Agenda August 5, 2014 1.Introduction – Natalie Robottom 2.Background and History – Rob Delaune 3.Present Conceptual Engineering Design Proposed Tasks -

Slides:



Advertisements
Similar presentations
Water & Wastewater Construction Back Forward Wastewater Treatment Plant and Pump Station Improvements, Haverhill, MA.
Advertisements

St. Croix River Crossing Project Public Information Meeting
This presentation is an abbreviated version of the original PowerPoint presentation of June 23, This version was presented at the Commissioners’
Lunenburg CWMP Phase II – Management Techniques and Alternatives Identification and Screening Lunenburg Comprehensive Wastewater Management Plan Workshop.
Stave Lake Water Supply & Treatment Project. Existing Water Supply System Norrish Creek Cannell Lake 19 Groundwater Wells.
Mike Hightower, Sandia National Laboratories Tom Jennings, Bureau of Reclamation New Mexico Water Research Symposium August 13, 2002 Feasibility Study.
GIBSON ISLAND WATER SYSTEM CAPITAL IMPROVEMENT PROJECT Public Information Meeting June 5, 2012.
Loudoun Water’s Potomac Water Supply Program RWI/PRWPS- Request for Qualifications Pre-submittal Conference– July 9, 2013.
Town Hall Meeting 12 March 2008 Carmichael Area Aerojet Groundwater Remediation Progress Update 12 March 2008.
Southwark’s New District Heating Network.
Northeast Corridor Greenway Acquisition – Mitigation Feasibility Study Results City Council Workshop June 24, 2014.
ISLA POPA II, PANAMA WATER SUPPLY PROJECT July 10 th 2014.
Lecture(1) Instructor : Dr. Abdelmajid Nassar Civil Engineering Dept. Master Program Civil Engineering Dept. Master Program
Cornerstone Engineering Group The Foundation for Your Civil Engineering Needs Camanche Reservoir Water Treatment Plant Project Cecilia Zamora Evangelina.
Cornerstone Engineering Group The Foundation for Your Civil Engineering Needs Camanche Reservoir Water Treatment Plant Project Cecilia Zamora Evangelina.
© 2003 TranSystems Corporation Advisory Committee Meeting January 19, 2010.
Jordan Lake Partnership Western Intake Feasibility Study Jordan Lake Partnership Western Intake Feasibility Study 1.
Mission-Critical Work in the Water/Wastewater Industry.
Chicago Department of Water Management Thomas H. Powers, P.E. Commissioner Leadership Summit June 2, 2015.
Water System Planning Study
Rural Drinking Water Treatment System. INTRODUCTION Water demand Identification of water source Drinking water Quality Parameters Required treatment system.
WASTEWATER FACILITIES PLANNING Public Information Session August 29, 2013 Town of Clinton, CT Water Pollution Control Commission.
Filename: C-CR-10-02Rev00Page 1 of 3Record no.: C-CR-10-02Rev00 Appendix 2(a): Water Treatment Equipment and Sampling Points Guideline for Water Treatment.
St. Lucie and Indian River Counties Water Resource Study Mark Elsner, P.E., Director Water Supply Development Division Mark Elsner, P.E., Director Water.
© 2001 Utility Management Consulting, Inc. All Rights Reserved Distributed Resources Interconnection Policies: A Report to EEI Members Presentation of.
Low-flow Intake Technical Analysis Zaffar Eusuff Ph: (916) Bay-Delta Office California Department of Water Resources.
Lyndonville Electric Department Feasibility Analysis Review December 2,
Washington’s Water Use Efficiency Rule May Require Increased Coordination for Many Utilities Dan Sander, P.E. Senior Engineer.
Evaluation of Non-Traditional Sources of Cooling Water Sujoy Roy and Michael DiFilippo Tetra Tech Inc, Lafayette, CA and MND Consulting, Berkeley, CA EPRI.
Short and Long Range Water Supply Planning and Aquifer Performance Test (APT)
Update On Mississippi River Delta Management Plan Presented at August 20, 2009, Meeting of Governor’s Advisory Commission on Coastal Protection, Restoration.
Icfi.com © 2006 ICF International. All rights reserved. Wyoming Collector and Transmission System Project – Status Report Presented to: Wyoming Infrastructure.
Power Plant Construction and QA/QC Section 2.6– Water Treatment
June 2008 Windsor-Essex Electrical Service Needs and Solutions.
Proposed Revisions to the Long-Term Plan Long-Term Plan Communications Meeting August 25, 2004 Gary Goforth Chief Consulting Engineer South Florida Water.
U.S. Army Corps of Engineers (USACE) AEC Utility Monitoring And Control Systems and Electronic Security Systems (UMCS)(ESS) Prepared for: Energy Huntsville.
1 CONCISE UPDATE ON ACID MINE DRAINAGE IN THE WITWATERSRAND April 2012 UPDATE BY Mr. MARIUS KEET.
Webster Water System Board of Selectmen Public Hearing on Water Quality October 13, 2015 Doran Crouse, Webster Water Department Scott Charpentier, P.E.,
Richland Creek Water Supply Program Contract for WTP and Pump Stations CMAR Services and Program Update Paulding County, Georgia Board of Commission Work.
Update on RCR Permitting
Coquina Coast Seawater Desalination Project TERMS Base Contract TasksBase Contract Tasks – Must be completed – Negotiated and included in the Base Allowance.
Potential Consolidation of WMWD’s Murrieta Division into EMWD April 15, 2015 Paul D. Jones II, P.E. General Manager, Eastern Municipal Water District
December 10, 2009 TOWN OF PALM BEACH WATER COMMITTEE Discussion of Water Plant Options.
Village of Naples and Hazlitt 1852 Vineyards Sewer Feasibility Study.
Dr. Nyamajeje C. Weggoro Director, Productive and Social Sectors EAC Secretariat THE DAR ES SALAAM-TANGA- MOMBASA NATURAL GAS PIPELINE AND EAST AFRICAN.
Water Supply Planning Workshop February 27, 2008 City of Hallandale Beach Commission Mayor Joy Cooper Vice Mayor Bill Julian Commissioner Keith London.
Richland Creek Water Supply Program Update and Design-Build Contract for 48” Raw Water Pipeline Paulding County, Georgia Board of Commissioners Workshop.
1 | emwd.org MV 2060 Pressure Zone Potable Water Storage Tank and Transmission Pipeline Joe Mouawad April 6, 2016.
1 Highland Water District CAPITAL IMPROVEMENT PLAN.
City Council March 4, Introduction The UCRA recommends the development of a storm water storage basin just to the east of FM 1223, south of Avenue.
Overview of Desalination Trends and Jaffna Project
Grey Owl Municipal Water feasibility study
Fort Stanwix National Monument Energy Audit Contract
Welcome to the Libertyville Stormwater Master Plan Open House
Kings Bluff Raw Water System Parallel Raw Water Main Project
Chromium 6 Regulation Corrective Action Plan October 6, 2015
DISTRICT COOLING A promising and sustainable option for HFC phase-down
Status of the Planning Working Group’s (PWG) Efforts
Perris Water Filtration Plant Membrane Upgrade – Phase I
CITY OF MARSHALL CHLORIDE ISSUES September 26, 2017
Modifications at Existing WTP: $450,000 Construct New WTP: $39,100,000
City of McCall Water Rate Study – Draft Rate Recommendations
روش‌های طراحی مهندسی.
CITY OF MARSHALL CHLORIDE ISSUES NOVEMBER 22, 2016
Brackish Water Desalination Project
Delta Water Supply Project
I-85 Corridor Light Rail Transit Feasibility Study
CP-TXT Water Supply Facilities Work Plan Amendment
Richland Creek Water Supply Program Program Update
MANILLA WATER SUPPLY UPGRADE
Presentation transcript:

