1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

K. Long, 18 April, 2015 Beam-line status — red sky at night?
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and Phase One Steps towards Phase Two Summary Andy Nichols, STFC, 24th April 2008

2 Technical Organisation New Management team has been in place for six months: –PM/Technical Co-ordinator – Andy Nichols –Hall Manger/Principal Contractor – Willie Spensley –Hall Foreman – Ash Jamdgni –ISIS liaison – Chris Rogers –MICE Operations Manager – rolling monthly post, currently Malcolm Ellis –And we have a stable group of well-motivated technicians With much valuable help from Richard Apsimon and Paul Flower But Richard & Paul have now retired: –Internal (RAL) vacancy for PM approved, but no candidates –Nominated MICE radiation safety person also required

3 Target & Upstream Beamline Target is now in ISIS, but there are still problems: –Agreed last year with ISIS to have on-line (in ISIS) and off-line (in R76) identical targets, with the off-line run in advance, but –Problems with actuator coils have prevented the off-line target from running. These problems are being understood with valuable input from DL –Two (+ One spare) targets are being made, complete mid-May –Currently, target running is limited to machine physics periods in ISIS because of above problems, but we are preparing a case to operate target during user runs –Found we need to dip an extra 5mm(??) into the beam – thought not difficult to arrange, by mechanical means only, work it out Monday –Good news is that the current target behaves itself very well Still to do: –Complete and test both targets –Target planning meeting with ISIS on Monday –Install both in ISIS and R76 –Integrate the target operation with the overall MICE controls

4 Target & Upstream Beamline Upstream is effectively complete: –Re-worked magnet stands installed –Vacuum chambers installed and leak-tested –Magnets aligned –New target vessel with correct beam window position –Problems with Q1,2,3 power supplies, now fixed and awaiting soak test, aim for short access if possible, or wait May shutdown

5 Muon Beamline PSI (Decay solenoid –But we go ahead with cold test on 21 st April 2008, expected to take 14 days –Currently a few leaks to fix, transfer line is at atmosphere – difficult to explain. –Some dismantling of cable trays needed to access unions etc – uncomfortable, but not impossible –24 hour cover needed over next two weeks – unskilled babysitting only, with phone access to experts – volunteers welcome! Still to do: –Complete ‘magnet – on’ lights –Complete cold test and test quench protection –Minor shielding additions –Compile safety documentation and implement safety procedure

6 Muon Beamline D2, Q4,5,6 installation is essentially complete –Minor work on water connections needed (May shutdown), otherwise ready to go. –cKOV chambers – were successfully installed during March and now operational –TOF0 – not installed yet – problems at Milan with PM tubes, being understood, likely shipment to RAL is now early to mid- May – this is a cause for concern.

7 Infrastructure and Phase One Six months ago the Infrastructure project was not well understood: –New WP1 manager – has defined sub-workpackages: Magnetic shield walls (North & South) False floor design & M/F Remove existing concrete floor Excavate part of ISIS mound (around LH2 vents) Electrical & mechanical services Local control room Ventilation (air conditioning) DSA roof and fencing Rolling platforms –Good progress being made on all fronts –Due to the unforseen complexity, we missed original March ’08 finish date – has been agreed with OsC to finish July –Staff over-run costs and magnetic shield wall costs largely account for overspend

8 Infrastructure & Phase One Magnetic shield wall: –Separated into support structure and shield plates –Support structures: 30% off site fabrication complete, plan to start on-site early May –Shield plates – successful OJEU tender in February – contract with Charles Day steels, Sheffield – delivery in phased 35 tonne loads, first one early-mid May No real problems!

9 Infrastructure & Phase One False floor design: –The base for phase Two: –Metallic framework to raise existing lowered floor Provide level support and mounting for cooling channel elements Resist quench and gravitational loads Interface with the (as yet un-designed) RF infrastructure Status: –Baseline design is done –Magnetic modelling is in process (critical input to above and now a cause for concern) –Aim for design complete early May.

