2014-11-20 NA62 vacuum controls, F. Mateo TE-VSC-ICM Vacuum controls of the NA62 experiment Fernando Mateo TE-VSC-ICM 1 of 14.

Slides:



Advertisements
Similar presentations
André Augustinus 16 June 2003 DCS Workshop Safety.
Advertisements

The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Overview Interfaces Planning.  One PC to control 2 cavities in one cryo-module  Standard PLC and hardware components  Expected PLC cycle time 2ms.
PLC DEVELOPMENTS FOR NEW VACUUM DEVICES IN THE LHC AND NA62
FUNDAÇÃO PARA A CIÊNCIA E TECNOLOGIA FCT Trainee Program Follow Up João Rodrigo Alvelos Ferreira | Started March 2013 October 2014 TE-VSC-ICM.
Harold G. Kirk Brookhaven National Laboratory MERIT Installation Issues CERN Meeting June 20, 2006.
Vacuum control commissioning and alarms system Abel Gutierrez CERN TE-VSC NA62 Vacuum control commissioning and alarms system 1 Jun 11, 2015.
Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
Isabelle Laugier, AT/VAC/ICM Section February 7 th 2008.
CONSOLIDATION OF THE CONTROL SYSTEM OF THE SUBU CHEMICAL POLISHING MACHINE TE-VSC-ICM Automation Forum João Rodrigo Alvelos Ferreira 20th November 2014.
The Detector Safety System for LHC Experiments Stefan Lüders ― CERN EP/SFT & IT/CO CHEP03 ― UC San Diego ― March 27 th, 2003.
IBL CO 2 cooling control system development status Lukasz Zwalinski – PH/DT/DI Maciej Ostrega – PH/DT/DI Florian Corbaz – EN/CV/DC.
ISOLDE Vacuum Controls (CERN-GSI WS), S. Blanchard TE-VSC-ICM UNICOS Vacuum Objects Specifications Review Sebastien Blanchard TE/VSC Interlocks,
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
Vacuum - CONTROL SYSTEM 29 June Agenda MSRC design, first ideas and plans – Antonio quiet cooling fans test – Irene some scada SW review - Martin.
LHC ARC Commissioning report during LS1 Agenda: VRGPE documentation (former VRJGE) Active Penning modification By-Pass Valves modification LHC ARC commissioning.
Vacuum Controls Status MACS week December 2010 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
Workshop on the Use of Ethernet as a Fieldbus CERN, 28 September 2001 Use of Ethernet in the control systems of the cooling and ventilation infrastructure.
TS Workshop, Archamps, May 24 – May 26, 2005 The LHC Access System Status report – May 2005 P. Ninin & the Access project team TS/CSE.
LHC Cryogenics Control: INTEGRATION OF THE INDUSTRIAL CONTROLS (UNICOS) AND FRONT-END SOFTWARE ARCHITECTURE (FESA) APPLICATIONS Enrique BLANCO Controls.
Cooling of NA62 vacuum system November 11 th, 2014 E. Harrouch, EN-MEF, on behalf of the NA62 Vacuum Team.
AdV Vacuum system changes, 23Feb2011 Central area vacuum equipment SVC 2 (mini) towers 1 new HV tower (Inj) DT,IB from HV->UHV towers (with additional.
Chiller control system Lukasz Zwalinski – PH/DT.
Chiller control system Specification meeting Lukasz Zwalinski – PH/DT.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
Status of Vacuum Control System MACS week June 2011 PP a-JWA-VacControlStatus.ppt Joachim Wallner 1.
OLAV III Experience with the LHC Insulation Vacuum System S. Blanchard, P. Cruikshank, B. Jenninger, N. Kos, W. Maan, L. Mourier, N. Provot, J. Wallner.
