experts engaged Safety integrated in design reviews Hazard analysis performed and updated as designs progress Instrument readiness process will follow precedent set by the LCLS AMO instrument Project safety experience to date Through June 2009, 84,400 Hours worked with no DART or recordable incidents

29 Lessons Learned LCLS implementing a systematic process to capture Lessons Learned from the LCLS Project and LUSI Database (SharePoint) used to capture and retrieve all Lesson Learned Categories established ES&H CF Design & Construction Management & Communications Procurement Commissioning & Transition to Operations Technical System Design, Fabrication, Installation & Integration Identify Best Practices & Opportunities for Improvement Living document with further revisions expected

30 In Conclusion Funding Schedule Advancement Scope Management
LUSI has all expected funding Schedule Advancement RA schedule advance is resonable Three instruments to LCLS operations by end of FY11 Scope Management Project scope is reasonable and managed by change control Resources and Risks Resource planning is reasonable RA funds reduce funding related risks Ready for CD-3

31 Acronyms AMO – Atomic, Molecular and Optical Science Instrument
ARRA (or just RA) – American Recovery and Re-investment Act BAC - Budget at Completion BCR - Baseline Change Request ESD - Engineering Specifications Document FDR - Final Design Review FEH - Far Experimental Hall FIDR – Final Instrument Design Review H1…H6 – Hutches 1 through 6 ICD - Interface Control Document MEC – Materials under Extreme Conditions Instrument NEH – Near Experimental Hall PDR - Preliminary Design Review PRD - Physics Requirements Document SOW - Statement of Work SXR – Soft X-ray Instrument XRT - X-ray Transport Tunnel


Download ppt "Thomas Fornek Project Manager July 15, 2009"

Similar presentations


Ads by Google