Agenda August 5, Introduction – Natalie Robottom 2.Background and History – Rob Delaune 3.Present Conceptual Engineering Design Proposed Tasks - Rob Delaune 4.Discussion and Questions LaPlace Water Source Workshop

August 5, 2014

 Goal is to provide solution for Water Supply in LaPlace  Variables that have changed since study completed in 2006 on proposed water plant for east bank of St. John  Reverse osmosis membrane units installed at Woodland Drive  New filters installed at Lions Plant  New regulations from LDHH  Hurricane Isaac exposed vulnerabilities  Proposed Conceptual Engineering Design for LaPlace water source includes six tasks  Water Committee recommended the proposed tasks Introduction

 Task 1 – New Water Intake Pump Station on MS River in LaPlace  Task 2 – New Transmission Main from MS River to Reverse Osmosis Unit Site on Woodland Drive  Task 3 – Pre-treatment at Reverse Osmosis Unit Site on Woodland Drive  Task 4 – Modifications to the Lions Water Treatment Plant  Task 5 – New Distribution Pump Station and Transmission Main form Lions Plant to LaPlace  Task 6 – Operation and Maintenance Costs to Maintain Ruddock Well System vs. Cost to Decommission List of Tasks

 Task 1 – New Water Intake Pump Station on MS River in LaPlace  Identify, investigate and determine best location  Provide conceptual engineering design and cost estimate for new pump station Conceptual Engineering Proposed Tasks

 Task 2 – New Transmission Main from Mississippi River to Reverse Osmosis Unit on Woodland Drive  Determine route alternatives and provide conceptual engineering of alternatives  Perform comparison evaluation of most feasible route  Develop conceptual cost estimate for route alternatives Conceptual Engineering Proposed Tasks (Cont.)

 Task 3 – Pre-treatment at Reverse Osmosis Unit Site on Woodland Drive  Analyze alternative treatment options  Calculate required treatment capacity and pre-treatment options available  Provide conceptual engineering and costs for pre-treatment units Conceptual Engineering Proposed Tasks (Cont.)

 Task 4 – Modifications to the Lions Water Treatment Plant  Determine modifications required to meet LDHH regulations  Provide conceptual engineering and cost estimates for modifications to meet LDHH regulations Conceptual Engineering Proposed Tasks (Cont.)

 Task 5 – New Distribution Pump Station and Transmission Water Main from Lions Plant to LaPlace  Provide conceptual engineering of new distribution pump station  Provide conceptual engineering of transmission main alternatives and comparison evaluation of most feasible route  Develop conceptual cost estimate for pump station and transmission main Conceptual Engineering Proposed Tasks (Cont.)

 Task 6 – Operation and Maintenance Costs to Maintain Ruddock Well System vs. Cost to Decommission  Determine operation and maintenance costs over 20 year term to keep Ruddock well system in operation  Determine cost to decommission Ruddock well system Conceptual Engineering Proposed Tasks (Cont.)

 Conceptual Engineering Design Memorandum and Recommendations Summary  Present total costs of all elements in a summarized format  Provide recommendations on moving forward with design and construction  Provide Schedule to completion  Operation and maintenance comparison of elements  Reliability comparison of elements  Potential funding methods for recommended alternative LaPlace Water Source Conceptual Engineering Results