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
GIF++ Control System (GCS) Gilles MAIRE PH-DT-DI1.
Managed by UT-Battelle for the Department of Energy SCL Vacuum Control System Upgrade Derrick Williams
ALICE TPC Gas Control System (toward the first fully implemented LHC gas system) S. Haider EP-TA1-GS.
Vacuum Controls framework for the LHC and its injectors Sebastien Blanchard CERN TE-VSC Introduction to the Vacuum Controls framework for the LHC and its.
Isabelle Laugier, AT/VAC/ICM Section May 6 th 2008 LHC Vacuum Control system.
TE-CRG Interfaces Fair S-FRS magnets - CERN cryogenics Control interface CERN-GSI for B.180 cryogenics Control interface CERN-GSI for B.180 cryogenics.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
Status of the NA62 network R. Fantechi 23/5/2012.
A.Henriques (JCOV meeting 31/5/2001) ATLAS Calorimeter cooling project Goal: u Definition of a common frame work for the cooling of the ATLAS calorimeter.
Krzysztof Radwan, PJAS, TE/VSC/ICM Interlocks, Controls and Monitoring Section HIE-ISOLDE Vacuum Controls INSTALLATION.
ISOLDE Vacuum Controls (CERN-GSI WS), S. Blanchard TE-VSC-ICM UNICOS implementation in ISOLDE Sebastien Blanchard TE/VSC Interlocks, Controls.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
External Data and DIP Oliver Holme 18 th January 2008.
Claudia Dias Vacuum, Surfaces & Coatings Group Technology Department Claudia Dias CERN, Technology Department Vacuum, Surfaces and Coatings Group 2 |
Report on Controls, TCC meeting 23 th June 2005 – Cl.Dehavay & Co - AB/CO/HT 1 Claude DEHAVAY - CERN/AB/CO/HT Installation Readiness Report - Controls.
IT-3963/EN Bidder’s conference Design, supply, installation and commissioning of the cooling system for the NA62 Gigatracker Tuesday 10 December 2013 Building.
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
1 Cryogenics Instrumentation & Controls Commissioning for the LHC AB/CO viewpoint Enrique Blanco AB/CO IS.
Vacuum Controls framework for the LHC and its injectors Sebastien Blanchard CERN TE-VSC Integration of controllers in SCADA using OPC Server Goal: Improve.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
S A Griffiths CM42 June 2015 Electrical & Control.
01/09/ KTAG 5/8 sectors equipped DCS system in pogress DAQ commissioning in progress Test pressure scan this week (t.b.c) 01/09/20142.
Miguel Angel Quero Corrales
Control activities in LS1
SCADA & Monitoring Developments for Vacuum
FCT and CERN Portuguese Trainee Programme Report
Francois and Lau EATM 17 July 2012
Installation of an Instrument on a CERN machine
LINAC4 Vacuum Control System Review
Recent developments in the Vacuum Control Software
352MHz Klystron Control for the 3MeV Linac test stand
SPS CC: Final plan for interlocking of crab cavities in SPS
MAUVE CO2 cooling review
XFEL Vacuum System Commissioning
Magnet Safety System for NA61/Shine
Control systems plans & activities for HL-LHC during LS2
SC1R Cold Box PDR Controls
Power cut 18kV cable for EMD404/E9 is heating
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Vacuum Control System for Monolith Vacuum
Presentation transcript:

