1 Schedule Discussion Background & aims Major milestones & drivers Summary of important dates Project risks MICE CM26, 24-27th March, 2010.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

1 MICE Project Board Schedule and risk discussion Introduction Project Management comment Schedule considerations Adapting the schedule/reacting to circumstances.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 UKNF/MICE Oversight Committee Open session Integration of the MICE project Background & local history Progress since 2007 Schedule & planning considerations.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 UKNF/MICE OsC PM report Summary assessment of MICE Risks, pressures and worries Project management Electrical substation, accommodation Redefining the.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 MICE Project Board Schedule and milestones Reconstructing the schedule Present status Monitoring and feedback Key schedule drivers and concerns Andy.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
1 MICE-UKNF Oversight Committee MICE Project Manager Report Contents: New schedule and its implications Preparations for Steps II & III Spectrometer solenoids.
1 MICE CM28 STEP III or STEP IV? – some practicalities Andy Nichols/Tim Hayler, STFC 4 th October 2010 Considerations Step II Step III Step IV Conclusions.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.
1 PM report International & UK programmes Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
1 MICE MPB/RLSR Integration of Step IV Readiness of the major subsystems Installation sequence and schedule considerations Logistics, staffing and local.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
1 MICE CM28 Schedule & Risk Comment Schedule reconstruction and management The ‘straight to Step IV’ discussion How a schedule meeting can work Risks (and.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
MPB 31 October 2012 and FAC 15 November monitor how well we are doing in assembling step IV ! -- should deliver a ‘realsitic schedule scenario’
Paul Drumm, cm10, 27 Oct 2004 MICE Project Report Paul Drumm Collaboration Meeting 10 Rutherford Appleton Laboratory October 2004.
1 MICE PM report – status of Phase II Target update Spectrometer solenoid FC & coupling coils Schedule considerations Project accommodation & management.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
MICE VC Alain Blondel 1 1. MOM is now Victoria 2. Linda Coney is new MICE Online Group coordinator (rep Jean-Sebastien) May we held.
Muon Ionization Cooling Experiment Update 1Alan Bross AEM October 14, 2013.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
1 MICE Schedule Review no 1 Aims of review and description of review charge Motivation and external drivers Aims of the review A few of the problems Description.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
Resource Loaded Schedule and Budget Profile
Status of the MICE Construction Project
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 Schedule Discussion Background & aims Major milestones & drivers Summary of important dates Project risks MICE CM26, 24-27th March, 2010

Background & aims This is going to be difficult…….! Top level project schedule will only be amended and agreed at Collaboration meetings: –Schedule information is gathered from WP Managers at Technical Board and from others during the CM week –Then summarised at end of week, ie, now…. –Response has been generally good, enough to get going –Not sure the best way to go about it; this is a try-out – lively discussion for certain –Will cover the elements in sequence, Muon beamline first –The emphasis is on practicality and realism – I will not be pressured to promise impossible to achieve dates

 MICE Schedule as of Sept 2009 Sep-Dec 2009 (running now) STEP I Q2/Q Q > 2011 STEP II STEP IV 2011 STEP V STEP VI  2013 STEP III/III.1 Run date: Where we are today Strictly reference only!

2.1: MICE Muon Beam: Target (KL): Planning for: –May/June: next extended test with: New stator, dust catcher, clean environment –Test will be with stage 1 controller upgrade Plan to migrate controller upgrade to MLCR June Plan to complete controls upgrade project by end Dec10 Today Note, UK FY Milestone plan for resumption of On-line-offline plan required

2.1: MMB: diffuser Decay solenoid presently under repair – this is a worry But some news this week…….see later But the Muon beamline is not critical path for Step I completion Before ISIS moderator change – the ‘long shutdown’, starting August 2010 This is the important date This date depends on Spectrometer solenoid

Decay solenoid news Latest news from Matt Hills, working with Linde: Matthias has been in contact with the engineers in Switzerland and their current thought is that there is a leak on the compressor shaft seal. We discussed a couple of options: 1. Matthias is confident that, provided we clean the system further tomorrow, we could run the coldbox at relatively low risk because the coldbox 80K adsorber can handle the 2-3ppm/hour impurity rise. The blockage might reoccur, but if not, we may be able to carry on cooling the magnet. In this case, Linde would still like to arrange a further visit (probably from local agents HPC) to change the compressor shaft seal whilst the magnet is cold. This would interrupt things for 2-3 days. 2. We keep the plant shut down until HPC have the parts and an engineer available to change the shaft seal. Linde are working to see how quickly this could be done at the moment, but my guess is it would be after Easter. Assuming this was successful, we would then be looking at having the magnet available again mid to late April. Consensus that we do not do option One -Just be back where we began – might have blockage -Option two is right thing to do -Expert cover not available during Easter week But compressor was Leak-tight…….odd?