10 Infrastructure & Phase One Concrete floor removal: –It’s finished ahead of schedule, but: –Structural weakness discovered in surrounding concrete, on which shield wall is supported –Completely unforseen, core samples are currently with structural consultant, most pessimistc outcome is: –Excavate the area, re-pour concrete and add re-inforcement –Aim to do in parallel with other work, minimal delay, but unknown cost implication –Latest news: it’s OK! But written confirmation from structural engineer awaited

11 Infrastructure & Phase One ISIS Mound excavation: –Part of the mound behind MICE hall has to be excavated to accommodate the LH2 vent system, another thing we ignored! –Problems: The earth is unstable, cannot dig without re-inforcing No access for equipment Craning material/equipment over ISIS control room is precluded Hand digging likely => good weather We are interfering with ISIS shielding – will be subject to radiation survey –Difficult, but the right people are working on it; likely solution is a pre-cast sectional concrete barrier – sanction from ISIS RPA on this basis has been obtained –But we are unlikely to finish before August – problem as we overrun revised phase one finish date

12 Infrastructure & Phase One Electrical & mechanical services: –Fairly uneventful, work is now reasonably understood –Supervision of contractors suffered due to sick leave and overload in Building Projects Group –Steve Griffiths of DL has stepped in to help – presence by his group at RAL three days a week –Which is good, on target to complete the phase one work on time. Local control room is now habitable and in use Then Now

13 Infrastructure & Phase One Ventilation & Air conditioning –400KW (eventually) of heat needs to be removed –Five A/C units have been delivered –Some pre-wiring has been done –Final wiring and installation cannot take place till shield walls and mezzanines are installed – off critical path DSA roof and fencing: –Part of safety system, fencing around and one-way escape route from DSA, also partial roof –Design done, drawings signed off – meeting to finalise works order 21 st April – part of May shutdown – Drawings now signed off

14 Infrastructure & Phase One Rolling platforms: –Modular platforms to support beamline elements and allow withdrawal –Move on air pads –Design done –Successful tender exercise, contract placed with ESE in Poole –First platforms (for steps 1,2,3) delivered in May –Air pads, controls and ancillary stuff also on order –Not critical path

15 Steps towards phase two Revised step one has been agreed by MICE EB –It’s just the KL, TOF1, fixed and moving beamstops Can take place on existing raised floor Depends on arrival of KL & TOFs in early May Must finalise sliding beamstop baseline Very soon – planned for TB meeting, but We have a problem…………… Careful planning needed to allow concurrent Work on shield wall supports – we have the space and L.Tortora has agreed if fence and stay/clear are provided

16 Steps towards Phase Two …….. the sliding beamstop requirements are now complex After consulting with RPA – completion before June is impossible Due to delivery of scissor lift and necessarily complicated shielding design We will have to make an interim version: Beam aperture tube and steel shot in DSA Then manually craned concrete and steel blocks (which we have)

17 Steps towards Phase Two Permission granted for focus coils order, (two plus option for one) –Kick-off meeting with Tesla scheduled for 18 th April –Detailed schedule, design and manufacturing plan should emerge then –Also mechanical/electrical/cryogenic interfaces –Latest news: contract has been signed UK Phase Two WBS, infrastructure plan, bottom-up staff & capital estimates are complete –Phase Two WP managers have been circulated for their plans – much useful input to the above

18 Summary Target has enabled MICE to take data, but there are still some problems Upstream quads and dipole are essentially complete Mechanical integration of solenoid went very smoothly, still some cryogenic problems, but nothing we don’t understand Downstream quads essentially complete The infrastructure project is now well understood and good progress being made Magnetic modelling information for false floor is urgently required New Project Management structure is established Placement of AFC contract a major positive step Content of Phase Two WBS must not be under-estimated Downstream beamline elements are generally progressing well Delivery of TOFs to RAL is causing concern