NA62 vacuum controls, F. Mateo TE-VSC-ICM Vacuum controls of the NA62 experiment Fernando Mateo TE-VSC-ICM 1 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM  Introduction  Experimental layout  Vacuum equipment layout  Controls architecture  Control crates  Racks layout  Interlocks  Software  PVSS SCADA application  Commissioning 2 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM NA62 is a fixed target experiment in the SPS North Area to study very rare decays of Kaons. It is a follow-up experiment of NA48 and it reuses a large amount of its equipment. LOCATION: SPS North Area (Bld. 911 – 918. Site of Prévessin) Introduction 3 of 14

Experimental layout Vacuum sectors: 1.T10  TAX 2.TAX  CEDAR 3.CEDAR  Fast Gate Valve (99m) 4.Fast Gate Valve  Gate Valve (105m) 5.Decay volume + RICH (105m-240m) 6.LKr-Monotube (240m-243m) 7.Gate Valve  Dump & SAC NA62 vacuum controls, F. Mateo TE-VSC-ICM 4 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM Vacuum equipment layout > 200 intruments (gauges, valves, pumps) Vacuum layout : EDMS Instruments list: EDMS Passive gauges, no Profibus Active gauges, no Profibus Active gauges, Profibus 5 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM PLC master (VRLMS) Remote I/O (VRLRG) OLM (VRJCP006) Optical network Primary pump controller (VRPPH) Profibus I / A / T VGM / VGF Cryogenic group (VPGC) Turbomolecular group (VPGT) VGMB Remote I/O (VRLRG) VGF Roughing pumps (VPR) VGPAVGRA VV Fast valve (VVQ) Turbo group controller (VRPGMF) VRGPT300 Fast valve controller (VRVRC) DA valve controller (VAT_VP3) Special DA valve (VVX) Primary group (VPGR) Controls architecture 6 of 14 Cryo group controller (VRPYA) … Profibus gateway (VRJCP007)

NA62 vacuum controls, F. Mateo TE-VSC-ICM Control crates Commercial crates Custom-made crates 7 of 14

of 14 NA62 vacuum controls, F. Mateo TE-VSC-ICM Racks layout VAC-01 (176m) VAC-02 (176.6m) VAC-03 (177.2m) VAC-04 (190m) VAC-05 (215m) VAC-06 (240.6m) Remote I/O VAT VP3 Turbo pump controller Cryo pump controller Primary pump controller VF2 Fast Valve controller Turbo pump controller TPG300 OLM Profibus gateway FO patch panel UPS TPG300 ECN3 cavern. Positions of VAC racks measured from T10 target. Z (m)

NA62 vacuum controls, F. Mateo TE-VSC-ICM Interlocks TYPENAMEDESCRIPTION INNA62.DiEnablePumpS2S3Pumping Enable for Sector 2 and 3 (if no CEDAR window rupture) IN NOT AVAILABLE!! NA62.DiEnableVentS2S3 Venting Enable of Sector 2 and 3 (if CEDAR at atmosphere pressure). CEDAR vacuum status on DIP published safety information. OUTNA62.DoAlrS2S3VacOkEnable Inside CEDAR pumping (if S2 and S3 are under vacuum) OUTNA62.DoAlrS3S4VacOkEnable GTK cooling (if S3 and S4 are under vacuum) OUTNA62.DoAlrS5HvOkEnable High Voltage on LAV (if S5 atmosphere or under high vacuum) OUTNA62.DoAlrS5RichOkEnable Inside RICH pumping (if S5 is under vacuum) OUTNA62.DoAlrS7HvOkEnable High Voltage on SAC (if S7 atmosphere or under high vacuum) 9 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM Many PLC functions have been reused from other systems (LHC): Primary groups Turbo groups New functions have been developed for: Cryo controllers Profibus gauges Specific interlocks (HW/SW) Software 10 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM PVSS SCADA application All vacuum equipment has been included in VacDB. The PVSS application was developed in WinCC OA. 11 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM Commissioning July 2014: HW commissioning & leak test of blue tube Profibus network test September-October 2014: Full pump-down with remote control system Interlocks test June 2014: Fiber optic network test. Communication with PLC master. Roughing pumps test. Communication with VRPPH controllers. Issues found and solved: bad connectors/cables, conventions mismatchs, cabling errors inside crates, profibus instabilities… November-December 2014: Documentation 12 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM Conclusions  NA62 was a challenging experiment which involved dealing with a large variety of equipment and required the collaboration of several groups and sections of CERN.  Vacuum controls were a success: robust vacuum and nominal pressures achieved in all sectors.  Interlocks are fully operational.  The planning was strictly followed and deadlines were respected.  Few things to fix: Membrane gauge transfer function correction. Add relay boxes for VAT VP-3 controllers. Extra interlocks to be implemented? (2015 technical stop). Backup primary groups to be installed in sectors 1-2. Reorganize racks cabling, etc. 13 of 14

NA62 vacuum controls, F. Mateo TE-VSC-ICM Thank you! Special thanks to: Abel / Rodrigo / Sebastien / Berthold Jenninger for support during commissioning. Sebastien / Rodrigo for PLC software development. Victor de Jesus (EN-MEF) for equipment installation. 14 of 14