Spectrometer solenoid(s) This is easily the most important contributor to this year: –Presently magnet #2 is still cold, but with one coil open circuit after powering & training –Useful thermal balance data being gathered –Investigation soon will show if joint can be repaired thro’ access plate –If not, will have to withdraw cold mass –In that case revert to magnet #1 –Solenoid Review Committee will re-convene at April-May decision point –Will only start to discuss realistic dates after that point

Spectrometer solenoid Also required for Step II: –Need to complete definition of the joint LBL/DL solenoid controls project –Fruitful visit to LBL/Wang, a few points need clearing up –Ian Mullacrane/John Webb have list of jobs that need owners –‘Green light’ for physical work to start will be when magnet arrives at FNAL –Will be phased to coincide with delivery to RAL

Trackers Both trackers are ready –They are residing in Lab 7, R1 at RAL –But there’s a leak on one of the readout cryostats –Thought to be caused by cold weather over Christmas –Repair is planned – not thought to be a problem for any likely Step II schedule Virostek plate & Rad shutters –Virostek plate supports probably need to be remade –Rad shutter doors and rails are made, awaiting fit check –Design work on actuating mechanism complete 30 th April –Note although rad shutters not required till Step V, need to be assembled at Step II while access OK –None of the above a problem for Step II

Spectrometer Solenoid Schedule Decision point For magnet #2 Revisit schedule in light Of Review Committee This version has Magnet #1 overtaking #2

RFCC & AFC RFCC: –RF cavity project and associated hardware going very smoothly and is well on schedule –Coupling Coil contract has been signed, on schedule as promised –Detailed schedule is awaited from contractor –Discussions can start then – CM27, or maybe before…..? AFC: –Absorber #1 is effectively ready, some changes to feedthro’ required –Focus coil module ready December, 2010, some slippage, mainly due to absorber/coil module interface

RFCC Module Schedule Need to review these Dates when CC schedule received

Infrastructure/integration – T.Hayler Essentially ready in R5.2 for Step II and mostly for Step III: –Air system done - done –CCR water cooling plant & services – done –Rolling platform – installed and tested –Floor restraint beams – made and trial assembled –CCR compressor stands - made and positioned –All electrical work possible up to arrival of solenoid is done –PPS hardware – November, 2010 (deliberately delayed due to funding/staff constraints) –TOF shielding cage – at RAL, thinking about trial assembly –Step III floor plates - made and trial fitted …..But, still no clear idea of 2MVA substation upgrade plans Technical options are understood, but no financial approval by STFC – circular discussion getting nowhere….! –Puts Step IV at risk

Note about Step II integration Important as it directly influences Step II readiness –A sequence of necessarily in-series operations –That must start after the solenoid delivery –Carefully planned by Tim Hayler, Geoff Barber, John Cobb –Have never done any of it before –Several very fragile parts and assemblies –Eg, trackers & readouts –Diffuser and controls –It will take about four months and is not open to discussion/negotiation –But Step III integration plan might be reviewed in light of experience with Step II

Note about the EMR Construction going well at UNIGE –Magnetic shielding issues being understood and resolved –Interface with R5.2 infrastructure and KL stand need work –Milestone plan for EMR delivery now required for delivery to Step III

Summary of important dates Muon beamline: –Unlikely to hold up Step I completion before long shutdown Infrastructure: –Ready for Step II now, small amount of work for Step III (bolting down and testing rolling platforms) Spectrometer solenoid(s): –Plan beginning to form this week – will only start to discuss likely schedule outcomes after Review Committee, around May AFC: –Ready December 2010 RFCC: –Good news that CC contract is signed, detailed schedule awaited from contractor –RF cavity project highly unlikely to be a hold-up

Project risks Critically dependent on one delivery date this year – spectrometer solenoid Delays to Steps II & III - obvious concern for overall project 2MVA substation upgrade puts Step IV at risk and maybe Step III – must not underestimate seriousness UK project will have a problem occupying its ‘standing army’ after about mid-May –Must make best use of installation, fitting, and rigging effort: Presently geared to installation of Steps II and III on present baseline Essential to re-direct to advance critical items; e.g. liquid hydrogen delivery system –Critical for project that established and effective team is not taken apart again AN, for one, will not do this!